SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $31,285 | $31,285 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | Submit DRAFT 2011 SOW/budget to COTR | 6/1/2011 | 7/1/2011 | Concluded | Richard Golden Jr (Inactive) | 7/20/2010 2:13:53 PM | |
Description: Draft SOW and budget submitted to COTR 90 days before the end of the current contract. COTR will create a CR for data entry and notify contractor via e-mail. | |||||||
B | Suggested | Per COTR, revise/finalize the new contract package, (SOW, EC docs, budget and property inventory) | 7/1/2011 | 7/16/2011 | Concluded | Richard Golden Jr (Inactive) | 7/20/2010 2:13:53 PM |
Description: (Milestone end date: 75 days prior to end of the performance period). | |||||||
C | ASSEB | Accrual - Submit FY 10 September estimates to BPA | 8/14/2011 | 9/10/2011 | Concluded | Michael Blouin | 7/19/2010 12:23:15 PM |
Description: Provide BPA with an estimate of contract work that will occur prior to September 30 but will not be billed until October 1 or later. Generally, this should be done by September 10. | |||||||
D | DELIV | Successful Project Management | 9/30/2011 | Concluded | Michael Blouin | 7/19/2010 12:23:15 PM | |
Description: Submit next year's SOW, Budget, and Property Inventory to the BPA COTR. The SOW should include location information (latitude and longitude) for those work elements that require it. If contractor or contractor's organization takes longer than 30 days to sign the contract, the contractor will need to send this funding package to BPA more than 90 days before the end of the current contract. Contractor to interview candidates to replace key personnel, if necessary. Contractor to document candidates interviewed and outcome of hiring process. |