This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. 46273 REL 23 (04/01/2011 - 03/31/2012) | $0 | $0 | ||
Work Element Budget (Current Performance Period) | $0 | $0 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | Ensure proper Environmental Compliance is in place | 4/1/2011 | 4/2/2011 | Concluded | Joseph Connor (Inactive) | 4/14/2011 11:06:10 AM | |
Description: BPA working through sponsor will verify property environmental clearance is in place prior to any work beginning that requires environmental clearance. | |||||||
B | DELIV | Environmental Compliance requirements in place and completed. | 4/2/2011 | Concluded | Joseph Connor (Inactive) | 4/14/2011 11:06:10 AM | |
Description: BPA working with the sponsor will make sure the proper environmental compliance is in place and that activities requiring environmental clearance may proceed |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1479. Are herbicides used as part of work performed under this contract? | No | No | |||
1722. Will water craft, heavy equipment, waders, boots, or other equipment be used from outside the local watershed as part of work performed under this contract? | No | No |