1994-018-07 EXP GARFIELD CO: IMPROVE AND ENHANCE RIPARIAN HABITAT
Contract Start Date:
6/1/2013
Contract End Date:
5/31/2014
Title:
F: 157 - Collect water quality data and analyze in local lab
Description:
Data collected by local district has been used to demonstrate the effectiveness of upland and riparian practices in improving water quality and reducing the sedimentation in the stream.

The one operating ISCO was located between the Pomeroy High and Grade School. The High School was remodeled over the last year. In the remodeling process, the power source for the ISCO was eliminated. There, the ISCO is not operating at this time. It may take sometime to either restore the power or move the ISCO to another site. No data will be collected in the near future.
WE Agreement Type:
Contracted
Deliverable Specification:
When the power source is restored to the site or the ISCO moved, it will collect water samples approximately every 24 days and run through district lab for analysis of total suspended solids (TSS). Temperature, pH, and dissolved oxygen data is collected at time of sample collection and included in spreadsheet maintained by Pomeroy CD.
WSE Effective Budget:
$0
% of Total WSE Effective Budget:
0.00%
WSE Start:
06/01/2013
WSE End:
05/31/2014
WSE Completion:
WSE Progress:
Canceled
WSE ID Continued From:
n/a
WSE ID Continued To:
n/a
Finite or Recurring:
Recurring

SOWRevision Planned Updated Contractor Comments (optional) BPA Comments (optional)
Work Element Budget (Current Performance Period) $0 $0

5 Milestones
Sort Type Title Start End Status Modified By Modified Date
A EC Environmental compliance requirements complete 6/1/2013 1/31/2014 Concluded Andre L'Heureux (Inactive) 3/30/2013 8:42:52 PM
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff (completion can be based on pre-existing environmental documentation from BPA).
B Confirm Status with BPA 6/1/2013 1/31/2014 Concluded Andre L'Heureux (Inactive) 3/30/2013 8:44:13 PM
Description: Contact EC Lead, by 1/31/14 (120 days prior to end of contract period), if WE is funded/collection is resumed.
C PUBPROTOCOL Review, revise, and Publish protocol, study design, and methods in monitoringmethods.org 6/1/2013 5/31/2014 Canceled Duane Bartels 1/29/2013 12:00:28 PM
Description: The Protocol (including temporal and spatial design) and Methods for this work element are stored at monitoringmethods.org and need to be finalized (i.e., "Published" through monitoringmethods.org), preferably prior to data collection. Preparations for contract renewals must include reviewing any previously published Protocols/Methods to ensure that they are consistent with how work will be done in any subsequent contract.
D Collect water samples when ISCO sampler is restored 6/1/2013 1/31/2014 Canceled Andre L'Heureux (Inactive) 3/30/2013 8:54:19 PM
Description: Computerized ISCO water sampler is located between the Pomeroy Grade School and High School. This unit samples the water every day for 24 days. These sample bottles are collected by district personnel and analyzed at the district soil and water testing lab. The problem that has occurred over the last year is that when the high school was remodeled, they cut off the power supply to the sampler. We are trying to get the power hooked up again, but may have to move the ISCO to a different location.
E DELIV Data made available to WDOE, BPA, and other interested parties. 5/31/2014 Canceled Duane Bartels 1/29/2013 12:00:30 PM
Description: When the power source is restored to the site or the ISCO moved, it will collect water samples approximately every 24 days and run through district lab for analysis of total suspended solids (TSS). Temperature, pH, and dissolved oxygen data is collected at time of sample collection and included in spreadsheet maintained by Pomeroy CD.

Work Site ID Latitude Longitude State County Province Subbasin
28646 46.472478 -117.596766 Washington Garfield Columbia Plateau Tucannon

Primary Focal Species:
Steelhead (O. mykiss) - Snake River DPS (Threatened)
Secondary Focal Species:
Trout, Rainbow (Oncorhynchus mykiss)

Title Link
NONE - No data repository or not electronically available N/A
Study Plan Name Study Plan Owner Protocol State Sample Design Name
Water quality monitoring in the Hangman Creek Watershed to track changes in water quality over time v1.0 Stephanie Hallock Draft Collect water quality data and analyze in local lab - Pomeroy Conservation District v1.0

N/A

Title Category Subcategory Subcategory focus 1 Subcategory focus 2
Average daily water conducitivity in a stream reach Water Quality Conductivity (ID: 154) NA NA
Average pH in a stream reach Water Quality pH (ID: 158) NA NA
Average daily turbidity in a stream reach Water Quality Turbidity (ID: 161) NA NA
Average daily temperature in a stream reach Water Quality Water Temperature (ID: 162) NA NA
Water Quality Index of a stream reach Water Quality Water Quality Index (ID: 350) NA NA