This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $0 | $0 | covered under WE D |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | FinInv01 | Submit final invoice for prior contract within 90 days to facilitate contract closeout | 3/1/2014 | 5/31/2014 | Concluded | Andrew Murdoch | 1/10/2014 9:54:27 AM |
Description: Within 90 days of the last day of the PRIOR contract, the contractor shall issue a final invoice. In instances where more than 90 days is needed (e.g., because subcontractors have not invoiced), the contractor shall: 1. review records, 2. estimate all outstanding costs, and 3. provide BPA with a single, cumulative estimate of all completed, but uninvoiced work. This amount shall be emailed to FWinvoices@bpa.gov and the COTR. | |||||||
B | DraftNew | Begin drafting contract renewal documents and conduct internal review as needed | 10/1/2014 | 10/31/2014 | Concluded | Andrew Murdoch | 1/10/2014 9:54:27 AM |
Description: Your statement of work, line-item budget, and (if required) property inventory for your next contract are due to BPA at least 5 months prior to the contract start date (longer if your internal processes require more time to get the contract signed and in place prior to the start date). | |||||||
C | Submit | Submit contract renewal package (SOW, Excel budget, property inventory) to BPA COTR | 11/1/2014 | 11/30/2014 | Concluded | Andrew Murdoch | 1/10/2014 9:54:27 AM |
Description: Once your statement of work (SOW) in Pisces is complete, and you have attached your line-item budget (LIB) and property inventory (PI) (if required), click the “Submit” button on the SOW tab to notify your COTR the package is ready for review. | |||||||
D | FixCmts | Address comments and revise SOW, LIB, and PI as needed to get BPA manager approval | 12/1/2014 | 12/31/2014 | Concluded | Andrew Murdoch | 1/10/2014 9:54:27 AM |
Description: Once your COTR and his or her BPA manager have reviewed your contract renewal package and returned any comments to you, you will need to provide responses and changes as needed to achieve approval from the BPA manager, who will then forward the package to the Contracting Officer. This should be completed at least two months prior to the next contract start date, but may need to be 3 or 4 months depending on your internal processing time for contract signatures. If you have subcontracts that need to be signed prior to the contract start, it should be a minimum of 4 months. | |||||||
E | Sign&Rtrn | Return signed contract to BPA’s Contracting Officer within 30 days | 1/1/2015 | 1/31/2015 | Concluded | Andrew Murdoch | 1/10/2014 9:54:27 AM |
Description: Respond to the CO and COTR indicating any problems with the contract within 20 days, or return the signed contract to the BPA Contracting Officer (CO) within 30 days. | |||||||
F | ACCR01 | Accrual - Submit September estimate to BPA | 8/10/2014 | 9/10/2014 | Concluded | Andrew Murdoch | 1/10/2014 9:54:28 AM |
Description: Provide BPA with an estimate of contract work that will occur prior to September 30 but will not be billed until October 1 or later. Data must be input in to Pisces by September 10 (begins Aug 10, ends Sep 10). | |||||||
G | CostSh01 | Facilitate inputting Cost Share information into Pisces at the Project level | 9/30/2014 | 11/1/2014 | Concluded | Andrew Murdoch | 1/10/2014 9:54:28 AM |
Description: (c)There are multiple contractors under this project, and you are not the lead project Proponent, email federal FY Cost Share information for your contract to the lead project Proponent by Nov 1. (Milestone starts Sep. 30 and ends Nov. 15 for options a and b, and ends Nov 1 for option c) | |||||||
H | DELIV | Funding Package - Sign contract | 2/28/2015 | Concluded | Sharon Grant (Inactive) | 2/5/2014 8:06:52 AM | |
Description: Statement of Work for work beginning March 1, 2014. -- Contractor shall sign the contract and mail it back to the BPA Contracting Officer (CO). No invoices may be processed by BPA until the CO receives the signed contract. The CO shall be in receipt of the contractor-signed copy of the contract before the end of the current contract. September Accruals BiOp / Metrics: -- Enter Actual metrics for each Work Element that requires metrics as they are completed (designated by the deliverable milestone being marked complete). Location Data -- No later than the end of the performance period, provide at least one latitude and longitude describing the physical location of each Work Element requiring location information. -- Any location information that changes after the contract is issued should be edited as soon as it is known. This includes new locations where before there were none. |