1. 56662 REL 48 (03/01/2014 - 04/30/2015) | $10,392 | $7,813 | ||
Work Element Budget (Current Performance Period) | $10,392 | $7,813 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | DraftNew | Begin drafting contract renewal documents and conduct internal review as needed | 10/1/2014 | 12/15/2014 | Concluded | David Byrnes (Inactive) | 12/5/2014 6:04:52 PM |
Description: Your statement of work, line-item budget, and (if required) property inventory for your next contract are due to BPA at least 5 months prior to the contract start date (longer if your internal processes require more time to get the contract signed and in place prior to the start date). | |||||||
B | Submit | Submit contract renewal package (SOW, Excel budget, property inventory) to BPA COTR | 11/1/2014 | 1/15/2015 | Concluded | David Byrnes (Inactive) | 12/5/2014 6:04:52 PM |
Description: Once your statement of work (SOW) in Pisces is complete, and you have attached your line-item budget (LIB) and property inventory (PI) (if required), click the “Submit” button on the SOW tab to notify your COTR the package is ready for review. | |||||||
C | FixCmts | Address comments and revise SOW, LIB, and PI as needed to get BPA manager approval | 12/1/2014 | 2/10/2015 | Concluded | David Byrnes (Inactive) | 12/5/2014 6:04:53 PM |
Description: Once your COTR and his or her BPA manager have reviewed your contract renewal package and returned any comments to you, you will need to provide responses and changes as needed to achieve approval from the BPA manager, who will then forward the package to the Contracting Officer. This should be completed at least two months prior to the next contract start date, but may need to be 3 or 4 months depending on your internal processing time for contract signatures. If you have subcontracts that need to be signed prior to the contract start, it should be a minimum of 4 months. | |||||||
D | Sign&Rtrn | Return signed contract to BPA’s Contracting Officer within 30 days | 2/1/2015 | 3/15/2015 | Concluded | David Byrnes (Inactive) | 12/5/2014 6:04:53 PM |
Description: Respond to the CO and COTR indicating any problems with the contract within 20 days, or return the signed contract to the BPA Contracting Officer (CO) within 30 days. | |||||||
E | FinInv01 | Submit final invoice for prior contract within 90 days to facilitate contract closeout | 3/1/2014 | 7/31/2014 | Concluded | Sharon Grant (Inactive) | 12/5/2014 10:50:26 AM |
Description: Within 90 days of the last day of the PRIOR contract, the contractor shall issue a final invoice. In instances where more than 90 days is needed (e.g., because subcontractors have not invoiced), the contractor shall: 1. review records, 2. estimate all outstanding costs, and 3. provide BPA with a single, cumulative estimate of all completed, but uninvoiced work. This amount shall be emailed to FWinvoices@bpa.gov and the COTR. | |||||||
F | ACCR01 | Accrual - Submit September estimate to BPA | 8/10/2014 | 9/10/2014 | Concluded | Sharon Grant (Inactive) | 12/5/2014 10:50:26 AM |
Description: Provide BPA with an estimate of contract work that will occur prior to September 30 but will not be billed until October 1 or later. Data must be input in to Pisces by September 10 (begins Aug 10, ends Sep 10). | |||||||
G | CostSh01 | Facilitate inputting Cost Share information into Pisces at the Project level | 9/30/2014 | 11/1/2014 | Concluded | Sharon Grant (Inactive) | 12/5/2014 10:50:26 AM |
Description: If there are multiple contractors under this project, and you are not the lead project Proponent, email federal FY Cost Share information for your contract to the lead project Proponent by Nov 1. (Milestone starts Sep. 30 and ends Nov. 15 for options a and b, and ends Nov 1 for option c) | |||||||
H | Manage and Administer Contract Terms and Conditions | 3/1/2014 | 4/30/2015 | Concluded | David Byrnes (Inactive) | 1/7/2015 3:44:57 PM | |
Description: Manage and administer the terms and conditions of this contract. | |||||||
I | DELIV | Funding Package - Submit draft to COTR | 2/27/2015 | Concluded | David Byrnes (Inactive) | 12/5/2014 6:04:54 PM | |
Description: In Pisces, enter a new statement of work for the period Feb 1, 2014 through Jan 31, 2015 (if applicable). Per BPA contracting requirements, the SOW and all associated documents (budget, spending plan, property inventory, etc.), must be submitted a minimum of 90 days prior to the expiration of the current contract. |