This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. 65089 (02/15/2014 - 02/14/2015) | $221,422 | $266,823 | ||
Work Element Budget (Current Performance Period) | $266,823 | $266,823 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | ACCR01 | Accrual - Submit September estimate to BPA | 8/10/2014 | 9/10/2014 | Concluded | David Byrnes (Inactive) | 4/27/2014 9:01:44 PM |
Description: Provide BPA with an estimate of contract work that will occur prior to September 30 but will not be billed until October 1 or later. Data must be input in to Pisces by September 10 (begins Aug 10, ends Sep 10). | |||||||
B | CostSh01 | Facilitate inputting Cost Share information into Pisces at the Project level | 9/30/2014 | 11/1/2014 | Concluded | David Byrnes (Inactive) | 4/27/2014 9:01:44 PM |
Description: If there are multiple contractors under this project, and you are not the lead project Proponent, email federal FY Cost Share information for your contract to the lead project Proponent by Nov 1. (Milestone starts Sep. 30 and ends Nov. 15 for options a and b, and ends Nov 1 for option c) | |||||||
C | Solicit estimates for bulk purchase of equipment | 2/15/2014 | 5/31/2014 | Concluded | David Byrnes (Inactive) | 4/27/2014 9:01:44 PM | |
Description: Solicit estimates for the bulk purchase of total stations suitable for conducting CHaMP habitat surveys. | |||||||
D | Purchase equipment | 2/15/2014 | 8/31/2014 | Concluded | David Byrnes (Inactive) | 4/27/2014 9:01:44 PM | |
Description: Purchase necessary equipment (in addition to total station replacement) for 2014 field season for all watersheds where CHaMP is being implemented. | |||||||
E | Identify Qualified Vendors for purchasing replacement Total Stations | 2/15/2014 | 3/12/2014 | Concluded | David Byrnes (Inactive) | 4/27/2014 9:01:44 PM | |
Description: To prepare for the planned replacement of 13 Nikon total stations, identify three or more qualified vendors from whom to request bids. | |||||||
F | Request total station bids, review and evaluat results and in coord with BPA to select the Best Buy | 3/13/2014 | 4/7/2014 | Concluded | David Byrnes (Inactive) | 4/27/2014 9:01:44 PM | |
Description: Contact three or more vendors to asses price packaging for Nikon exchange for purchase new Topcon total stations. | |||||||
G | Complete purchase of replacement total stations | 4/8/2014 | 5/15/2014 | Concluded | David Byrnes (Inactive) | 4/27/2014 9:01:44 PM | |
Description: Coordinate with BPA in making final vendor selection of Topcon instruments and initiate and complete the exchange of Nikons and the purchase of replacement Topcons. | |||||||
H | Inventory equipment | 2/15/2014 | 1/31/2015 | Concluded | David Byrnes (Inactive) | 4/27/2014 9:01:44 PM | |
Description: Create an inventory of total stations purchased for CHaMP, including manufacturer, model number, serial number, date of purchase. This inventory should also be updated to reflect the date and to which collaborator the equipment is signed out to and the expected date of return. | |||||||
I | DELIV | All administrative tasks fulfilled with timely quality products | 1/31/2015 | Concluded | David Byrnes (Inactive) | 4/27/2014 9:01:44 PM | |
Description: All administrative tasks shall be fulfilled on time and with quality products. Timely responses to requests for more information are required. Proactive communication between the contractor and BPA's Contracting Officer (CO) and Contracting Officer Technical Representative (COTR) is required if a significant lag in scheduled delivery is expected. |