SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $30,000 | $31,125 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 5/1/2014 | 5/2/2014 | Concluded | Nick Bean | 2/4/2014 12:13:21 PM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff (completion can be based on pre-existing environmental documentation from BPA). | |||||||
B | Complete electrofishing treatment in Trib 1 | 9/1/2014 | 10/31/2014 | Concluded | Nick Bean | 2/5/2014 4:55:32 PM | |
Description: A three person crew operating a Smith Root backpack electrofishing unit will complete a minimum of 2 successive passes in Trib 1 using multiple pass depletion techniques (Murphy and Willis 1996, Heimbuch et al. 1997) in continuous 100m block-netted sections. Electrofishing will start at the culvert barrier located near the mouth of the stream and end at a point where no fish are present. Brook trout will be removed and WCT will be returned to the creek downstream of the capture location, no more than 100m from the collection location. The first 100 fish of each species are weighed to the nearest 0.1 gram, measured (total length) to the nearest mm and checked for previous capture identifiers (PIT Tags, fin clips). The treatment will be completed prior to brook trout spawning (generally mid September). | |||||||
C | DELIV | One brook trout removal treatment completed in Trib 1 | 10/31/2014 | Concluded | Nick Bean | 2/4/2014 12:11:53 PM | |
Description: One brook trout treatment will be completed in the fish bearing stream channel section of Trib 1 (approximately 2 Km). A treatment is comprised of a minimum of two complete passes back to back using electrofishing gear, in continuous block netted 100 m sections. BKT will be removed from the stream and WCT will be returned no more than 100m from capture location. |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1770. Targeted animal | Trout, Brook (Salvelinus fontinalis) | Trout, Brook (Salvelinus fontinalis) |
Work Site ID | Latitude | Longitude | State | County | Province | Subbasin |
---|---|---|---|---|---|---|
83184 | 48.657259 | -117.237983 | Washington | Pend Oreille | Intermountain | Pend Oreille |