This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $2,405 | $2,405 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | Administer subcontractor paperwork | 1/1/2014 | 3/31/2014 | Concluded | Andre L'Heureux (Inactive) | 11/23/2013 3:36:24 PM | |
Description: Read all BPA contract terms and conditions include all contract clauses that are required to flow down into subcontracts in preparation for subcontract negotiation. Upload confidential copy of subcontracts to Pisces. Upload is due 30 days from date of subcontractor signature. Email the link to the COTR after upload. | |||||||
B | ACCR01 | Accrual - Submit September estimate to BPA | 8/11/2014 | 9/10/2014 | Concluded | Andre L'Heureux (Inactive) | 11/23/2013 3:19:42 PM |
Description: Provide BPA with an estimate of contract work that will occur prior to September 30 but will not be billed until October 1 or later. Data must be input in to Pisces by September 10 (begins Aug 10, ends Sep 10). | |||||||
C | CostSh01 | Input Cost-Share information into Pisces at the Project level | 10/1/2014 | 11/15/2014 | Concluded | Andre L'Heureux (Inactive) | 11/23/2013 3:19:42 PM |
Description: Enter previous federal fiscal year Cost-Share information on the Project’s Cost Share tab (project-level view in Pisces) by Nov 15. | |||||||
D | DraftNew | Begin drafting contract documents for the PA-24 (Build) and conduct review as needed (SRSRB) | 8/18/2014 | 9/30/2014 | Concluded | Andre L'Heureux (Inactive) | 11/23/2013 3:36:24 PM |
Description: Your statement of work, line-item budget, and (if required) property inventory for a subsequent contract (to implement the PA-24 design) are due to BPA at least 5 months prior to the contract start date (longer if your internal processes require more time to get the contract signed and in place prior to the start date). | |||||||
E | Submit | Submit contract package (SOW and Excel budget) to BPA COTR | 9/15/2014 | 10/31/2014 | Concluded | Andre L'Heureux (Inactive) | 11/23/2013 3:44:21 PM |
Description: Once your statement of work (SOW) in Pisces is complete, and you have attached your line-item budget (LIB) and property inventory (PI) (if required), click the “Submit” button on the SOW tab to notify your COTR the package is ready for review. | |||||||
F | FixCmts | Address comments and revise SOW and LIB as needed to get BPA manager approval | 10/1/2014 | 10/31/2014 | Concluded | Andre L'Heureux (Inactive) | 11/23/2013 3:44:21 PM |
Description: Once your COTR and his or her BPA manager have reviewed your contract renewal package and returned any comments to you, you will need to provide responses and changes as needed to achieve approval from the BPA manager, who will then forward the package to the Contracting Officer. This should be completed at least two months prior to the next contract start date, but may need to be 3 or 4 months depending on your internal processing time for contract signatures. If you have subcontracts that need to be signed prior to the contract start, it should be a minimum of 4 months. | |||||||
G | Sign&Rtrn | Return signed contract to BPA’s Contracting Officer within 30 days | 10/13/2014 | 11/14/2014 | Concluded | Andre L'Heureux (Inactive) | 11/23/2013 3:44:21 PM |
Description: Respond to the CO and COTR indicating any problems with the contract within 20 days, or return the signed contract to the BPA Contracting Officer (CO) within 30 days. | |||||||
H | DELIV | Effective implementation management and timely contract administration | 12/31/2014 | Concluded | Andre L'Heureux (Inactive) | 11/23/2013 3:15:28 PM | |
Description: All administrative tasks shall be fulfilled on time and with quality products. Timely responses to requests for more information are required. Proactive communication between the contractor and BPA's Contracting Officer (CO) and Contracting Officer Technical Representative (COTR) is required if a significant lag in scheduled delivery is expected. |