Show new navigation
On
Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program

Summary

RSS Feed for updates to BOG Change Request #329 for Project 2005-009-00 Follow this via RSS feed. Help setting up RSS feeds?
BOG Change Request #329 for Project 2005-009-00

BOG Change Request #329 (Within Year) for Project 2005-009-00


Author Information:   Christine Read - Bonneville Power Administration
Primary Contact Information:  


Request Status: BPA Approved
Scheduled for Meeting: Unscheduled
Project Number:2005-009-00
Project Name:Twisp Side Channel
Proponents:Methow Salmon Recovery Foundation
BPA Project Manager: Cecilia Brown (Inactive)
  
Author: Christine Read
Requesting changes to:Budget

Explanation of Need:

IMPORTED FROM CBFWA MODIFICATIONS DATABASE ON 01-07-2010

"Proposed action achieve the objective(s)"

Phase II Improvements will include:

?creating resting areas by constructing small rock weirs, placing woody debris and boulders, creating meander, constructing pools and runs, revegetating for shade, and recruitment of woody debris

?increasing flood plain width by deepening some areas and creating a more typical creek shape

?removing culvert barriers from ponds 2 and 3

?restoring free access for wild fish to and through ponds 1, 2, 3, and 4

?restoring year-round surface water flow throughout the isolated side channel and pond complex.

Phase II is scheduled for construction this summer and will include open channels with control structures between Pond 1 and Pond 2 and between Pond 2 and Pond 3. Other improvements include a metal control structure between Pond 5 and Twisp River on the existing channel to allow control over fish passage into the site.

The channels between the ponds and the channel back to the river will be sized for a flow of 2 to 6 CFS. Average width of the new channel will be less than 5 feet. The average change in elevation between the ponds is about 3 feet which requires 4 ? 5 drop structures in each channel with a 0.8 foot drop at each structure or less. The rock drops will be typical Rosgen type vortex weirs using rocks at least 2 foot in diameter. A total of 14 rocks will be required for each structure which includes a base rock buried beneath the upper rock for stability. The first channel between Ponds 1 and 2 is about 115 feet in length and will require one 30-inch diameter HDPE culvert underneath the access road to the site. The second channel between Pond 2 and Pond 3 is about 90 feet in length which requires that the rock structures be about 30 feet apart. A very small piece of geotextile liner is used on each of the rock structures to assure that low flows still provide adequate fish passage. No headgates or other structures will be used to control or stop flow between ponds. The channels will accept any overflow from the pond.

The metal control structure between pond 5 and the Twisp River will be constructed of ?? steel plate and will have a low flow notch that can be closed off with stoplogs to raise the water surface and create a passage barrier at certain times of the year when it is not desirable to have fish passage into the pond system. For the most part, this structure will be used to prevent native fish and especially Bulltrout from interacting with hatchery fish being reared in the pond. The height of the structure above the streambed will be about 4 feet. Large rocks will be used around the edges of the structure to prevent erosion of the banks around the structure.

The banks of the constructed channels will be lined with sod cut from the area to stabilize the channels. Additional revegetation will be completed in the disturbed area using native plants and shrubs. The channel base will be lined with sized gravels suitable for spawning. Gravels will be of sufficient depth to deter encroachment of canary reed grass, which is prevalent in the lower Twisp River, from establishment.

"Is the situation the result of a catastrophic event that occurred within the existing location?"

No

"Has a habitat/population/mechanical/structural dilemma developed in the proposed study location since the contract was signed with BPA?"

Yes

"Budget Impact"

$39,851.00

Plan to proceed if request is denied:

"Provide explanations as to why the following alternative funding solutions are not feasible and will jeopardize the project:"

"Reducing existing scope of project"

The project scope has been reduced as far as feasible to meet project objectives of fish passage up and down stream through the side channel habitat.

The remaining work element represent the final work elements necessary to reconnect the sidechannel with e Twisp River at he lower end.

Additional private funding has been secured for al revegetation and supplementation element costs.

"Deferral of existing work elements to a later date:"

The completion of Phase 1 work elements this past year provided gravity flow through the upper portion of the side channel which currently must be screened to prevent fish entrapment in the uppermost side channel ponds. Removal of the final perched culverts and construction of open - channels will remove fish barriers and allow for removal of the upper diversion screen.

This action will allow year round access by all listed fish species for rearing and over-wintering purposes.

Deferral of the work to a later period will likely result in increased construction costs and will certainly result in increased labor costs associated with maintain fish access though the site.

Please explain any NEW cost share associated with this request:

None

 

Expense Budget Summary

Fiscal Year Working Budget Within Year Adjustments Reschedule
from FY
Reschedule
to FY
Potential New
Working Budget
2006 $39,851 +
$39,851
+
<none>
+
<none>
=
$79,702
__________ __________ __________
$39,851
$0
$0


Fiscal Year Account Type Adjustment Adjustment Type
2006 Expense $39,851 Within-Year

View Budget Transfers for this project


Date Time Type From To By
4/5/2006 12:00 AM Status BPA Approved <System>

Go To Project Overview for Project 2005-009-00: Twisp Side Channel

Project Number:
2005-009-00
Title:
Twisp Side Channel
Summary:
See contract summary
Proposer:
None
Proponent Orgs:
Methow Salmon Recovery Foundation (Non-Profit)
Starting FY:
2005
Ending FY:
2010
Stage:
Area:
Province Subbasin %
Columbia Cascade Methow 100.00%
Purpose:
Habitat
Emphasis:
Restoration/Protection
Focal Species:
Chinook - Upper Columbia River Spring ESU
Chinook - Upper Columbia River Summer/Fall ESU
Steelhead - Upper Columbia River DPS
Trout, Brook
Trout, Bull
Trout, Rainbow
Whitefish, Mountain
Species Benefit:
Anadromous: 100.0%   Resident: 0.0%   Wildlife: 0.0%
Tags:
None
Special:
None
BiOp Association:
None

Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

To see more detailed project budget information, please visit the "Project Budget" page

No Decided Budget Transfers

Pending Budget Decision?  No


Actual Project Cost Share

Current Fiscal Year — 2025
Cost Share Partner Total Proposed Contribution Total Confirmed Contribution
There are no project cost share contributions to show.
Previous Fiscal Years
Fiscal Year Total Contributions % of Budget
There are no cost share summaries to display from previous years.

Contracts

The table below contains contracts with the following statuses: Active, Closed, Complete, History, Issued.
* "Total Contracted Amount" column includes contracted amount from both capital and expense components of the contract.
Expense Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
24674 SOW Methow Salmon Recovery Foundation 200500900 EXP TWISP SIDE CHANNEL History $81,568 9/20/2005 - 8/31/2006
30075 SOW Methow Salmon Recovery Foundation 200500900 EXP TWISP SIDE CHANNEL PHASE 2 History $39,828 10/20/2006 - 9/30/2007



Annual Progress Reports
Expected (since FY2004):1
Completed:1
On time:1
Status Reports
Completed:9
On time:2
Avg Days Late:54

                Count of Contract Deliverables
Earliest Contract Subsequent Contracts Title Contractor Earliest Start Latest End Latest Status Accepted Reports Complete Green Yellow Red Total % Green and Complete Canceled
24674 30075 200500900 EXP TWISP SIDE CHANNEL PHASE 2 Methow Salmon Recovery Foundation 09/20/2005 09/30/2007 History 9 6 0 0 0 6 100.00% 1
Project Totals 9 6 0 0 0 6 100.00% 1


The table content is updated frequently and thus contains more recent information than what was in the original proposal reviewed by ISRP and Council.

No assessments are available for this project.
Project Relationships: None