Show new navigation
On
Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program

Environmental Compliance Summary

Contract 16522: PI 200306300 REPRO SUCCESS ABERNATHY CREEK
Viewing 27 of 27 Work Statement Elements
Sort
WE ID
WE Title
EC Required
WE Start
WE End
NEPA
Public Involvement
NOAA
USFWS
NHPA
Has Provisions
Inadvertent Discovery
Completed
A63Rearing 20,000 F1 steelhead for release into Abernathy CreekYes01/01/200505/15/2005NoNoNoNoNoNoNo
B158Mark/tag all pre-smolt F1 yearlings prior to release from AFTCYes04/01/200505/31/2005NoNoNoNoNoNoNo
C176Release 20,000 F1 steelhead yearlings each year into Abernathy CreekYes04/01/200505/15/2005NoNoNoNoNoNoNo
D157Estimating annual steelhead, cutthroat, and coho smolt out migration in Abernathy, Germany, and MYes04/01/200505/31/2005NoNoNoNoNoNoNo
E157Monitor changes in physiological status of HOR steelhead at Abernathy AFTCYes02/01/200505/31/2005NoNoNoNoNoNoNo
F157Collect three, stratified, random samples of 35 HOR and 35 NOR steelhead smolts from the downstreYes04/01/200505/31/2005NoNoNoNoNoNoNo
G157Compare morphological parameters, physiological parameters, and smolt status between HOR and NOR Yes06/01/200509/30/2005NoNoNoNoNoNoNo
H19Maintain remote PIT-tag interrogation systemNo01/01/200512/31/2005NoNoNoNoNoNoNo
I158PIT-tag steelhead and cutthroat trout within Abernathy Creek Yes08/01/200510/31/2005NoNoNoNoNoNoNo
J159Use the Stream width PIT-tag Interrogation System (SPIS) installed in Abernathy Creek (BPA ProjeNo04/01/200509/30/2005NoNoNoNoNoNoNo
K157Estimate residualism and evaluate ecological impacts by in-stream snorkel surveys and PIT packinYes04/01/200509/30/2005NoNoNoNoNoNoNo
L157Estimate allele frequencies for each brood year of yearlings released from the AFTCYes05/01/200509/30/2005NoNoNoNoNoNoNo
M66Determine the total number of NOR adult steelhead, cutthroat trout, and coho migrating upstream Yes01/01/200512/31/2005NoNoNoNoNoNoNo
N66Estimate smolt-to adult return rates and total number of adult returns of HOR steelhead releasedYes01/01/200512/31/2005NoNoNoNoNoNoNo
O66Pass NOR and HOR adult steelhead upstream of AFTC Yes01/01/200506/01/2005NoNoNoNoNoNoNo
P64Develop a genetically integrated broodstockYes01/01/200506/30/2005NoNoNoNoNoNoNo
Q176Spawn adults and cull each F2 full-sib familyYes02/01/200506/30/2005NoNoNoNoNoNoNo