A | 185 | Periodic Status Reports for BPA | No | 07/01/2011 | 09/30/2014 | Yes | No | No | No | No | No | No | 04/01/2010 |
B | 100 | Construction Management General Requirements - | No | 02/01/2011 | 06/30/2013 | Yes | No | No | No | No | No | No | 02/01/2011 |
C | 100 | Construction Management Specific Requirements - | No | 02/01/2011 | 06/30/2013 | Yes | No | No | No | No | No | No | 02/01/2011 |
D | 119 | Submit Required Budget and Scope information | No | 03/01/2011 | 06/30/2013 | Yes | No | No | No | No | No | No | 02/01/2011 |
E | 98 | Provide Contractor Access to Dam | Yes | 10/03/2011 | 06/30/2013 | Yes | No | No | No | No | No | No | 02/01/2011 |
F | 98 | Provide for additional security guard | Yes | 09/01/2011 | 06/30/2013 | Yes | No | No | No | No | No | No | 02/01/2011 |
G | 98 | Construct trail adjacent to road and hatchery site | Yes | 07/16/2012 | 09/30/2014 | Yes | No | No | No | No | No | No | 07/20/2012 |
H | 165 | Provide NEPA compliance documentation | No | 07/23/2012 | 07/27/2012 | Yes | No | No | No | No | No | No | 02/01/2011 |
I | 132 | Submit Progress Report not required | No | 03/31/2013 | Yes | No | No | No | No | No | No | 02/01/2011 |