Province | Subbasin | % |
---|---|---|
Columbia Cascade | Okanogan | 100.00% |
Previous: | Next: |
---|---|
n/a |
* Expenditures data includes accruals and are based on data through 31-Mar-2025.
A | 130367 | 185 | Produce CBFish Status Report | Periodic Status Reports for BPA | Provide timely input to BPA for completion of quarterly status update on the work elements and milestones in this scope of work. | $1,000 | 0.10% | 07/01/2011 | 09/30/2014 |
B | 130368 | 100 | Construction Management | Construction Management General Requirements - | COE responsibilities for construction inspection and coordination of critical issues of specific areas where COE has responsibilities. This work element covers Personnel costs for various USACE staff providing technical oversight to this portion of the work. | $229,134 | 23.68% | 02/01/2011 | 06/30/2013 |
C | 130369 | 100 | Construction Management | Construction Management Specific Requirements - | Provide effective coordination, communication and construction inspection per specific agreements with BPA This work element includes travel for staff as needed. | $300,000 | 31.00% | 02/01/2011 | 06/30/2013 |
D | 130370 | 119 | Manage and Administer Projects | Submit Required Budget and Scope information | Submit Accruals and IPACs in a timely manner. | $0 | 0.00% | 03/01/2011 | 06/30/2013 |
E | 130371 | 98 | Other | Provide Contractor Access to Dam | Provide appropriate paperwork for timely processing of background checks and clearances for contractors to enter and work in and on the dam. | $200,000 | 20.66% | 10/03/2011 | 06/30/2013 |
F | 130372 | 98 | Other | Provide for additional security guard | Once Work Plans are in Place Governing construction of the reservoir water supply features the USACE will provide for a contract security guard to aid in contractors less time consuming access to the dam. | $116,640 | 12.05% | 09/01/2011 | 06/30/2013 |
G | 130373 | 98 | Other | Construct trail adjacent to road and hatchery site | Subcontractor to perform all work required to construct a trail leading from the Project’s “Information and Rest Area” to a connecting point with the Fish Hatchery. | $121,056 | 12.51% | 07/16/2012 | 09/30/2014 |
H | 130374 | 165 | Produce Environmental Compliance Documentation | Provide NEPA compliance documentation | Provide appropriate Environmental compliance documents | $0 | 0.00% | 07/23/2012 | 07/27/2012 |
I | 130375 | 132 | Produce Progress (Annual) Report | Submit Progress Report not required | NA - not required. | $0 | 0.00% | 03/31/2013 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Construction coordination & inspection services provided by COE staff as delineated in budget. | B: 100. Construction Management General Requirements - | 06/30/2013 | 03/31/2013 | |
Construction management services & requirements fulfilled & complete per contractual requirements | C: 100. Construction Management Specific Requirements - | 06/30/2013 | 03/31/2013 | |
Accruals and IPACs | D: 119. Submit Required Budget and Scope information | 03/01/2012 | 03/01/2012 | |
USACE Provide access to the dam construction | E: 98. Provide Contractor Access to Dam | 06/30/2013 | 03/31/2013 | |
Provide for Subcontract security guard | F: 98. Provide for additional security guard | 06/30/2013 | 03/31/2013 | |
Construct Trail | G: 98. Construct trail adjacent to road and hatchery site | 09/30/2014 | 06/30/2014 | |
Provide proof of completion of Environmental Compliance | H: 165. Provide NEPA compliance documentation | 07/27/2012 | 07/27/2012 | |
Progress Report not required | I: 132. Submit Progress Report not required | 03/31/2013 | 03/31/2013 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 04/01/2010 | ||||||
B | 100 | Construction Management General Requirements - | 02/01/2011 | ||||||
C | 100 | Construction Management Specific Requirements - | 02/01/2011 | ||||||
D | 119 | Submit Required Budget and Scope information | 02/01/2011 | ||||||
E | 98 | Provide Contractor Access to Dam | 02/01/2011 | ||||||
F | 98 | Provide for additional security guard | 02/01/2011 | ||||||
G | 98 | Construct trail adjacent to road and hatchery site | 07/20/2012 | ||||||
H | 165 | Provide NEPA compliance documentation | 02/01/2011 | ||||||
I | 132 | Submit Progress Report not required | 02/01/2011 |