Milestones Summary

Contract 26434: 200301700 CHAR CHANNEL & RIPARIAN HABITAT QUAL - WENATCHEE WDOE
Viewing 29 of 29 Milestones
Sort Order
WE ID
Work Element Name
Title
Description
Sort
Type
Title
Start
End
Status
Modified By
Modified Date
A165Produce Environmental Compliance DocumentationEnsure existing compliance is adequate for next seasonReview and evaluate existing NEPA compliance / permits to ensure coverage is adequate for any work to be performed during the next season (if applicable). If work will change significantly, inform BPA EC Lead (see Contact list) and determine next steps so that compliance will be assured no later than the start of the next field season.ADELIVNEPA Compliance Review 02/28/2007Concluded 02/22/2006 7:04 AM
B157Collect/Generate/Validate Field and Lab DataStream Habitat SurveysConduct single habitat survey at each of 50 randomly selected stream sites in the Wenatchee basin as identified by the Regional Tech Team (RTT) and NOAA Fisheries; reviewed by the U.S. Forest Service and the Chelan County Conservation District.A Environmental compliance requirements complete03/01/200603/14/2006Concluded 02/22/2006 7:04 AM
B157Collect/Generate/Validate Field and Lab DataStream Habitat SurveysConduct single habitat survey at each of 50 randomly selected stream sites in the Wenatchee basin as identified by the Regional Tech Team (RTT) and NOAA Fisheries; reviewed by the U.S. Forest Service and the Chelan County Conservation District.B Field preparation03/15/200606/15/2006Concluded 02/22/2006 7:04 AM
B157Collect/Generate/Validate Field and Lab DataStream Habitat SurveysConduct single habitat survey at each of 50 randomly selected stream sites in the Wenatchee basin as identified by the Regional Tech Team (RTT) and NOAA Fisheries; reviewed by the U.S. Forest Service and the Chelan County Conservation District.C Conduct Site surveys07/01/200609/30/2006Concluded 02/22/2006 7:04 AM
B157Collect/Generate/Validate Field and Lab DataStream Habitat SurveysConduct single habitat survey at each of 50 randomly selected stream sites in the Wenatchee basin as identified by the Regional Tech Team (RTT) and NOAA Fisheries; reviewed by the U.S. Forest Service and the Chelan County Conservation District.D Enter and review data collected07/15/200611/17/2006Concluded 02/22/2006 7:04 AM
B157Collect/Generate/Validate Field and Lab DataStream Habitat SurveysConduct single habitat survey at each of 50 randomly selected stream sites in the Wenatchee basin as identified by the Regional Tech Team (RTT) and NOAA Fisheries; reviewed by the U.S. Forest Service and the Chelan County Conservation District.EDELIVSubmission of site sampled data (see specs) 11/17/2006ConcludedG McClintock (Inactive)02/28/2006 11:15 AM
C119Manage and Administer ProjectsCharacterize Riparian Habitat Quality - Wenatchee SubbasinCovers project management and administrative work related to the contract excluding environmental compliance.A Prepare FY06 Mid-year accrual estimate05/28/200606/30/2006CanceledGerald McClintock (Inactive)06/13/2006 9:16 AM
C119Manage and Administer ProjectsCharacterize Riparian Habitat Quality - Wenatchee SubbasinCovers project management and administrative work related to the contract excluding environmental compliance.B Prepare FY06 Year-end accrual estimate08/15/200609/30/2006Concluded 03/22/2006 5:32 PM
C119Manage and Administer ProjectsCharacterize Riparian Habitat Quality - Wenatchee SubbasinCovers project management and administrative work related to the contract excluding environmental compliance.C Prepare BioOp Report elements10/01/200612/28/2006Concluded 03/22/2006 5:32 PM
C119Manage and Administer ProjectsCharacterize Riparian Habitat Quality - Wenatchee SubbasinCovers project management and administrative work related to the contract excluding environmental compliance.DFPCIRFunding Package - Conduct internal review (e.g., Supervisor or Interagency)11/01/200611/30/2006Concluded 03/22/2006 5:32 PM
C119Manage and Administer ProjectsCharacterize Riparian Habitat Quality - Wenatchee SubbasinCovers project management and administrative work related to the contract excluding environmental compliance.E Prepare FY07 SOW & Budget12/01/200601/15/2007Concluded 03/22/2006 5:32 PM
C119Manage and Administer ProjectsCharacterize Riparian Habitat Quality - Wenatchee SubbasinCovers project management and administrative work related to the contract excluding environmental compliance.F Prepare FY07 SOW & Budget12/01/200601/15/2007CanceledGerald McClintock (Inactive)05/15/2006 10:05 AM
C119Manage and Administer ProjectsCharacterize Riparian Habitat Quality - Wenatchee SubbasinCovers project management and administrative work related to the contract excluding environmental compliance.GDELIVFunding Package - Submit draft to COTR 01/31/2007Concluded 03/22/2006 5:32 PM
D132Produce Progress (Annual) ReportSubmit Annual Report to NOAA FisheriesProduce an annual report for the period January 1, 2006 through December 31, 2006 per the specifications listed, and submit to NOAA Fisheries. A copy will be submitted to the BPA COTR as well.A Submit Draft Annual report01/01/200701/15/2007Concluded 02/22/2006 7:04 AM
D132Produce Progress (Annual) ReportSubmit Annual Report to NOAA FisheriesProduce an annual report for the period January 1, 2006 through December 31, 2006 per the specifications listed, and submit to NOAA Fisheries. A copy will be submitted to the BPA COTR as well.B Receive Draft report comments02/01/200702/15/2007Concluded 02/22/2006 7:04 AM
D132Produce Progress (Annual) ReportSubmit Annual Report to NOAA FisheriesProduce an annual report for the period January 1, 2006 through December 31, 2006 per the specifications listed, and submit to NOAA Fisheries. A copy will be submitted to the BPA COTR as well.C Revise Draft Annual report per comments02/15/200702/28/2007Concluded 02/22/2006 7:04 AM
D132Produce Progress (Annual) ReportSubmit Annual Report to NOAA FisheriesProduce an annual report for the period January 1, 2006 through December 31, 2006 per the specifications listed, and submit to NOAA Fisheries. A copy will be submitted to the BPA COTR as well.DDELIVFinal 2006 Annual Report submitted to NOAA Fisheries 02/28/2007Concluded 02/22/2006 7:04 AM