Milestones Summary

Contract 64187: 2003-017-00 EXP ISEMP -USFWS ENTIAT R FISHERIES EFFECT. M&E 2014
Viewing 69 of 69 Milestones
Sort Order
WE ID
Work Element Name
Title
Description
Sort
Type
Title
Start
End
Status
Modified By
Modified Date
A185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.ASRFeb-Jun 2014 (2/1/2014 - 6/30/2014)07/01/201407/15/2014ConcludedSharon Grant (Inactive)05/16/2013 12:00 PM
A185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.BSRJul-Sep 2014 (7/1/2014 - 9/30/2014)10/01/201410/15/2014ConcludedSharon Grant (Inactive)05/16/2013 12:00 PM
A185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.CSROct-Dec 2014 (10/1/2014 - 12/31/2014)01/01/201501/15/2015ConcludedSharon Grant (Inactive)05/16/2013 12:00 PM
A185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.DSRFinal Jan 2015 (1/1/2015 - 1/31/2015)01/17/201501/31/2015ConcludedSharon Grant (Inactive)05/16/2013 12:00 PM
B119Manage and Administer ProjectsOverall Project ManagementManage on-the-ground efforts. Also covers administrative work in support of on-the-ground efforts and in support of BPA's programmatic requirements such as metric reporting, financial reporting (e.g., accruals), and development of an SOW package (includes draft SOW, budget, spending plan, and property inventory).ADraftNewBegin drafting contract renewal documents and conduct internal review as needed09/01/201409/30/2014ConcludedPamela Nelle11/18/2013 1:29 PM
B119Manage and Administer ProjectsOverall Project ManagementManage on-the-ground efforts. Also covers administrative work in support of on-the-ground efforts and in support of BPA's programmatic requirements such as metric reporting, financial reporting (e.g., accruals), and development of an SOW package (includes draft SOW, budget, spending plan, and property inventory).BSubmitSubmit contract renewal package (SOW, Excel budget, property inventory) to BPA COTR10/30/201410/30/2014ConcludedPamela Nelle11/18/2013 1:29 PM
B119Manage and Administer ProjectsOverall Project ManagementManage on-the-ground efforts. Also covers administrative work in support of on-the-ground efforts and in support of BPA's programmatic requirements such as metric reporting, financial reporting (e.g., accruals), and development of an SOW package (includes draft SOW, budget, spending plan, and property inventory).CFixCmtsAddress comments and revise SOW, LIB, and PI as needed to get BPA manager approval11/01/201411/30/2014ConcludedPamela Nelle11/18/2013 1:29 PM
B119Manage and Administer ProjectsOverall Project ManagementManage on-the-ground efforts. Also covers administrative work in support of on-the-ground efforts and in support of BPA's programmatic requirements such as metric reporting, financial reporting (e.g., accruals), and development of an SOW package (includes draft SOW, budget, spending plan, and property inventory).DSign&RtrnReturn signed contract to BPA’s Contracting Officer within 30 days12/01/201412/31/2014ConcludedPamela Nelle11/18/2013 1:29 PM
B119Manage and Administer ProjectsOverall Project ManagementManage on-the-ground efforts. Also covers administrative work in support of on-the-ground efforts and in support of BPA's programmatic requirements such as metric reporting, financial reporting (e.g., accruals), and development of an SOW package (includes draft SOW, budget, spending plan, and property inventory).EFinInv01Submit final invoice for prior contract within 90 days to facilitate contract closeout11/01/201401/31/2015ConcludedPamela Nelle11/18/2013 1:29 PM
B119Manage and Administer ProjectsOverall Project ManagementManage on-the-ground efforts. Also covers administrative work in support of on-the-ground efforts and in support of BPA's programmatic requirements such as metric reporting, financial reporting (e.g., accruals), and development of an SOW package (includes draft SOW, budget, spending plan, and property inventory).FACCR01Accrual - Submit September estimate to BPA08/10/201409/30/2014ConcludedPamela Nelle11/18/2013 1:29 PM
B119Manage and Administer ProjectsOverall Project ManagementManage on-the-ground efforts. Also covers administrative work in support of on-the-ground efforts and in support of BPA's programmatic requirements such as metric reporting, financial reporting (e.g., accruals), and development of an SOW package (includes draft SOW, budget, spending plan, and property inventory).GCostSh01Facilitate inputting Cost Share information into Pisces at the Project level09/30/201411/01/2014ConcludedPamela Nelle11/18/2013 1:29 PM
B119Manage and Administer ProjectsOverall Project ManagementManage on-the-ground efforts. Also covers administrative work in support of on-the-ground efforts and in support of BPA's programmatic requirements such as metric reporting, financial reporting (e.g., accruals), and development of an SOW package (includes draft SOW, budget, spending plan, and property inventory).HDELIVAll BPA Contract Documents 01/31/2015ConcludedPamela Nelle11/18/2013 2:13 PM
C165Produce Environmental Compliance DocumentationEC for FY13 and pre-work for FY14 contractAssemble, gather, acquire, or prepare documents in support of obtaining environmental compliance from BPA (such as filling out a NEPA Checklist, providing maps, obtaining permits, conducting public involvement activities, completing an archaeological survey, etc.). Ensure a compliance letter has been received, or is still valid, prior to commencing any affected work.AECCOMPObtain BPA's EC Lead sign-off that EC requirements are complete02/01/201402/28/2014ConcludedPamela Nelle11/18/2013 1:32 PM
C165Produce Environmental Compliance DocumentationEC for FY13 and pre-work for FY14 contractAssemble, gather, acquire, or prepare documents in support of obtaining environmental compliance from BPA (such as filling out a NEPA Checklist, providing maps, obtaining permits, conducting public involvement activities, completing an archaeological survey, etc.). Ensure a compliance letter has been received, or is still valid, prior to commencing any affected work.B1-HIPHIP3 Risk Determination: Contact BPA EC Lead for risk determination02/01/201402/28/2014ConcludedPamela Nelle11/18/2013 1:32 PM
C165Produce Environmental Compliance DocumentationEC for FY13 and pre-work for FY14 contractAssemble, gather, acquire, or prepare documents in support of obtaining environmental compliance from BPA (such as filling out a NEPA Checklist, providing maps, obtaining permits, conducting public involvement activities, completing an archaeological survey, etc.). Ensure a compliance letter has been received, or is still valid, prior to commencing any affected work.CLAMPDetermine if contract work could adversely affect Pacific lamprey02/01/201402/28/2014ConcludedPamela Nelle11/18/2013 1:35 PM
C165Produce Environmental Compliance DocumentationEC for FY13 and pre-work for FY14 contractAssemble, gather, acquire, or prepare documents in support of obtaining environmental compliance from BPA (such as filling out a NEPA Checklist, providing maps, obtaining permits, conducting public involvement activities, completing an archaeological survey, etc.). Ensure a compliance letter has been received, or is still valid, prior to commencing any affected work.DESAReport lamprey observation and catch data to USFWS03/01/201401/31/2015ConcludedPamela Nelle11/18/2013 2:14 PM
C165Produce Environmental Compliance DocumentationEC for FY13 and pre-work for FY14 contractAssemble, gather, acquire, or prepare documents in support of obtaining environmental compliance from BPA (such as filling out a NEPA Checklist, providing maps, obtaining permits, conducting public involvement activities, completing an archaeological survey, etc.). Ensure a compliance letter has been received, or is still valid, prior to commencing any affected work.EANSInspect water craft, waders, boots, etc. to be used in or near water for aquatic invasive species03/01/201401/30/2015ConcludedPamela Nelle11/18/2013 1:37 PM