A | 61 | Maintain Artificial Production Facility/Infrastructure | Install Backup Generator at WEC lab for CTUIR lamprey program. | Purchase and install a backup generator to serve the WEC lab where the CTUIR lamprey, and mussel programs are located. Work will be subcontracted out to the Walla Walla Community college who owns the site and will own and operate the backup generator. | A | EC | Environmental compliance requirements complete | 02/01/2024 | 02/29/2024 | Concluded | James Barron | 12/15/2023 3:38 PM |
A | 61 | Maintain Artificial Production Facility/Infrastructure | Install Backup Generator at WEC lab for CTUIR lamprey program. | Purchase and install a backup generator to serve the WEC lab where the CTUIR lamprey, and mussel programs are located. Work will be subcontracted out to the Walla Walla Community college who owns the site and will own and operate the backup generator. | B | | Communicate and share with BPA when bid for generator is received. | 02/01/2024 | 07/01/2025 | Concluded | James Barron | 12/19/2023 3:50 PM |
A | 61 | Maintain Artificial Production Facility/Infrastructure | Install Backup Generator at WEC lab for CTUIR lamprey program. | Purchase and install a backup generator to serve the WEC lab where the CTUIR lamprey, and mussel programs are located. Work will be subcontracted out to the Walla Walla Community college who owns the site and will own and operate the backup generator. | C | DELIV | Backup Generator is in place and operational. | | 01/31/2026 | Concluded | James Barron | 12/19/2023 3:50 PM |
B | 185 | Produce CBFish Status Report | Periodic Status Reports for BPA | The Contractor shall report on the status of milestones and deliverables in CBFish. Reports shall be completed either monthly or quarterly as determined by the BPA COR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COR. | A | SR | Feb-Mar 2024 (2/1/2024 - 3/31/2024) | 04/01/2024 | 04/15/2024 | Concluded | James Barron | 12/15/2023 3:19 PM |
B | 185 | Produce CBFish Status Report | Periodic Status Reports for BPA | The Contractor shall report on the status of milestones and deliverables in CBFish. Reports shall be completed either monthly or quarterly as determined by the BPA COR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COR. | B | SR | Apr-Jun 2024 (4/1/2024 - 6/30/2024) | 07/01/2024 | 07/15/2024 | Concluded | James Barron | 12/15/2023 3:19 PM |
B | 185 | Produce CBFish Status Report | Periodic Status Reports for BPA | The Contractor shall report on the status of milestones and deliverables in CBFish. Reports shall be completed either monthly or quarterly as determined by the BPA COR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COR. | C | SR | Jul-Sep 2024 (7/1/2024 - 9/30/2024) | 10/01/2024 | 10/15/2024 | Concluded | James Barron | 12/15/2023 3:19 PM |
B | 185 | Produce CBFish Status Report | Periodic Status Reports for BPA | The Contractor shall report on the status of milestones and deliverables in CBFish. Reports shall be completed either monthly or quarterly as determined by the BPA COR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COR. | D | SR | Oct-Dec 2024 (10/1/2024 - 12/31/2024) | 01/01/2025 | 01/15/2025 | Concluded | James Barron | 12/15/2023 3:19 PM |
B | 185 | Produce CBFish Status Report | Periodic Status Reports for BPA | The Contractor shall report on the status of milestones and deliverables in CBFish. Reports shall be completed either monthly or quarterly as determined by the BPA COR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COR. | E | SR | Jan-Mar 2025 (1/1/2025 - 3/31/2025) | 04/01/2025 | 04/15/2025 | Concluded | James Barron | 12/15/2023 3:19 PM |
B | 185 | Produce CBFish Status Report | Periodic Status Reports for BPA | The Contractor shall report on the status of milestones and deliverables in CBFish. Reports shall be completed either monthly or quarterly as determined by the BPA COR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COR. | F | SR | Apr-Jun 2025 (4/1/2025 - 6/30/2025) | 07/01/2025 | 07/15/2025 | Active | James Barron | 12/15/2023 3:19 PM |
B | 185 | Produce CBFish Status Report | Periodic Status Reports for BPA | The Contractor shall report on the status of milestones and deliverables in CBFish. Reports shall be completed either monthly or quarterly as determined by the BPA COR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COR. | G | SR | Jul-Sep 2025 (7/1/2025 - 9/30/2025) | 10/01/2025 | 10/15/2025 | Active | James Barron | 12/15/2023 3:19 PM |
B | 185 | Produce CBFish Status Report | Periodic Status Reports for BPA | The Contractor shall report on the status of milestones and deliverables in CBFish. Reports shall be completed either monthly or quarterly as determined by the BPA COR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COR. | H | SR | Oct-Dec 2025 (10/1/2025 - 12/31/2025) | 01/01/2026 | 01/15/2026 | Active | James Barron | 12/15/2023 3:19 PM |
B | 185 | Produce CBFish Status Report | Periodic Status Reports for BPA | The Contractor shall report on the status of milestones and deliverables in CBFish. Reports shall be completed either monthly or quarterly as determined by the BPA COR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COR. | I | SR | Final Jan 2026 (1/1/2026 - 1/31/2026) | 01/17/2026 | 01/31/2026 | Active | James Barron | 12/15/2023 3:19 PM |
C | 119 | Manage and Administer Projects | Install backup generator | Install backup generator | A | ConAdmin | Error-check & update actual WE budget spending w/in 4 months (reflect contract close-out value) | 02/01/2024 | 02/01/2024 | Concluded | James Barron | 12/20/2023 1:34 PM |
C | 119 | Manage and Administer Projects | Install backup generator | Install backup generator | B | FinStatusRpt | Submit Financial Status Report | 02/01/2024 | 12/31/2025 | Active | James Barron | 12/20/2023 1:37 PM |
C | 119 | Manage and Administer Projects | Install backup generator | Install backup generator | C | CostSh01 | Facilitate inputting Cost Share information into CBFish at the Project level | 02/01/2024 | 12/31/2025 | Active | James Barron | 12/20/2023 1:37 PM |
C | 119 | Manage and Administer Projects | Install backup generator | Install backup generator | D | Update IDR | Revise Line Item Budget to incorporate change in indirect rate for the remaining contract period | 02/01/2024 | 02/01/2024 | Concluded | James Barron | 12/20/2023 1:37 PM |
C | 119 | Manage and Administer Projects | Install backup generator | Install backup generator | E | SFTY | Comply with all applicable federal, state, tribal and local safety requirements, including reporting | 02/01/2024 | 12/31/2025 | Active | James Barron | 12/20/2023 1:37 PM |
| | | | | | | | | | | | |