Official acceptance and approval of BA's by applicable compliance representatives |
B: 165. Prepare Biological Assessments for applicable projects |
|
01/31/2010 |
|
Obtain DSL/USACE approval on JPA permits |
C: 165. Submit JPA to state and federal entities |
|
01/31/2010 |
|
Obtain official approval from Tribal & state cultural resource preservation agency representation |
D: 165. Cultural Resource protection & preservation |
|
09/30/2009 |
07/28/2009 |
Active participation with co-managerial interests in the Umatilla Basin |
E: 189. Coordinate with other entities planning & implementing habitat improvements in the Umatilla Basin |
|
01/31/2010 |
01/31/2010 |
Develop and utilize applicable and effective monitoring techniques |
F: 157. Collect various forms of professional, scientific data for project potential analysis |
|
01/31/2010 |
01/31/2010 |
Summarized data in the format of professional scientific reports |
G: 162. Analyze/interpret scientific data |
|
01/31/2010 |
01/31/2010 |
Delivery of engineered implementation designs/drawings with specifications |
H: 175. Preparation & submittal of engineering designs/specifications for Meacham Creek project |
|
01/31/2010 |
11/30/2009 |
Improve riverine process via levee setback on Meacham Creek |
I: 180. Enhance floodplain connectivity and function via levee setback at Meacham Creek |
|
12/31/2009 |
12/31/2009 |
Improve instream habitat conditions on Meacham Creek |
J: 29. Improve habitat quality and quantity of floodplain habitat features and channel in lower Meacham Cr |
|
01/31/2010 |
|
Installation of fence at Cunningham property |
K: 40. Install riparian fence at West Birch Creek RM 2.7-3.0 and Meacham Creek |
|
03/31/2009 |
03/31/2009 |
Vegetative planting in existing and new project areas |
L: 47. Supplement riparian areas of existing and new projects with additional vegetation |
|
01/31/2010 |
11/30/2009 |
Maximize survival of vegetation plantings in CTUIR project areas |
M: 22. Maintain vegetation plantings at all CTUIR habitat implementation project areas |
|
01/31/2010 |
11/30/2009 |
Removal of non-preferred species of vegetative growth from project areas |
N: 53. Control of noxious weeds in project areas by physical and chemical means |
|
01/31/2010 |
12/31/2009 |
Maintaining proper operation of instream habitat structures |
O: 186. Monitor & troubleshoot issues that interfere w/ proper function of instream improvement structures |
|
01/31/2010 |
01/31/2010 |
Maintenance of conservation easements |
P: 186. Secure & adhere to details of conservation easements assoc. w/ habitat projects |
|
01/31/2010 |
01/31/2010 |
Development of additional water sources to supplement the low annual precipitation of 11" |
Q: 34. Develop additional water sources & strategies to improve survival of riparian vegetation on B&G |
|
01/31/2010 |
11/30/2009 |
Utilize area farming practice methods to till established weed areas at the B&G property |
R: 48. Tillage strategies at B & G project to improve vegetative planting survival of preferred species |
|
01/31/2010 |
11/30/2009 |
Produce methods for use as monitoring project effectiveness |
S: 156. Develop strategic and scientifically accepted monitoring methods for application |
|
01/31/2010 |
01/31/2010 |
Summarized data in the format of professional scientific reports |
T: 174. Produce Umatilla River and Willow Creek watershed habitat assessment plans |
|
01/31/2010 |
|
Review and provide technical input on issues that may adversely affect natural resources |
U: 122. Review and provide technical input on issues and topics that affect the areas natural resource |
|
01/31/2010 |
01/31/2010 |
Attach 2007 Progress Report in Pisces |
V: 132. Submit Annual Progress Report for the FY 2009 period (Feb 2009) to (Jan 2010) |
|
01/31/2010 |
01/31/2009 |
2010 draft SOW and accrual reports |
W: 119. Manage and Administer Project |
|
11/02/2009 |
11/16/2009 |