projects managed |
B: 119. Manage Restoration Projects |
|
02/28/2011 |
09/28/2010 |
List of Selected Projects (and contingency projects) to be implemented in 2008 |
C: 114. Select habitat improvement actions for 2011 |
|
02/28/2011 |
08/15/2010 |
Project databases that are maintained and up to date. |
D: 160. Update Project Database |
|
02/28/2011 |
09/28/2010 |
Disseminated data |
E: 161. Create informal summary reports and maps |
|
02/28/2011 |
09/28/2010 |
5 outreach sessions completed |
F: 99. Conduct field and classroom education at local schools |
|
02/28/2011 |
09/28/2010 |
Technical review and input provided to various policy and planning efforts |
G: 122. Input to various Tribal planning and policy efforts |
|
02/28/2011 |
09/28/2010 |
Completed environmental documentation |
H: 165. Environmental Compliance |
|
01/01/2010 |
01/01/2010 |
Completed FY 09 Annual Report submitted to BPA |
I: 132. Produce Project Annual Report for FY 09 |
|
11/28/2009 |
11/28/2009 |
Leasing Range Units to protect riparian areas |
J: 92. Lease Range Units in the Logy Creek Watershed |
|
02/28/2011 |
02/28/2011 |
3 rotary screw traps deployed and recovered |
K: 70. Deploy and Recover 5ft Rotary Screw Traps |
|
06/08/2010 |
06/08/2010 |
3 miles of completed snorkel surveys |
L: 157. Snorkel Survey NF Simcoe Creek |
|
02/28/2011 |
09/28/2010 |
3 miles of completed snorkel surveys |
M: 157. Snorkel Survey Mid Toppenish Creek |
|
01/31/2011 |
09/28/2010 |
3 miles of completed snorkel surveys |
N: 157. Snorkel Survey Ahtanum Creek Diversions |
|
01/31/2011 |
09/28/2010 |
3 miles of completed snorkel surveys |
O: 157. Snorkel Survey Ahtanum Creek Forks index site |
|
01/31/2011 |
09/28/2010 |
3 miles of completed snorkel surveys |
P: 157. Snorkel Survey Dry and Logy Creek index sites |
|
01/31/2011 |
09/28/2010 |
Wapato Irrigation Project diversions managed for minimum instream flow. |
Q: 186. Manage Operation of Upper and Lower WIP canals on Ahtanum Creek |
|
02/28/2011 |
09/28/2010 |
Winter stock water diversion managed at Olney lateral |
R: 186. Assist with Summer Operation of Olney Lateral |
|
02/28/2011 |
09/28/2010 |
Functioning fences, wells and stock tanks |
S: 186. Maintain livestock wells/stock tanks/livestock fences/improved springs |
|
11/30/2010 |
09/28/2010 |
Data collected and ready to be entered into the Project's databases. |
T: 157. Collect Field Data |
|
02/28/2011 |
09/28/2010 |
complete 1 mile of surveys |
U: 157. Timber, Fish and Wildlife (TFW) surveys |
|
02/28/2011 |
09/28/2010 |
Completed sediment inventories and database |
V: 157. Conduct Sediment Inventories |
|
02/28/2011 |
09/28/2010 |
Construction of approximately 5 grade control structures |
W: 29. MF Dry Creek Grade Control Structures |
|
11/30/2010 |
09/30/2010 |
Remove Culvert from Middle Fork Dry Creek |
X: 29. MF Dry Creek Culvert Removal |
|
11/30/2010 |
09/30/2010 |
2 wells converted to stock wells |
Y: 34. Convert existing wells to stock wells |
|
02/28/2011 |
09/28/2010 |
Construct Grade Control in Lincoln Meadow |
Z: 29. Lincoln Meadow-- Construct Grade Control Structures |
|
09/28/2010 |
09/28/2010 |
Construction of Ahtanum Creek Bank stabiliztion |
AA: 29. Ahtanum Creek Bank Stabilization Project |
|
02/28/2011 |
09/01/2010 |
One set of engineered plans for removal of 3-4 culverts along Panther Creek. |
AB: 175. Engineered Plan for Panther Creek Culverts Project |
|
02/01/2010 |
02/01/2010 |
Replace 3 passage barrier culverts with culverts capable of passage |
AC: 184. Panther Creek Culvert Replacement Project |
|
12/31/2010 |
09/30/2010 |
Construct 1 passive type irrigation fish screen |
AD: 69. Smartlowit Fish Screen Installation |
|
12/31/2010 |
12/31/2010 |
Construct one bank stabilization project on Ahtanum Creek |
AE: 29. CR 20206 Ahtanum Creek Bank Stabilization Project |
|
09/30/2010 |
06/30/2010 |
Complete engineer plans to remove diversion structure |
AG: 175. CCR 21216 Durham Project |
|
02/28/2011 |
02/28/2011 |
Complete engineered design plans for two on Reservation fish screens on Simcoe Creek |
AH: 175. CCR 21216 Design 2 on Reservation Fish Screens on Simcoe Creek |
|
02/28/2011 |
02/28/2011 |
3 rotary screw traps deployed and recovered |
AI: 70. CCR 21216 Deploy and Recover 5ft Rotary Screw Traps |
|
02/28/2011 |
03/31/2010 |