Upload SOW, budget, property inventory for upcoming contract period to Pisces. |
B: 119. Manage and Administer Project |
|
11/01/2011 |
12/05/2011 |
Receipt of environmental compliance clearance from BPA |
C: 165. Produce Environmental Compliance Documentation |
|
01/31/2012 |
01/31/2012 |
Attach 2009 Annual Progress Report in Pisces |
D: 132. Produce Annual Progress Report for the FY 2009 period (Feb 2009) to (Jan 2010) |
|
01/31/2012 |
|
Attach 2010 Annual Progress Report in Pisces |
E: 132. Produce Annual Progress Report for the FY 2010 period (Feb 2010) to (Jan 2011) |
|
11/30/2011 |
|
List of final projects |
F: 114. CTUIR Umatilla Subbasin Restoration Coordination |
|
01/31/2012 |
01/31/2012 |
Provide technical input and summaries to enhance or protect natural resources in the subbasin. |
G: 122. Review and provide technical input on issues and topics that affect the areas natural resource |
|
01/31/2012 |
01/31/2012 |
Coordinate watershed association activities |
H: 191. Umatilla River Watershed coordination duties |
|
01/31/2012 |
01/31/2012 |
Complete outreach and education activities |
I: 99. Public Outreach and Education |
|
01/31/2012 |
01/31/2012 |
Produce methods for monitoring project effectiveness |
J: 156. Incorporate developed strategic and scientifically accepted monitoring methods for application |
|
01/31/2012 |
01/31/2012 |
Complete data collection and summarized findings |
K: 157. Monitoring and Evaluation CTUIR Umatilla Anadromous Fish Habitat Project |
|
01/31/2012 |
01/31/2012 |
Maximize survival of planted trees and shrubs in enhancement project areas |
L: 22. Maintain trees and shrubs, and grass seeding in Umatilla River Basin habitat enhancement areas |
|
01/31/2012 |
01/31/2012 |
Complete scheduled tree and shrub plantings in project areas |
M: 47. Supplement riparian areas of existing and new projects with additional vegetation |
|
01/31/2012 |
01/31/2012 |
Treat 512 acres (109 riparian & 403 upland) in enhancement areas |
N: 53. Control of noxious weeds in project areas by physical and chemical means |
|
01/31/2012 |
01/31/2012 |
Maintain proper operation of instream habitat structures |
O: 186. Inspect and maintain function of instream improvement structures |
|
01/31/2012 |
01/31/2012 |
Maintenance of land or structures associated with conservation easements |
P: 186. Maintenance of habitat features associated with project conservation easements |
|
01/31/2012 |
01/31/2012 |
Complete channel reconstruction and in-stream enhancement on 1.1 miles of stream |
Q: 29. Meacham Creek floodplain restoration and in-stream enhancement, river miles 6.0 to 7.0 |
|
11/30/2011 |
11/30/2011 |
Complete levee removal floodplain enhancements to Meacham Creek |
R: 180. Enhance floodplain connectivity and function via levee setback on Meacham Creek, river miles 6.0-7.0 |
|
01/31/2012 |
01/31/2012 |
3 miles of fence constructed on Meacham Creek |
S: 40. Install riparian fence enclosure in Meacham Creek, river miles 2.0-9.0 |
|
01/31/2012 |
12/30/2011 |
Oversight of fence construction in Isquulktpe Watershed |
T: 100. Construction oversight of boundary fence in Isquulktpe Watershed |
|
11/30/2011 |
11/30/2011 |
Maintain 355 acres (61 riparian, 294 upland) in project area |
U: 22. Enhance native vegetation growth in the B&G Resources Property, Umatilla River (RM 41-44) |
|
11/30/2011 |
09/30/2011 |
Project Design and Implementation Plan |
V: 175. Birch Creek Taylor Dam Removal and Habitat Restoration Project |
|
01/31/2012 |
01/31/2012 |
Modify irrigation dam for fish passage |
W: 84. Tier 2 Work Element: Peterson Dam Modification Project on Birch Creek, river mile 2.5 |
|
10/31/2011 |
|
Initiate project coordination and identify priority status and implementation need. |
X: 175. Tier 2 Work Element: Westland/Ramos Habitat Restoration Project Plan |
|
01/31/2012 |
|