Province | Subbasin | % |
---|---|---|
Columbia Cascade | Entiat | 20.00% |
Methow | 40.00% | |
Wenatchee | 40.00% |
Previous: | Next: |
---|---|
56662 REL 65: 2009-003-00 EXP UPPER COLUMBIA HABITAT RESTORATION |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
All administrative tasks fulfilled with timely quality products | A: 119. Perform project management and administrative duties | 12/31/2016 | 12/28/2016 | |
Assist BPA in producing Environmental Compliance documents | B: 165. Environmental Compliance | 12/31/2016 | 12/28/2016 | |
Complete the USFS NEPA process for the Stormy Project Area A in the Entiat Watershed | F: 165. Entiat Stormy A USFS NEPA Process 2014-125 | 11/15/2016 | 12/13/2016 | |
NEPA analysis and documentation to obtain permits for the Upper Stillwaters projects | G: 165. Entiat Upper Stillwaters USFS NEPA Process 2013-109 | 11/15/2016 | 12/13/2016 | |
Chewuch RM15.5-20 EC process | H: 165. Chewuch RM15.5-20 Phase 1 USFS EA development-NEPA 2015-142 | 12/31/2016 | 12/28/2016 | |
Lower Wenatchee Public Outreach | I: 99. Lower Wenatchee Public Outreach - 2012-98 | 12/30/2016 | 12/13/2016 | |
Lower Wenatchee River Reach Assessment Report, uploaded to Pisces | J: 115. Lower Wenatchee Reach Assessment 2014-121 | 12/30/2016 | 12/28/2013 | |
8-Mile Creek Fish Barrier Removal Design | K: 175. 8-Mile Creek Fish Barrier Removal Design 2015-141 | 12/31/2016 | 12/28/2016 | |
Draft conceptual designs and report, uploaded to Pisces | L: 175. Chewuch RM17-20 Fish Enhancement Project Survey 2015-140 | 11/01/2016 | 11/01/2016 | |
Draft and Final Construction Plans | M: 175. Chewuch RM 15.5-17 Fish Enhancement Project Engineering 2012-97 | 12/31/2016 | 12/28/2016 | |
Construction Management & Monitoring Plan Complete | Q: 100. LWP Groups 2&3 Habitat Restoration Construction Oversight-2012-99 | 12/31/2016 | 12/13/2016 | |
Implement Groups 2&3 LWP Habitat Restoration project | R: 30. LWP Groups 2&3 Habitat Restoration Construction-2012-99 | 12/16/2016 | 12/13/2016 | |
Final Design Set and Monitoring Plan | Z: 175. Twisp Ponds Left Bank Side Channel Design 2010-54 | 07/01/2016 | 06/30/2016 | |
Bidding Assistance and Construction Management | AA: 100. Twisp Ponds Left Bank Side Channel Construction Management 2010-54 | 12/31/2016 | 12/28/2016 | |
1,000 feet of side channel created | AB: 30. Twisp Ponds Left Bank Side Channel Construction 2010-54 | 11/01/2016 | 09/30/2016 | |
Final Design Set and Monitoring Plan | AC: 175. Twisp Horseshoe Side Channel Design (RM 11.5) 2010-39 | 12/31/2016 | ||
Final Design Set and Monitoring Plan | AF: 175. Early Winters Creek - Twenty Below Engineering 2014-117 | 12/31/2016 | ||
Construction Management and Monitoring Plan | AI: 100. Newby Narrows Fish Habitat Enhancement Project Construction Oversight 2015-153 | 12/31/2016 | ||
Improve channel structure and complexity to 5,000 linear feet of the Twisp River | AJ: 29. Newby Narrows Fish Habitat Enhancement Project Construction 2015-153 | 12/31/2016 | ||
Final Construction Plan and Monitoring Plan (Including As-Builts) | AM: 175. Entiat 3-D LWM Revisited Design Engineering 2009-29 | 09/30/2016 | ||
NEPA analysis and documentation to obtain permits for Upper Wenatchee projects | AP: 165. CCR-36111/Mod. 1 Upper Wenatchee USFS NEPA Process 2015-145 | 12/30/2016 | ||
River Safety Assessment Reports, uploaded to Pisces | AQ: 174. CCR-36111/Mod. 1 UC River Safety Assessments (2016) 2011-61 | 12/31/2016 | 12/28/2016 | |
Beaver Creek Reach Assessment Report and Data, uploaded to Pisces | AR: 115. CCR-36111/Mod. 1 Beaver Creek Reach Assessment 2015-154 | 12/31/2016 | ||
Final Construction Plan | AS: 175. CCR-36111/Mod. 1 Newby Narrows Design Phase 4 2015-153 | 01/30/2016 | 01/30/2016 | |
Skinney creek design through phase 2 | AT: 175. CCR-36111/Mod. 1 Skinney Creek Design 2015-144 | 12/30/2016 | 12/13/2016 | |
Confidential Water Rights Evaluation | AU: 154. CCR-36111/Mod. 1 Methow Basin EWD Instream Flow Project - Water Rights Assessment 2015-152 | 12/31/2016 | ||
Produce Detailed Restoration Plans Suitable for Permitting | AZ: 175. CCR-36111/Mod. 1 Twisp River - Scaffold Camp Restoration Engineering 2015-146 | 12/31/2016 | ||
Produce Detailed Restoration Plans Suitable for Permitting | BA: 175. CCR-36111/Mod. 1 Twisp River - Horseshoe PHASE 2 Restoration Engineering 2010-39 | 12/31/2016 | ||
Produce Detailed Restoration Plans Suitable for Permitting and Construction Bidding | BB: 175. CCR-36111/Mod. 1 Twisp River - War Creek Restoration Engineering 2015-148 | 12/31/2016 | ||
Plant Native Woody Vegetation and Install Deer Exclusion Fencing | BC: 47. CCR-36111/Mod. 1 Twisp Ponds Left Bank Riparian Restoration 2010-54 | 12/31/2016 | 10/31/2016 | |
Produce Detailed Restoration Plans Suitable for Permitting | BD: 175. CCR-36111/Mod. 1 Upper Methow Fawn Creek Design 2015-147 | 12/31/2016 | ||
Produce Detailed Restoration Plans Suitable for Permitting | BE: 175. CCR-36111/Mod. 1 Methow River (M2) - WDFW Floodplain Groundwater Gallery Design 2016-155 | 12/31/2016 | ||
Implement Groups 2&3 LWP Habitat Restoration project | BF: 29. LWP Groups 2&3 Habitat Restoration Construction-2012-99 (CCR-36111/Mod. 1) | 12/16/2016 | 12/13/2016 | |
Produce Detailed Restoration Plans Suitable for Permitting and Construction Bidding | BG: 175. CCR-37158/Mod. 2 Peshastin RM 2.7 Design 2016-160 | 12/31/2016 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered) |
|
Coho (O. kisutch) - Unspecified Population |
|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened) |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Perform project management and administrative duties | 10/01/2015 | ||||||
B | 165 | Environmental Compliance | 10/01/2015 | ||||||
C | 185 | Periodic Status Reports for BPA | 10/01/2015 | ||||||
D | 132 | 2015 Annual Progress Report (submitted via other contract) | 10/01/2015 | ||||||
E | 132 | 2016 Annual Progress Report (submitted via other contract) | 10/01/2015 | ||||||
F | 165 | Entiat Stormy A USFS NEPA Process 2014-125 | 10/01/2015 | ||||||
G | 165 | Entiat Upper Stillwaters USFS NEPA Process 2013-109 | 10/01/2015 | ||||||
H | 165 | Chewuch RM15.5-20 Phase 1 USFS EA development-NEPA 2015-142 | 10/01/2015 | ||||||
I | 99 | Lower Wenatchee Public Outreach - 2012-98 | 10/01/2015 | ||||||
J | 115 | Lower Wenatchee Reach Assessment 2014-121 | 10/01/2015 | ||||||
K | 175 | 8-Mile Creek Fish Barrier Removal Design 2015-141 | 10/01/2015 | ||||||
L | 175 | Chewuch RM17-20 Fish Enhancement Project Survey 2015-140 | 06/02/2016 | ||||||
M | 175 | Chewuch RM 15.5-17 Fish Enhancement Project Engineering 2012-97 | 06/02/2016 | ||||||
N | 175 | Meacham Flats Habitat Restoration Engineering - 2012-102 | 05/10/2016 | ||||||
O | 100 | Meacham Flats Habitat Restoration Construction Oversight - 2012-102 | 10/01/2015 | ||||||
P | 30 | Meacham Flats Habitat Restoration Construction 2015-127 | |||||||
Q | 100 | LWP Groups 2&3 Habitat Restoration Construction Oversight-2012-99 | 10/01/2015 | ||||||
R | 30 | LWP Groups 2&3 Habitat Restoration Construction-2012-99 | 04/01/2016 | ||||||
S | 175 | Signal Peak Habitat Restoration Design Engineering 2013-108 | 06/02/2016 | ||||||
T | 100 | Signal Peak Habitat Restoration Construction Management 2013-108 | 10/01/2015 | ||||||
U | 30 | Signal Peak Side-Channel Construction 2013-108 | |||||||
V | 29 | Signal Peak Rip-Rap Enhancement Sites A & B Construction 2013-108 | |||||||
W | 175 | Upper Burns Habitat Restoration Design Engineering 2013-107 | 10/01/2015 | ||||||
X | 100 | Upper Burns Habitat Restoration Design Construction Management 2013-107 | 10/01/2015 | ||||||
Y | 29 | Upper Burns Rip-Rap Enhancement Construction 2013-107 | |||||||
Z | 175 | Twisp Ponds Left Bank Side Channel Design 2010-54 | 03/16/2016 | ||||||
AA | 100 | Twisp Ponds Left Bank Side Channel Construction Management 2010-54 | 10/01/2015 | ||||||
AB | 30 | Twisp Ponds Left Bank Side Channel Construction 2010-54 | 06/15/2016 | ||||||
AC | 175 | Twisp Horseshoe Side Channel Design (RM 11.5) 2010-39 | 10/01/2015 | ||||||
AD | 100 | Twisp Horseshoe Side Channel Construction Management (RM 11.5) 2010-39 | 10/01/2015 | ||||||
AE | 30 | Twisp Horseshoe Side Channel Construction (RM 11.5) 2010-39 | |||||||
AF | 175 | Early Winters Creek - Twenty Below Engineering 2014-117 | 12/31/2016 | ||||||
AG | 100 | Early Winters Creek - Twenty Below Construction Management 2014-117 | 10/01/2015 | ||||||
AH | 29 | Early Winters Creek - Twenty Below Construction 2014-117 | |||||||
AI | 100 | Newby Narrows Fish Habitat Enhancement Project Construction Oversight 2015-153 | 10/01/2015 | ||||||
AJ | 29 | Newby Narrows Fish Habitat Enhancement Project Construction 2015-153 | 07/01/2016 | ||||||
AK | 100 | Lower Twisp Large Wood Enhancement Project Construction Oversight 2015-127 | 10/01/2015 | ||||||
AL | 29 | Lower Twisp Large Wood Enhancement Project Construction 2015-127 | |||||||
AM | 175 | Entiat 3-D LWM Revisited Design Engineering 2009-29 | 02/05/2016 | ||||||
AN | 100 | Entiat 3-D LWM Revisited Construction Management 2009-29 | 10/01/2015 | ||||||
AO | 29 | Entiat 3-D LWM Revisited Habitat Enhancement Project Construction 2009-29 | |||||||
AP | 165 | CCR-36111/Mod. 1 Upper Wenatchee USFS NEPA Process 2015-145 | 10/01/2015 | ||||||
AQ | 174 | CCR-36111/Mod. 1 UC River Safety Assessments (2016) 2011-61 | 10/01/2015 | ||||||
AR | 115 | CCR-36111/Mod. 1 Beaver Creek Reach Assessment 2015-154 | 03/16/2016 | ||||||
AS | 175 | CCR-36111/Mod. 1 Newby Narrows Design Phase 4 2015-153 | 03/16/2016 | ||||||
AT | 175 | CCR-36111/Mod. 1 Skinney Creek Design 2015-144 | 10/01/2015 | ||||||
AU | 154 | CCR-36111/Mod. 1 Methow Basin EWD Instream Flow Project - Water Rights Assessment 2015-152 | 10/01/2015 | ||||||
AV | 175 | CCR-36111/Mod. 1 Methow Basin EWD Instream Flow Project - Eng. Feasibility Assessment 2015-152 | |||||||
AW | 100 | CCR-36111/Mod. 1 Big Valley South Construction Oversight 2012-101 | 10/01/2015 | ||||||
AX | 29 | CCR-36111/Mod. 1 Big Valley South Habitat Complexity 2012-101 | |||||||
AY | 180 | CCR-36111/Mod. 1 Big Valley South Structure Removal 2012-101 | |||||||
AZ | 175 | CCR-36111/Mod. 1 Twisp River - Scaffold Camp Restoration Engineering 2015-146 | 10/01/2015 | ||||||
BA | 175 | CCR-36111/Mod. 1 Twisp River - Horseshoe PHASE 2 Restoration Engineering 2010-39 | 10/01/2015 | ||||||
BB | 175 | CCR-36111/Mod. 1 Twisp River - War Creek Restoration Engineering 2015-148 | 10/01/2015 | ||||||
BC | 47 | CCR-36111/Mod. 1 Twisp Ponds Left Bank Riparian Restoration 2010-54 | 06/15/2016 | ||||||
BD | 175 | CCR-36111/Mod. 1 Upper Methow Fawn Creek Design 2015-147 | 10/01/2015 | ||||||
BE | 175 | CCR-36111/Mod. 1 Methow River (M2) - WDFW Floodplain Groundwater Gallery Design 2016-155 | 10/01/2015 | ||||||
BF | 29 | LWP Groups 2&3 Habitat Restoration Construction-2012-99 (CCR-36111/Mod. 1) | 08/17/2016 | ||||||
BG | 175 | CCR-37158/Mod. 2 Peshastin RM 2.7 Design 2016-160 | 10/01/2015 |