Contract 57048: 2002-070-00 EXP NP SWCD - LAPWAI CK WATERSHED RESTORATION
Project Number:
Title:
Lapwai Creek Anadromous Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
57048
Contract Title:
2002-070-00 EXP NP SWCD - LAPWAI CK WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
52837: 2002-070-00 EXP NP SWCD LAPWAI CREEK WATERSHED RESTORATION
  • 61265: 2002-070-00 EXP NP SWCD - LAPWAI CK WATERSHED RESTORATION
Contract Status:
Closed
Contract Description:
The Restoring Anadromous Fish Habitat in the Lapwai Creek Watershed, project 2002-070-00, began in 2003.  This multi-year project focuses on restoring and improving fish habitat within the Lapwai Creek watershed.  The limiting factors addressed include low summer flows, wide fluctuation in annual stream flows, connectivity, loss of all or partial floodplain, sedimentation of spawning and rearing habitat, high summer stream temperatures, and lack of in-stream cover.  Past accomplishments have entailed the installation of land improvement projects to address these limiting factors, including 8.2 miles of riparian fencing, 6.21 miles of upland fencing, 385 acres of weed control, two livestock waste systems, 9,000 LF of riparian plantings, three stream crossings, 10.5 miles of road improvements, 2 miles of streambank bioengineering restoration, 4.5 acres of wetland enhancement, 15,209 acres of direct seeding, 14 alternative watering systems for livestock, 13 water and sediment control structures, and the development of 42 habitat conservation plans, 9.27 miles of access restored, 3.1 miles of floodplain reconnected, 82 acres of tree planting, and 200 acres of grass seeding.  

Prior to the initiation of this project, a massive data gap existed on fish, the condition of fish habitat, and limiting factors within the watershed.  Under the FY 2007 contract, we focused primarily on the analysis and compilation of the fish presence and abundance data, and stream habitat data collected annually since 2003.  The data was analyzed and converted into a GIS-compatible format and then combined with other available, watershed-wide data sets developed by the Nez Perce Soil and Water Conservation District, the Nez Perce Tribe Watershed Division (NPT) and the NPT Water Resources Division.  The synergistic effect of these combined data sets came together in the development of the "Strategy for the Ecological Restoration of Lapwai Creek Watershed," a document intended to direct efforts and resources toward the highest priority restoration projects and areas of the Lapwai Creek Watershed.  This document provides an accurate assessment of the status and health of the aquatic resources within the watershed, and will allow us to spatially prioritize the implementation of future watershed protection and restoration projects for the Lapwai Creek Watershed. This plan was updated in FY08 to incorporate information identified by the ISRP review.
                                                                                                                                                                          
FY 12 Contract Summary:

The "Strategy for the Ecological Restoration of Lapwai Creek Watershed," which was completed under the FY 07 contract and revised in FY08, was the main reference for prioritizing implementation and developing the FY 12 SOW.  

Under this contract, the NPSWCD plans to install 4,464 LF of fence, control  6 acres of noxious weeds, improve 700 LF or road, plant 6 acres with native trees and shrubs, install 3 water developments, install one erosion control structure, maintain vegetation at 33 sites (310 acres), develop 8 habitat restoration plans, remove two passage barriers, treat 73 acres of hybrid knotweed, treat 115 acres of orange hawkweed, release biocontrol adults at 5 sites, and install 2,225 acres of direct seeding.

Status and Trend and Implementation/Effectiveness monitoring under this contract is coordinated with the Nez Perce Tribe.  The Nez Perce Tribe conducts the monitoring and evaluation required to determine population status and trends, as well as the physical and biological response to the habitat/watershed restoration efforts.  The Nez Perce Soil and Water Conservation District (NPSWCD) utilizes the Nez Perce Tribe's monitoring data to prioritize habitat improvement and site specific project areas.  Since the majority of the land within the watershed is privately owned, the District also coordinates with the landowners to obtain project approval for both the NPT and the NPSWCD to continue habitat restoration actions throughout the Lapwai Creek watershed. The NPSWCD efforts focus on non-tribal properties, while the NPT efforts focus on tribal properties.
Account Type(s):
Expense
Contract Start Date:
05/01/2012
Contract End Date:
04/30/2013
Current Contract Value:
$261,756
Expenditures:
$261,756

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

Description: Photo looking downstream of site where thermograph was deployed in Polly Canyon, a tributary to Webb Creek.

Contract(s):

57048

Dimensions: 1600 x 1200

Description: View downstream of thermograph located near Lapwai Creek and Clearwater River confluence

Contract(s):

57048

Dimensions: 1600 x 1200

Description: Photo looking downstream of thermograph located at Slickpoo road crossing on Mission Creek.

Contract(s):

57048

Dimensions: 1600 x 1200

Description: Photo looking upstream from thermograph site #1 located on Rock Creek, a tributary of Mission Creek.

Contract(s):

57048

Dimensions: 1650 x 1275


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance Requirements Completed A: 165. Environmental Compliance 02/03/2013 02/03/2013
Final FY 10 report attached to this contract C: 132. Produce Progress Report for Period 5/1/11-4/30/12 08/15/2012 09/12/2012
FY 11 SOW Package and FY 10 Accrual Estimate D: 119. Management, Coordination, and Communication 02/19/2013 03/22/2013
Project selected for areas prioritized by the Lapwai Ecological Restoration Strategy document E: 114. Select, Prioritize, and Obtain Permission for 2013 Projects 12/31/2012 12/26/2012
Design package for 6 land improvement projects F: 175. Prepare Engineering and Technical Designs for 2013/2014 Projects 04/15/2013 03/28/2013
Completed RIPP Step 1 on 8 non-tribal Properties G: 115. Complete Habitat Restoration Plans 04/29/2013 03/28/2013
Updated GIS database H: 160. Maintain GIS database 04/15/2013 01/24/2013
Marketing plan implementation I: 99. Implement Lapwai Watershed Marketing Plan 03/31/2013 03/28/2013
Raw temperature data J: 157. Stream Temperature Data Collection in the Lapwai Creek Watershed 11/28/2012 11/28/2012
Data Sent to Idaho StreamNet Project Leader K: 161. Supply Publicly Available Data to Idaho StreamNet Project Leader 03/01/2013 03/28/2013
310 acres of vegetation maintained at 33 sites L: 197. Maintain Vegetation at Previously Planted Sites in Contract Years 2005 through Spring 2012 08/30/2012 09/30/2012
2.25 miles Stream Treated for Hybrid Knotweed M: 197. Control Hybrid Knotweed 10/31/2012 09/20/2012
Treat 116 acres of hawkweed at 3 sites. N: 197. Craig Mountain Hawkweed Treatment 08/24/2012 07/23/2012
50 Acres of Invasive Plant Management O: 197. Release biocontrol agents for yellow star thistle and spotted knapweed control. 07/30/2012 06/28/2012
3 Acres of Invasive Plant Management P: 197. Weed Control Demonstration Project and Field Trial 10/16/2012 08/20/2012
Bio-logs, wetland and grass plugs planted and stored in holding tanks until 2013/2014 installation. Q: 47. Preparation of Grass Plugs, Wetland Plugs and Bio-logs for 2013/2014 Planting 03/27/2013 03/31/2013
Plant native tree, shrub and grass in riparian and upland area R: 47. Plant Riparian Areas with Native Trees and Shrubs 04/20/2013 04/30/2013
1,023.2 acres seeded with direct seeding systems S: 48. Site 12-170 Reduce Sediment Delivery to Sweetwater Creek 11/30/2012 12/10/2012
600 acres seeded with direct seeding systems T: 48. Site 0632 and 0642 Reduce Sediment Delivery to Webb and Sweetwater Creeks 11/30/2012 12/10/2012
Restore 5 miles of stream access U: 184. Flat Iron Road Fish Passage Barrier Removal Site 12-157 04/30/2013 04/30/2013
Alternative water source installed V: 34. Site 12-161 Water Development 12/15/2012 12/20/2012
Install 264 linear feet of fence W: 40. Site 12-161 Install Fence 01/24/2013 12/20/2012
Repair 200 linear feet of fence X: 186. Site 12-161 Repair Fence 11/30/2012 12/20/2012
Road Improvement Site 12-156 Y: 38. Site 12-161 Road Improvement 03/31/2013 12/09/2012
Stream Crossing Installed Z: 38. Site 12-161 Stream Crossing 03/31/2013 03/28/2013
Plant native tree, shrub and grass in riparian and upland area AA: 47. Site 12-161 Planting 02/14/2013 02/21/2013
Perform pre-planting weed control along 1.8 acres of South Tom Beall Creek. AB: 197. South Tom Beall Buffer Project Weed Control Pre-Planting 04/30/2013 04/30/2013
Plant native tree, shrub and grass in riparian buffer AC: 47. South Tom Beall Buffer Project Riparian Planting Phase I 03/22/2013 03/22/2013
Reduce sediment along 300 lf of agricultural field access roads AD: 38. South Tom Beall Buffer Road Erosion Control 04/30/2013 03/28/2013
Restore wetland along South Tom Beall Creek AE: 181. South Tom Beall Buffer Project Wetland Restoration 04/18/2013 04/30/2013
600 acres seeded with direct seeding systems AF: 48. Reduce Sediment Delivery to Tom Beall Creek 11/30/2012 12/10/2012
Install approximately 4,000 linear feet of fence along Mission Creek AG: 40. Site 11-128 Livestock Exclusion from Mission Creek 04/26/2013 04/26/2012
Alternative water source installed AH: 34. Site 11-128 Water Development 04/26/2013 10/22/2012
Water and Sediment Control Structure installed AI: 55. Site 10-106 Gully Erosion Control 04/30/2013 04/30/2013
Install 800 linear feet of fence from Webb Creek Spring AJ: 40. Livestock Exclusion from Webb Creek Spring 12-153 04/26/2013 04/30/2013
Repair Webb Creek water system. AK: 186. Site 12-154 Repair Water Development 12/30/2012 12/30/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 6 instances of WE 197 Maintain/Remove Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 34 Develop Alternative Water Source
  • 3 instances of WE 38 Improve Road for Instream Habitat Benefits
  • 3 instances of WE 40 Install Fence
  • 4 instances of WE 47 Plant Vegetation
  • 3 instances of WE 48 Practice No-till and Conservation Tillage Systems
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance 05/01/2012
B 185 Periodic Status Reports for BPA 05/01/2012
C 132 Produce Progress Report for Period 5/1/11-4/30/12 05/01/2012
D 119 Management, Coordination, and Communication 05/01/2012
E 114 Select, Prioritize, and Obtain Permission for 2013 Projects 05/01/2012
F 175 Prepare Engineering and Technical Designs for 2013/2014 Projects 05/01/2012
G 115 Complete Habitat Restoration Plans 05/01/2012
H 160 Maintain GIS database 05/01/2012
I 99 Implement Lapwai Watershed Marketing Plan 05/01/2012
J 157 Stream Temperature Data Collection in the Lapwai Creek Watershed 06/19/2012
K 161 Supply Publicly Available Data to Idaho StreamNet Project Leader 05/01/2012
L 197 Maintain Vegetation at Previously Planted Sites in Contract Years 2005 through Spring 2012 06/19/2012
M 197 Control Hybrid Knotweed 06/19/2012
N 197 Craig Mountain Hawkweed Treatment 06/19/2012
O 197 Release biocontrol agents for yellow star thistle and spotted knapweed control. 06/19/2012
P 197 Weed Control Demonstration Project and Field Trial 06/19/2012
Q 47 Preparation of Grass Plugs, Wetland Plugs and Bio-logs for 2013/2014 Planting 05/01/2012
R 47 Plant Riparian Areas with Native Trees and Shrubs 06/19/2012
S 48 Site 12-170 Reduce Sediment Delivery to Sweetwater Creek 05/31/2012
T 48 Site 0632 and 0642 Reduce Sediment Delivery to Webb and Sweetwater Creeks 05/31/2012
U 184 Flat Iron Road Fish Passage Barrier Removal Site 12-157 05/31/2012
V 34 Site 12-161 Water Development 05/31/2012
W 40 Site 12-161 Install Fence 05/31/2012
X 186 Site 12-161 Repair Fence 05/31/2012
Y 38 Site 12-161 Road Improvement 05/31/2012
Z 38 Site 12-161 Stream Crossing 05/31/2012
AA 47 Site 12-161 Planting 05/31/2012
AB 197 South Tom Beall Buffer Project Weed Control Pre-Planting 05/31/2012
AC 47 South Tom Beall Buffer Project Riparian Planting Phase I 05/31/2012
AD 38 South Tom Beall Buffer Road Erosion Control 05/31/2012
AE 181 South Tom Beall Buffer Project Wetland Restoration 05/31/2012
AF 48 Reduce Sediment Delivery to Tom Beall Creek 05/31/2012
AG 40 Site 11-128 Livestock Exclusion from Mission Creek 05/31/2012
AH 34 Site 11-128 Water Development 05/31/2012
AI 55 Site 10-106 Gully Erosion Control 05/31/2012
AJ 40 Livestock Exclusion from Webb Creek Spring 12-153 05/31/2012
AK 186 Site 12-154 Repair Water Development 05/31/2012