Contract 57344: 199604200 EXP RESTORE SALMON CR ANAD FISH
Project Number:
Title:
Restore Salmon Creek Anadromous Fish
BPA PM:
Stage:
Closed
Area:
Province Subbasin %
Columbia Cascade Okanogan 100.00%
Contract Number:
57344
Contract Title:
199604200 EXP RESTORE SALMON CR ANAD FISH
Contract Continuation:
Previous: Next:
53459: 1996-042-00 EXP RESTORE SALMON CR ANADROMOUS FISH
  • 61640: 1996-042-00 EXP RESTORE SALMON CR ANAD FISH
Contract Status:
History
Contract Description:
Since 1910, water from Salmon Creek has been stored in Conconully Reservoir, which is delivered to agricultural fields within the Okanogan Irrigation District, via ~ 12 miles of Salmon Creek.  In addition,  the North Fork of Salmon Creek is diverted into Salmon Lake, an off-channel storage reservoirs, via a feeder canal.  Water is then released from Salmon Lake to augment storage of Conconully Reservoir.   Both reservoirs are near the town of Conconully, about 17 miles northwest of Okanogan. Two pumping plants supplement the water supply during water-short years.  Shell Rock Pump Station lifts water from the Okanogan River, and Duck Lake Pumping Plant withdraws water from Duck Lake.

Salmon Creek, a tributary to the Okanogan River, is considered to be one of the most significant opportunities to restore summer steelhead in the Okanogan Basin.  This project reconnects the Okanogan River with approximately 11 miles of habitat conducive for spawning and rearing of summer steelhead.  During controlled water releases in 2003, approximately 25 cfs was required for fish migration downstream of the diversion dam.  During 2008 a "low-flow" channel was constructed downstream of the diversion dam which provided suitable fish passage conditions at approximately 10 cfs.  The low flow channel extended the duration of water available through a 12-year water lease program.  During 2011, uncontrolled spill exceeded 500 cfs resulting in an undistinguishable low flow channel.  Extensive construction work will be necessary to reestablish a channel after the irrigation season in 2012, which will facilitate fish passage at reduced discharge in future years.  

Evaluation of the migration conditions and the stability of the low-flow channel will continue during the extent of the current water lease (2017).  Minor modifications of the low-flow channel are expected during normal run-off years.
Account Type(s):
Expense
Contract Start Date:
08/01/2012
Contract End Date:
07/31/2013
Current Contract Value:
$490,849
Expenditures:
$490,849

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance Requirements A: 165. Environmental Compliance Requirements 11/05/2012 11/15/2012
Funding Package - Submit draft to COTR B: 119. Develop SOW, Budget for 2013 03/01/2013 03/11/2013
Coordinate annual activities with landowners, local govts., irrigation district, WDFW and UCR C: 191. Coordinate annual activities with landowners, local govts., OID, WDFW and UCRSRB 06/28/2013 06/28/2013
Coordination with National Marine Fisheries Service and Bureau of Reclamation D: 161. Coordination with National Marine Fisheries Service and Bureau of Reclamation 05/31/2013 05/31/2013
Evaluation of fish passage conditions during controlled releases. E: 115. Evaluate fish passage conditions during controlled releases. 06/15/2013 06/15/2013
Low flow channel evaluation and potential modification F: 30. Low flow channel evaluation for potential modification 06/28/2013 06/28/2013
Construction oversight provided to construction contractor H: 100. Provide construction oversight for reconstruction of low flow channel / bank stabilization project 11/26/2012 12/20/2012
Conduct bathymetrical survey I: 115. Bathymetry survey of Conconully Reservoir 01/14/2013 11/16/2012
Attach Progress Report in Pisces K: 132. Submit Progress(Annual) Report for the period (8/1/2011) to (7/31/2012) 06/28/2013 06/28/2013
Complete a low flow channel downstream of the OID diversion dam L: 186. Re-construct a low flow channel in the lower reach of the Salmon Creek 12/31/2012 12/20/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 2 instances of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
  • 1 instance of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance Requirements 08/01/2012
B 119 Develop SOW, Budget for 2013 08/01/2012
C 191 Coordinate annual activities with landowners, local govts., OID, WDFW and UCRSRB 08/01/2012
D 161 Coordination with National Marine Fisheries Service and Bureau of Reclamation 08/01/2012
E 115 Evaluate fish passage conditions during controlled releases. 08/01/2012
F 30 Low flow channel evaluation for potential modification
G 29 Implement design to stabilize stream bank and create off-channel rearing habitat
H 100 Provide construction oversight for reconstruction of low flow channel / bank stabilization project 08/01/2012
I 115 Bathymetry survey of Conconully Reservoir 08/01/2012
J 185 Periodic Status Reports for BPA 08/01/2012
K 132 Submit Progress(Annual) Report for the period (8/1/2011) to (7/31/2012) 08/01/2012
L 186 Re-construct a low flow channel in the lower reach of the Salmon Creek