Contract 60348: 2003-017-00 EXP ISEMP-CASCADIA CONS. DIST/COORD & DATA COLLECTION
Project Number:
Title:
Integrated Status and Effectiveness Monitoring Program (ISEMP)
BPA PM:
Stage:
Complete
Area:
Province Subbasin %
Basinwide - 100.00%
Contract Number:
60348
Contract Title:
2003-017-00 EXP ISEMP-CASCADIA CONS. DIST/COORD & DATA COLLECTION
Contract Continuation:
Previous: Next:
56392: 2003-017-00 EXP ISEMP-CASCADIA CONS. DIST/COORD & DATA COLLECTION
  • 64301: 2003-017-00 EXP ISEMP - CASCADIA CONS DIST/COORD/ DATA COLL 2014
Contract Status:
Closed
Contract Description:
Contract Description: The Integrated Status and Effectiveness Monitoring Program (ISEMP, 2003-017-00) is an ongoing collaborative effort to design, test, implement and evaluate Status and Trends Monitoring for salmon and steelhead populations and their habitat, and watershed-scale Effectiveness Monitoring for management actions impacting salmon and steelhead populations and habitat in the Interior Columbia River Basin.

ISEMP explicitly addresses work requirements of many 2008 FCRPS Biological Opinion RPAs (56.1, 56.2, 56.3, 57.1, 57.2, 57.3, 57.4, 57.5) and is directly related to additional 2008 FCRPS Biological Opinion implementation strategy requirements and recommendations. ISEMP takes a pilot-project approach to the research and development of monitoring by implementing experimental programs in several major subbasins of the Interior Columbia: the Wenatchee, Entiat, Methow, John Day, South Fork Salmon and Lemhi River basins. The overall goa... l of the project is to provide regional salmon management agencies with the data, information and tools necessary to design efficient and effective monitoring programs.

Specifically, ISEMP generates quantitative guidance on and examples of: the robustness and limitations of population and habitat monitoring protocols, indicators and metrics; sampling design approaches for the distribution of monitoring effort in time and space; analytical approaches to the evaluation of monitoring data, information and programs; effective data management and communication designs that support the use, standardization and compilation of implementation, compliance, status, trends and effectiveness monitoring data by regional data generators and decision makers; and finally the design and implementation of watershed-scale restoration actions to maximize both the biological impact and associated learning opportunities resulting from the design and implementation strategy.

Through its work to date, ISEMP has developed expertise in the coordination and implementation of large-scale monitoring data collection programs. Applying this experience, ISEMP coordinates the installation, maintenance and calibration of in-stream PIT tag arrays across the Snake River basin and is designing and coordinating the implementation of a Columbia River basin-wide stream habitat status and trends monitoring. These programmatic implementation facets of ISEMP leverage previous experience with logistics and social factors to effectively implement comprehensive, standardized monitoring research and development at an unprecedented scale.  

This contract is one of several contracts that will implement this project.  Each contract is responsible for an end of contract progress report.  Additionally, a project level "synthesis report" will also be produced under this project and data and analysis from this contract will be utilized in the production of that project level report.  The synthesis report is a deliverable under the Terraqua contract (not this contract) under this project.  

In order to coordinate among Project elements, the need for any changes in scope that may arise during the implementation of this SOW will be communicated to NOAA Fisheries and Terraqua, Inc. (by contacting Chris Jordan (1 541 754 4629) and Mike Ward (509-486-2426)).   Actual changes to this SOW must be approved by BPA.This contract will support the overall project in the following manner:

The Cascadia Conservation District (CCD) offers support to other agencies as part of the larger project in the form of landowner coordination and agency coordination.  Specifically, the District coordinates outreach to private landowners, and facilitates landowners and cooperating agencies getting the appropriate information based on the needs of each entity (agency or private landowners).  For landowner coordination during habitat and fish monitoring surveys, private sites on the list are identified and appropriate landowners along these sections of stream are contacted by the District to ensure agency staff access will be possible and allowed by the landowner.  The purpose of the survey is explained to the landowner and permission to access the stream at specific locations is requested. A database is developed for the survey and maps are created of each site for the appropriate agency conducting the survey.  The District serves as the contact point for questions from landowners about the purpose of the survey and for any special requirements specific landowners may have for agency staff to be aware of during the visit to a private site.  The work under this contract is coordinated through Terraqua, Inc. and NOAA Fisheries, entities that also implement actions under this project.

This contract includes funding support for a position at the Cascadia Conservation District which is essential to the successful implementation of the Entiat Intensively Monitored Watershed (IMW).  The Entiat IMW is called for under the 2008 BiOp RPA 57.1 and seeks to determine whether a suite of instream habitat actions designed to improve habitat for listed salmonids and steelhead are effective.  The ISEMP has designed an implementation and monitoring experimental design for the Entiat IMW that calls for habitat restoration actions to be implemented in a spatially and temporally explicit manner.  This approach to action implementation and monitoring will require significant coordination, facilitation and support for the many agencies and stakeholders involved in restoring the Entiat River and the need for a person to head up this coordination effort was recognized by all those involved.  It was agreed that such a position should be housed at the CCD, with support from multiple agencies involved in the Entiat IMW, including the U.S. Bureau of Reclamation, Bonneville Environmental Foundation, and ISEMP.
  
Account Type(s):
Expense
Contract Start Date:
03/01/2013
Contract End Date:
02/28/2014
Current Contract Value:
$40,000
Expenditures:
$40,000

* Expenditures data includes accruals and are based on data through 28-Feb-2025.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
MarkerMarker
10 km
5 mi
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Christopher Beasley Quantitative Consultants Inc Yes Interested Party chris@qcinc.org (360) 620-2883
David Byrnes Bonneville Power Administration Yes COR dmbyrnes@bpa.gov (503) 230-3171
Susan Dretke Cascadia Conservation District Yes Technical Contact susan.dretke@wa.nacdnet.net (509) 664-9348
Peggy Entzel Cascadia Conservation District No Supervisor peggye@cascadiacd.org (509) 436-1601
Chris Fryefield Bonneville Power Administration Yes Env. Compliance Lead cbfryefield@bpa.gov (503) 230-4187
Chris Jordan National Oceanic and Atmospheric Administration Yes Technical Contact chris.jordan@noaa.gov (541) 754-4629
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Pamela Nelle Terraqua, Inc. Yes Administrative Contact pamela@terraqua.biz (509) 885-8143
Michael Rickel Cascadia Conservation District Yes Contract Manager miker@cascadiacd.org (509) 436-1601x103
Jason Sims Cascadia Conservation District No Interested Party jasons@cascadiacd.org (509) 436-1601
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Michael Ward Terraqua, Inc. Yes Interested Party mike@terraqua.biz (509) 486-2426


Viewing 6 of 6 Work Statement Elements
Sort Order
WSEV ID
WE ID
Work Element Name
Title
Description
WSE Effective Budget
% of Total WSE Effective Budget
WSE Start
WSE End
A111430185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.$4001.00%07/01/201302/28/2014
B111431191Watershed CoordinationEntiat IMW Coordination by All-Things-Entiat personnelThe agencies and stakeholders involved in restoring the Entiat River subbasin have endorsed the Entiat Intensively Monitored Watershed (IMW), an approach that calls for habitat restoration actions to be implemented in a spatially and temporally explicit manner (an Entiat IMW is required under the 2008 BiOp RPA 57.1 and seeks to determine whether a suite of instream habitat actions designed to improve habitat for listed salmonids and steelhead are effective). This approach to restoration action implementation and monitoring requires significant coordination, facilitation and support for the many agencies and stakeholders involved in restoring the Entiat River. This work element supports a technical and coordination position at the CCD that is essential to the successful implementation of the Entiat IMW. The purpose of this position is to provide technical and coordination assistance for the implementation of the Entiat IMW in support of the Entiat Watershed Planning Unit. Duties of this position include: 1. Project Partners Coordination This position will oversee the implementation of the Entiat IMW. This will require keeping partners informed, overseeing, supporting, and facilitating the decision making processes for the Entiat, and acting with the authority of a program leader and taking responsibility to facilitate decision making when consensus isn't readily reached. 2. Project Figurehead for Entiat IMW a. This position will provide a single point of contact regarding monitoring, project implementation, outreach, and project design work in the Entiat and will disseminate information and provide outreach to a broad range of Entiat stakeholders. b. The position will communicate effectively with landowners in the Entiat to keep them apprised of activities under the IMW and other partners’ work as it relates to the Entiat IMW and work to recruit new landowners and increase support for the Entiat IMW. c. Serve as a spokesperson for all aspects of Entiat IMW and coordinate the updates to the Entiat Implementation Schedule in partnership with the Upper Columbia Implementation Team Leader and various other requests from private, state and federal partners. 3. ISEMP and UCSRB Coordination This position will work with the ISEMP and the UCSRB to implement the IMW framework to advance project implementation, monitoring and adaptive management efforts in the Entiat a. Coordinate with ISEMP team and support all aspects of the Entiat IMW. b. Take responsibility to develop the Entiat IMW outreach letter (up to 2 per year) per BPA contract—and mail it to key stakeholders c. Interface as opportunities arise (public meetings) with landowners to further the Entiat IMW in conjunction with the Wenatchee/Entiat ISEMP coordinator.$25,51063.78%03/01/201302/28/2014
C11143299Outreach and EducationWenatchee and Entiat CHaMP Status and Trend Monitoring OutreachOutreach and education to specific landowners about habitat and fish surveys and request access permission to conduct physical habitat and fish surveys on private land. Track status of site evaluation, track requests from landowners regarding accessing property and final disposition of site using champmonitoring.org. Private landownership may limit access to individual sites. Prior to sampling sites that require access through private lands, access permission must be obtained directly from the landowner. Private landowner permission must be clearly documented. Access conditions may vary from year-to-year and sites that are scheduled for revisiting may need to be re-evaluated prior to each visit.$9,86224.66%05/01/201310/31/2013
D111433119Manage and Administer ProjectsManager and Administer ContractCovers work by the contractor to manage and administer on the ground efforts associated with the project. Also covers administrative work in support of on the ground efforts and in support of BPA's programmatic requirements such as monthly Pisces reports, metric reporting, financial reporting (e.g., accruals), and development of an SOW package (includes draft SOW, budget, spending plan, and property inventory).$3,8289.57%03/01/201302/28/2014
E111434132Produce Progress (Annual) ReportSubmit CCD final (annual) report for the period of performanceA final (annual) report will be prepared for this contract following the guidance listed under the "deliverable specification" section. Report covers current contract period, March 2012 through February 2013.$4001.00%10/01/201302/28/2014
F113997132Produce Progress (Annual) ReportAnnual FCRPS BiOp RM&E reportsUnder this contract, the Cascadia Conservation District will collaborate with ISEMP to provide the results of this work will be coordinated, compiled, and submitted to BPA by Terraqua Inc., using the BPA-supplied reporting templates for the RME and RPA reports (both the RM&E Technical Report Template and Annual RPA report will be generated at the project, or ISEMP, level). Each contract holder within the project will provide the necessary information to complete these reports, and the overall report production and completion will be coordinated and delivered as part of the Terraqua contract under this project[(By March 1st each year).$00.00%09/01/201302/28/2014
      
$40,000
   

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Communicate Coordination of Entiat habitat restoration project monitoring B: 191. Entiat IMW Coordination by All-Things-Entiat personnel 02/28/2014 02/28/2014
Complete site list in champmonitoring.org C: 99. Wenatchee and Entiat CHaMP Status and Trend Monitoring Outreach 10/31/2013 10/31/2013
SOW, reports and documents to maintain contract D: 119. Manager and Administer Contract 02/28/2014 02/28/2014
Final (annual) report to NOAA Fisheries and BPA E: 132. Submit CCD final (annual) report for the period of performance 02/28/2014 02/28/2014

Viewing of Implementation Metrics
Loading...
Sort Order
WE ID
Work Element Name
Title
Description
Metric ID
Metric
End Fiscal Year
Planned
Actual
Contractor Comments
All Measures
Annual Progress Report Measures
Populations
Viewing of Environmental Metrics Customize
Loading...
WSE ID
WSE Start
WSE End
WE ID
Title
WSE Progress
Study Plan
Protocol
Category
Subcategory
Focus 1
Focus 2
Specific Metric Title

Primary Focal Species Work Statement Elements

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 03/01/2013
B 191 Entiat IMW Coordination by All-Things-Entiat personnel 03/01/2013
C 99 Wenatchee and Entiat CHaMP Status and Trend Monitoring Outreach 03/01/2013
D 119 Manager and Administer Contract 03/01/2013
E 132 Submit CCD final (annual) report for the period of performance 03/01/2013
F 132 Annual FCRPS BiOp RM&E reports 03/01/2013