Contract 60836: 1987-100-01 EXP UMATILLA ANAD FISH HAB - CTUIR
Project Number:
Title:
Umatilla Anadromous Fish Habitat-Umatilla Tribe
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Umatilla 100.00%
Contract Number:
60836
Contract Title:
1987-100-01 EXP UMATILLA ANAD FISH HAB - CTUIR
Contract Continuation:
Previous: Next:
57257: 1987-100-01 EXP UMATILLA ANAD FISH HAB - CTUIR
  • 64560: 1987-100-01 EXP UMATILLA ANAD FISH HAB - CTUIR
Contract Status:
Closed
Contract Description:
The Confederated Tribes of the Umatilla Indian Reservation (CTUIR) propose ongoing fish habitat protection, restoration and enhancement, maintenance, and monitoring activities under the CTUIR Umatilla Anadromous Fish Habitat Project (198710001) to achieve the aquatic biological objectives and strategies and management plans established in the Umatilla Subbasin Plan (NPCC, 2004) and the Northwest Power and Conservation Council (NPCC) Fish and Wildlife Program (NPPC 2000).

The Umatilla Anadromous Fisheries Habitat Project (UAFHP) is an ongoing effort to protect, enhance, and restore functional floodplain, channel, and watershed processes to provide sustainable and healthy habitat for aquatic species in the Umatilla River Basin, including Threatened Mid-Columbia summer steelhead.  Project work further supports the CTUIR Department of Natural Resource ecological (River Vision 2008) and First Foods mission statements to sustain production.

The following is an agreement between BPA and CTUIR to provide funds for implementing habitat enhancement actions in the Umatilla River Basin.
Account Type(s):
Expense
Contract Start Date:
02/01/2013
Contract End Date:
01/31/2014
Current Contract Value:
$1,598,293
Expenditures:
$1,598,293

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Richard Christian Umatilla Confederated Tribes (CTUIR) Yes Contract Manager richardchristian@ctuir.org (541) 429-7283
Katey Grange Bonneville Power Administration Yes Env. Compliance Lead kcgrange@bpa.gov (503) 230-4047
Brenda Heister Bonneville Power Administration Yes Contracting Officer bsheister@bpa.gov (503) 230-3531
Gary James Umatilla Confederated Tribes (CTUIR) Yes Supervisor garyjames@ctuir.org (541) 429-7285
Michael Lambert Umatilla Confederated Tribes (CTUIR) Yes Contract Manager mikelambert@ctuir.org (541) 429-7240
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Scott O'Daniel Umatilla Confederated Tribes (CTUIR) Yes Technical Contact scottodaniel@ctuir.org (541) 429-7452
Tracey Yerxa Bonneville Power Administration Yes COR tyerxa@bpa.gov (503) 230-4738


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Upload SOW, budget, property inventory for upcoming contract period to Pisces. B: 119. Manage and Administer Project 11/01/2013 11/01/2013
Receipt of environmental compliance clearance on project work elements from BPA C: 165. Produce Environmental Compliance Documentation 01/31/2014 01/31/2014
List of final projects E: 114. CTUIR Umatilla Subbasin Restoration Coordination 01/31/2014 01/31/2014
Provide technical input and summaries to enhance or protect natural resources in the subbasin. F: 122. Review and provide technical input on issues and topics that affect the areas natural resource 01/31/2014 01/31/2014
Coordinate watershed association activities G: 191. Umatilla River Watershed coordination duties 01/31/2014 01/31/2014
Complete outreach and education activities H: 99. Public Outreach and Education 01/31/2014 01/31/2014
Maximize survival of native vegetation in enhancement project areas I: 197. Maintain vegetation and control noxious weeds in project areas within the Umatilla River Basin 01/31/2014 10/31/2013
Complete scheduled tree and shrub plantings in project areas J: 47. Supplement riparian areas of existing and new projects with additional vegetation 01/31/2014 12/20/2013
Maintain proper operation of instream habitat structures K: 186. Inspect and maintain function of instream improvement structures 01/31/2014 01/31/2014
Maintenance of land or structures associated with conservation easements L: 186. Maintenance of habitat features associated with project conservation easements 01/31/2014 01/31/2014
Complete levee removal floodplain enhancements to Meacham creek M: 180. Enhance Floodplain Connectivity and Function via Levee Setback on Meacham Creek, RM's 6-8.5 Phase I 01/31/2014 12/13/2013
Complete log structures for stability and habitat complexity. N: 29. Meacham Creek Floodplain Restoration and In-stream Enhancement, RM's 6-8.5 Phase II 09/30/2013 08/15/2013
Complete off-channel and side-channel development and enhancement. O: 30. Create and Enhance Side- and Off- Channel Habitat in Meacham Creek, RM's 6-8.5 Phase II 11/30/2013 08/15/2013
Maintain 355 acres (61 riparian, 294 upland) in project area P: 197. Enhance native vegetation growth in the B&G Resources Property, Umatilla River (RM 41-44) 11/30/2013 11/30/2013
Incorporate project effectiveness and regional data into project activities and annual BPA reporting Q: 115. Field Data Collection 01/31/2014 01/31/2014
Samples analyzed and data uploaded to CTUIR water quality data base R: 157. Meacham Creek Water Quality ISCO Sampling and Analysis 01/31/2014 01/31/2014
Written summary report describing the 2012 findings compared to previous work. S: 157. Macroinvertebrate study for evaluating Meacham Creek restoration effectiveness 01/31/2014 01/31/2014
Upload about 150 project effectiveness photo point photos to CTUIR data depository. T: 157. Project Effectiveness Photo Point Monitoring 01/31/2014 01/31/2014
A summary report with data analysis and findings will be incorporated into the annual report. U: 157. Geomorphic-Hyporheic Flow Study on Meacham Creek 01/31/2014 01/31/2014
USGS posted real-time accurate instantaneous stream flow data V: 157. Meacham Flow/Hydrology Monitoring (USGS) 01/31/2014 01/31/2014

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 2 instances of WE 197 Maintain/Remove Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 5 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 2 instances of WE 197 Maintain/Remove Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 5 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 197 Maintain/Remove Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 5 instances of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/01/2013
B 119 Manage and Administer Project 02/01/2013
C 165 Produce Environmental Compliance Documentation 02/01/2013
D 132 Produce Annual Progress Report for the FY12 period (Feb2012-Jan2013) 02/01/2013
E 114 CTUIR Umatilla Subbasin Restoration Coordination 02/01/2013
F 122 Review and provide technical input on issues and topics that affect the areas natural resource 02/01/2013
G 191 Umatilla River Watershed coordination duties 02/01/2013
H 99 Public Outreach and Education 02/01/2013
I 197 Maintain vegetation and control noxious weeds in project areas within the Umatilla River Basin 03/18/2013
J 47 Supplement riparian areas of existing and new projects with additional vegetation 02/25/2013
K 186 Inspect and maintain function of instream improvement structures 03/18/2013
L 186 Maintenance of habitat features associated with project conservation easements 02/01/2013
M 180 Enhance Floodplain Connectivity and Function via Levee Setback on Meacham Creek, RM's 6-8.5 Phase I 05/02/2013
N 29 Meacham Creek Floodplain Restoration and In-stream Enhancement, RM's 6-8.5 Phase II 05/02/2013
O 30 Create and Enhance Side- and Off- Channel Habitat in Meacham Creek, RM's 6-8.5 Phase II 05/02/2013
P 197 Enhance native vegetation growth in the B&G Resources Property, Umatilla River (RM 41-44) 03/18/2013
Q 115 Field Data Collection 03/15/2013
R 157 Meacham Creek Water Quality ISCO Sampling and Analysis 02/26/2013
S 157 Macroinvertebrate study for evaluating Meacham Creek restoration effectiveness 03/15/2013
T 157 Project Effectiveness Photo Point Monitoring 02/01/2013
U 157 Geomorphic-Hyporheic Flow Study on Meacham Creek 02/01/2013
V 157 Meacham Flow/Hydrology Monitoring (USGS) 02/01/2013