A | 152321 | 185 | Produce CBFish Status Report | Periodic Status Reports for BPA | The Contractor shall report on the status of milestones and deliverables in Pisces. Reports shall be completed either monthly or quarterly as determined by the BPA COTR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR. | $4,000 | 3.33% | 01/01/2015 | 01/31/2016 |
B | 152322 | 119 | Manage and Administer Projects | Manage and Administer Projects | Develop BPA contract materials for FY15, manage payment requests, providing timely reports and invoices to BPA. | $18,000 | 15.00% | 10/01/2014 | 01/31/2016 |
C | 152323 | 191 | Watershed Coordination | Willamette Coordination and HTT/RRT Meeting Facilitation | Attend various meetings dealing with fish and wildlife issues in the Willamette, including but not limited to: Willamette Wildlife MOA meetings, Willamette BiOp WATER meetings, and meetings with tribes, state and federal agencies, non-governmental organizations, and private funders.
Schedule HTT and RRT meetings. Prepare and disseminate any necessary information (agendas, handouts, etc) for HTT and RRT meetings. Attend and take notes at HTT and RRT meetings, and disseminate meeting notes post-meetings. | $35,000 | 29.17% | | 01/31/2016 |
D | 152324 | 114 | Identify and Select Projects | Facilitate the annual selection of FY15 HTT projects | Coordinate the project solicitation for SIP/HTT funding. Schedule and facilitate Willamette BiOp Habitat Technical Team (HTT) and Regional Review Team (RRT) review and selection of projects. Communicate with project applicants through the review and selection process. | $7,000 | 5.83% | 10/01/2014 | 11/30/2014 |
E | 152325 | 114 | Identify and Select Projects | Facilitate the annual selection of FY16 HTT projects | Coordinate the project solicitation for SIP/HTT funding. Schedule and facilitate Willamette BiOp Habitat Technical Team (HTT) and Regional Review Team (RRT) review and selection of projects. Communicate with project applicants through the review and selection process. | $42,000 | 35.00% | 07/14/2015 | 10/31/2015 |
F | 152326 | 132 | Produce Progress (Annual) Report | Submit Progress Report for the period 2/1/2012 - 9/30/2014 | The progress report summarizes the project goal, objectives, hypotheses, completed and uncompleted deliverables, problems encountered, lessons learned, and long-term planning. Examples of long-term planning include future improvements, new directions, or level of effort for contract implementation, including any ramping up or ramping down of contract components or of the project as a whole.
Progress reports must conform to BPA guidelines. See the ''formatting guidelines'' link at the Technical Reports and Publications page: https://www.cbfish.org/Help.mvc/GuidanceDocuments. | $7,000 | 5.83% | 10/01/2014 | 09/30/2015 |
G | 152327 | 132 | Produce Progress (Annual) Report | Begin Drafting the Progress Report for the period 10/1/2014 - 9/30/2015 | The progress report summarizes the project goal, objectives, hypotheses, completed and uncompleted deliverables, problems encountered, lessons learned, and long-term planning. Examples of long-term planning include future improvements, new directions, or level of effort for contract implementation, including any ramping up or ramping down of contract components or of the project as a whole.
Progress reports must conform to BPA guidelines. See the ''formatting guidelines'' link at the Technical Reports and Publications page: https://www.cbfish.org/Help.mvc/GuidanceDocuments. | $7,000 | 5.83% | 09/01/2015 | 01/31/2016 |