Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 73548 REL 11: 2007-224-00 EXP CCT METHOW RESTORATION
Project Number:
Title:
Okanogan Subbasin Habitat Implementation Program (OSHIP)
Stage:
Complete
Area:
Province Subbasin %
Columbia Cascade Okanogan 100.00%
Contract Number:
73548 REL 11
Contract Title:
2007-224-00 EXP CCT METHOW RESTORATION
Contract Continuation:
Previous: Next:
73139: 2007-224-00 EXP CCT METHOW RESTORATION
Contract Status:
Closed
Contract Description:
This contract is to conduct aquatic habitat protection/restoration projects in the Methow Subbasin.  Projects to be implemented will primarily emphasize benefits to ESA listed spring chinook, summer steelhead, and bull trout and secondarily to other salmonids and Pacific lamprey. Work will include regular attendance of coordination meetings with project sponsors and oversight groups to ensure that work is conducted consistent with established needs and in coordination with other existing restoration efforts.

Work under this contract cycle will include: side channel connection to increase rearing habitat and habitat complexity; culvert assessments for fish passage determination; instream enhancements to increase aquatic complexity; irrigation system improvements to increase efficiency and reduce instream surface withdrawal; beaver relocation and beaver dam analog placement to promote an increase in salmonid rearing habitat as well as to increase base flows and reduce water temperatures during the summer months;  livestock exclusion (fencing) to protect riparian areas; road relocation and decommissioning to reduce sediment delivery to Beaver Creek ( Environmental Compliance portion only).
Account Type(s):
Expense
Contract Start Date:
07/01/2017
Contract End Date:
06/30/2018
Current Contract Value:
$1,762,359
Expenditures:
$1,762,359

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Roy Beaty Bonneville Power Administration Yes F&W Approver rebeaty@bpa.gov (503) 230-5213
Joseph Connor Bonneville Power Administration Yes COR jwconnor@bpa.gov (503) 230-3172
Chris Fisher Colville Confederated Tribes No Supervisor chris.fisher@colvilletribes.com (509) 422-7427
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Billy Gunn Colville Confederated Tribes Yes Administrative Contact billy.gunn@colvilletribes.com (509) 422-7740
Keith Kistler Colville Confederated Tribes Yes Interested Party keith.kistler@colvilletribes.com (509) 422-7429
Peter Lofy Bonneville Power Administration No Interested Party ptlofy@bpa.gov (503) 230-4193
Solomonn Marsh Bonneville Power Administration Yes Contracting Officer spmarsh@bpa.gov (503) 230-3943
Kary Nichols Colville Confederated Tribes No Interested Party kary.nichols@colvilletribes.com (509) 422-4782
Christopher Roper Bonneville Power Administration No CO Assistant cproper@bpa.gov (503) 230-3514
Tybee Sheidler Bonneville Power Administration No CO Assistant tasheidler@bpa.gov (503) 230-3820
John Stensgar, Jr Colville Confederated Tribes Yes Administrative Contact lj.stensgar.fnw@colvilletribes.com (509) 634-2109
Paul G. Wagner Colville Confederated Tribes Yes Contract Manager paul.wagner@colvilletribes.com (509) 380-3747
Elham Zolmajd-Haghighi Bonneville Power Administration No CO Assistant ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance Documentation A: 165. Produce Compliance Documentation 06/30/2018 06/30/2018
Methow Restoration Project Management B: 119. Project Management 06/30/2018 06/30/2018
Watershed coordination C: 191. Methow Subbasin Coordination 06/30/2018 06/30/2018
Projects selected for implementation D: 114. Project Identification and Selection Process 02/28/2018 02/28/2018
Large wood instream structure F: 29. Devany Aquatic Complexity 06/30/2018
Side Channel Re-connection G: 30. Devany Side Channel 06/30/2018
Silver Reach Instream Structures H: 29. Silver Reach Instream Enhancements Phase 2 06/30/2018
Irrigation Well I: 82. Runyan Irrigation Well 06/30/2018 06/11/2018
Beaver Dam Analogs J: 29. Mission Beaver Dam Analogs 06/30/2018
Beavers relocated to the Methow basin. K: 190. Beaver Relocation Project 06/30/2018 06/30/2018
Livestock Exclusion Fencing L: 40. Mission Livestock Exclusion 06/30/2018
Barkley Irrigation System Upgrade M: 203. Barkley Irrigation System Improvements 06/30/2018 06/30/2018
Progress Report for the period 7/1/16 - 6/30/17 N: 132. Submit Progress Report for the period 7/1/16 to 6/30/17 06/30/2018
Hydrogeologic Memo O: 141. Fort Production Well Phase 1 06/30/2018
Outreach and Education in the Methow Valley P: 99. Methow Valley Public Outreach 06/30/2018 06/30/2018
Acquisition Appraisal Q: 172. Acquisition Appraisal 06/30/2018

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 203 Install Water Conservation Measure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 82 Install Well
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 1 instance of WE 203 Install Water Conservation Measure
  • 1 instance of WE 82 Install Well
Coho (O. kisutch) - Unspecified Population
  • 1 instance of WE 203 Install Water Conservation Measure
  • 1 instance of WE 190 Remove, Exclude and/or Relocate Animals
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 203 Install Water Conservation Measure
  • 1 instance of WE 190 Remove, Exclude and/or Relocate Animals
  • 3 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 82 Install Well
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 190 Remove, Exclude and/or Relocate Animals
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Produce Compliance Documentation 07/01/2017
B 119 Project Management 07/01/2017
C 191 Methow Subbasin Coordination 07/01/2017
D 114 Project Identification and Selection Process 07/01/2017
E 185 Periodic Status Reports for BPA 07/01/2017
F 29 Devany Aquatic Complexity
G 30 Devany Side Channel
H 29 Silver Reach Instream Enhancements Phase 2
I 82 Runyan Irrigation Well 01/05/2018
J 29 Mission Beaver Dam Analogs 09/28/2017
K 190 Beaver Relocation Project 01/05/2018
L 40 Mission Livestock Exclusion 10/31/2017
M 203 Barkley Irrigation System Improvements 07/01/2017
N 132 Submit Progress Report for the period 7/1/16 to 6/30/17 07/01/2017
O 141 Fort Production Well Phase 1 07/01/2017
P 99 Methow Valley Public Outreach 07/01/2017
Q 172 Acquisition Appraisal 07/01/2017