A | 245118 | 119 | Manage and Administer Projects | Project Administration | Idaho Office of Species Conservation administration of project. Development of budgets, SOW, inventory, subcontracting, and financial oversight of contract. | $0 | 0.00% | 06/01/2024 | 05/31/2025 |
B | 245117 | 185 | Produce CBFish Status Report | Periodic Status Reports for BPA | The Contractor shall report on the status of milestones and deliverables in CBFish. Reports shall be completed either monthly or quarterly as determined by the BPA COR. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COR. | $0 | 0.00% | 10/01/2024 | 05/31/2025 |
C | 245119 | 172 | Conduct Pre-Acquisition Activities | Conduct pre-acquisition work and complete acquisition of Little Springs CE | This work element will be used to complete the pre-acquisition work for the Little Springs CE. | $2,883 | 100.00% | 06/01/2024 | 05/31/2025 |
D | 245120 | 132 | Produce Progress (Annual) Report | No progress report required for this contract | There is no progress report required for this Contract | $0 | 0.00% |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Effective implementation management and timely contract administration | A: 119. Project Administration | 05/31/2025 | 12/12/2024 | |
Complete purchase of conservation easement | C: 172. Conduct pre-acquisition work and complete acquisition of Little Springs CE | 05/31/2025 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Project Administration | |||||||
B | 185 | Periodic Status Reports for BPA | |||||||
C | 172 | Conduct pre-acquisition work and complete acquisition of Little Springs CE | |||||||