Effective implementation management and timely contract administration |
A: 119. Manage Restoration Projects |
|
03/31/2025 |
|
Final Permits / Final ESA |
B: 165. Environmental Compliance |
|
03/31/2025 |
|
Final Metrics |
C: 99. Conduct Field Education - Restoration - Salmonid Life Histories |
|
03/31/2025 |
|
Update (out-year) prioritized Habitat Project list: Upload to CBFish |
D: 114. Select habitat improvement actions and identify possible projects for next fiscal year |
|
10/15/2024 |
|
Deliverable - Updated Database |
E: 160. Update Project Database |
|
03/31/2025 |
|
Raw Data Deliverable |
F: 161. Create informal summary reports and maps |
|
03/31/2025 |
|
Meet Objective - Deliverable |
G: 122. Input to various Tribal planning and policy efforts |
|
03/31/2025 |
|
Produce accessible, error-checked datasets |
H: 157. Operate rotary screw traps for steelhead |
|
03/31/2025 |
|
Complete 3 pass surveys in Ahtanum and Satus Creeks. |
I: 157. Conduct steelhead and bull trout spawner surveys |
|
03/31/2025 |
|
Water temperature record. |
J: 157. Collect water temperature data |
|
03/31/2025 |
|
Discharge measurements |
K: 157. Collect discharge measurements |
|
03/31/2025 |
|
Redd distribution and adult abundance index |
L: 162. Analyze redd count data |
|
03/31/2025 |
|
Steelhead Outmigrantmetrics |
M: 162. Analyze Steelhead Outmigrant Data |
|
03/31/2025 |
|
Ahtanum irrigation diversion managed |
N: 186. Assist with the operation of diversions and screens on Ahtanum Creek |
|
03/31/2025 |
|
Toppenish and Simcoediversions managed |
O: 186. Assist with operation of diversions and screens on Toppenish Creek |
|
03/31/2025 |
|
Functioning fences, wells, stock tanks, cattle guards, and habitat improvements |
P: 186. Maintain stock tanks/livestock fences/improved springs |
|
03/31/2025 |
|
Maintenance of vegetation and photos |
Q: 198. Maintain vegetation |
|
03/31/2025 |
|
UPLOAD FINAL DELIVERABLES |
R: 175. Satus Creek RM 7.75 - 34.5 Design Selection & Design |
|
03/31/2025 |
|
Aquatic and floodplain complexity actions completed |
S: 29. Satus Creek RM 23 - Wood Implementation (Phase 1 SubReach 3) |
|
11/25/2024 |
|
Construction Management Complete |
T: 100. Satus Creek RM 23 - Construction Management |
|
10/31/2024 |
|
Completed Large Wood Structures and Placement |
U: 30. Satus Creek RM 23 - Realign, connect, and/or create channel |
|
12/31/2024 |
|
As Built / Photos |
V: 29. Install Beaver Dam Analogs: NF Logy Phase 2 |
|
12/01/2024 |
|
As-Built Report / Photos |
W: 29. BDAs Panther Creek Phase Three |
|
12/31/2024 |
|
Lawrence Ditch Fish Screen Installed. PCF completed with photos. |
X: 208. Lawrence Ditch Fish Screening (CARRIED FORWARD FROM REL 283 WE Y) |
|
03/31/2025 |
|
Final Design Packet - Stamped |
Y: 175. 3-Way Phase II Levee Removal - Design Continuation |
|
03/31/2025 |
|
Deliverable: An accessible, error-checked data set with metadata |
Z: 162. Wakish Small Contract |
|
03/31/2025 |
|
Status Report |
AA: 174. Interfluve - On Call |
|
02/03/2025 |
|
Assessment and Alternatives Analysis Document Coordinated and Completed |
AB: 174. Ahtanum Restoration and Alternatives Analysis RM 18-13 |
|
01/31/2025 |
|
FINAL DESIGN PLAN SET |
AC: 175. Toppenish Wood Loading RM 45 - 51- Produce Designs |
|
03/28/2025 |
|
Construction Management Complete |
AD: 100. Pom Pom RM 40 Bridge and Channel Construction - Construction Management |
|
03/31/2025 |
|
Completed bridge installation, channel construction, and placement of three high flow culverts |
AE: 30. Pom Pom RM 40 Bridge Construction and Channel Alignment |
|
03/31/2025 |
|
Completed Annual Report |
AG: 132. Produce Project Annual Report for FY23 Mar23-Feb24 |
|
03/31/2025 |
|