View and print project details including project summary, purpose, associations to Biological Opinions, and area. To learn more about any of the project properties, hold your mouse cursor over the field label.
Province | Subbasin | % |
---|---|---|
Intermountain | Pend Oreille | 100.00% |
To view all expenditures for all fiscal years, click "Project Exp. by FY"
To see more detailed project budget information, please visit the "Project Budget" page
Annual Progress Reports | |
---|---|
Expected (since FY2004): | 0 |
Completed: | 0 |
On time: | 0 |
Status Reports | |
---|---|
Completed: | 0 |
On time: | 0 |
Avg Days Late: | None |
Name | Role | Organization |
---|---|---|
Virgil Watts III | Project Manager | Bonneville Power Administration |
Matthew Berger | Project Lead | Kalispel Tribe |
Ray Entz | Supervisor | Kalispel Tribe |
Joe Maroney | Interested Party | Kalispel Tribe |
Jolene Seymour | Administrative Contact | Kalispel Tribe |