RSS Feed for updates to Project 2007-092-00 - Restore Selway River Watershed Follow this via RSS feed. Help setting up RSS feeds?

Budget Transfers

Project 2007-092-00 - Restore Selway River Watershed

Show me decided transfers to/from:

Viewing 16 of 16 Decided Budget Transfers (All)
ID
Decision
Budget Decision Name
Acct FY
Acct Type
Project
Title
Proponent Orgs
Fund
Amount
Entered On
Entered By
Short Description
Rationale
  
76764/26/2007FY07-09 Solicitation Review2007Expense2007-092-00Restore Selway River WatershedNez Perce TribeGeneral$02/27/2007Richard BaumannFY07 BPA-approvedExpense Comment: Do not fund. BPA concurs with the rationale in the Council recommendation.
76814/26/2007FY07-09 Solicitation Review2008Expense2007-092-00Restore Selway River WatershedNez Perce TribeGeneral$02/27/2007Richard BaumannFY08 BPA-approvedExpense Comment: Do not fund. BPA concurs with the rationale in the Council recommendation.
76844/26/2007FY07-09 Solicitation Review2009Expense2007-092-00Restore Selway River WatershedNez Perce TribeBiOp FCRPS 2008 (non-Accord)$02/27/2007Richard BaumannFY09 BPA-approvedExpense Comment: Do not fund. BPA concurs with the rationale in the Council recommendation.
194476/9/2011Various Budget Transfers 6/9/20112011Expense2007-092-00Restore Selway River WatershedNez Perce TribeBiOp FCRPS 2008 (non-Accord)$200,0006/9/2011Christine ReadMove $200,000 (expense) from BiOp fund to Project BudgetThis transaction moves $796,900 (expense) from BiOp fund to Project Budget. The goal of this project is to restore the physical and biological characteristics of the Selway River watershed to provide quality habitat for anadromous and resident fish (under RPA 35). This project was reviewed by ISRP and met scientific review criteria. The project was recommended by Council at the May 11, 2011 meeting.
199407/19/2011FY12 initial planning budgets2012Expense2007-092-00Restore Selway River WatershedNez Perce TribeBiOp FCRPS 2008 (non-Accord)$200,0007/12/2011Christine ReadInitial FY12 BPA Planning Budget (Expense)FY12 budget from Tributary Habitat placeholder to satisfy BiOp targets in Selway River Watershed. Project will have two year contract beginning in FY12.
2328010/29/2012NPT FY13 Budget Upload2013Expense2007-092-00Restore Selway River WatershedNez Perce TribeBiOp FCRPS 2008 (non-Accord)$197,19310/12/2012Benjamin DickInitial FY13 BPA Planning Budget (Expense)FY12 Budget - $2,807 for Nez Perce Tribe contractual reduction
2346512/5/2012NPT Final Adjustments2013Expense2007-092-00Restore Selway River WatershedNez Perce TribeBiOp FCRPS 2008 (non-Accord)$1,25812/5/2012Benjamin DickIncrease project 2007-092-00 by $1,258 for NPT adjustmentBudget reflects baseline project budget of $200k. Small savings in GSA vehicle mileage and materials.
243398/6/2013FY14 Expense SOY upload2014Expense2007-092-00Restore Selway River WatershedNez Perce TribeBiOp FCRPS 2008 (non-Accord)$197,0007/25/2013Benjamin DickFY14 initial planning budget (expense)FY13 + restoration of $1549 negotiated reduction. FY14 budget is reduced by $3,000 to lower RM&E requirements for the programmatic action effectiveness approach for monitoring. Reduction should not reduce habitat work.
2487312/10/2013NPT budget upload Dec 6th2014Expense2007-092-00Restore Selway River WatershedNez Perce TribeBiOp FCRPS 2008 (non-Accord)($6,000)12/6/2013Benjamin DickReduce 2007-092-00 by $6,000 for FY14Reducing project 2007-092-00 by $6K for implentation and compliance reduction . Reduced funds will be transferred into the project 2002-068-00 starting in FY14. Transfer is permanent.
249301/9/2014NPT AEM adjustments2014Expense2007-092-00Restore Selway River WatershedNez Perce TribeBiOp FCRPS 2008 (non-Accord)$3,0001/9/2014Bryan MercierNez Perce Tribe AEM adjustmentNPT agreed to centralize AEM monitoring into a single project. This adjustment restores the habitat project funding to FY12 baseline less the AEM monitoring.
253456/4/2014FY15 SOY Expense Budgets2015Expense2007-092-00Restore Selway River WatershedNez Perce TribeBiOp FCRPS 2008 (non-Accord)$194,0005/28/2014Benjamin DickFY15 Initial Planning Budget (Expense)FY14 Budget No Inflation
2575311/10/2014November Increase Requests2014Expense2007-092-00Restore Selway River WatershedNez Perce TribeBiOp FCRPS 2008 (non-Accord)($148,886)11/7/2014Benjamin DickReschedule $148,886 from FY14 to FY15Rescheduling $148,886 of FY14 budget into FY15 for work that was not completed in the FY14 contract due to a wildfire that cut off access roads.
         
$1,185,301