Work Element 87: Prepare HEP Report - Published
WE Name:
87. Prepare HEP Report (Prepare HEP Report)
Work Category:
Habitat - Land Acquisition / Conservation Easement
WE Agreement Type:
Contracted
Status:
Expired
Definition:
Efforts leading to a report to present the findings of the Habitat Evaluation Procedure (HEP) survey conducted by the Regional HEP team.
WSE Description Template:
Effective Dates:
FY2005 to FY2023
Note on Expiration:
Work Phase:
planning/design
Sort Sequence:
8.01
Focal Species Required:
Yes
RM&E Metadata Required:
No
Finite or Recurring:
Recurring
Is BPA Internal:
No
Is Contracted:
Yes
Is Cost Share:
No
Is Construction:
No


Deliverable Status:
Required
Default Deliverable Desc:
Report
Potential Deliverables:
  • HEP Report attached in Pisces

  • Rule 1 (Location of Work): If you are preparing HEP reports for multiple locations, you may lump these under a single work element. However, you may wish to break the work into separate work elements if it provides clarity or better supports project management.

    Examples:

    Option 1 (lumping):

    WE: 87. Prepare HEP Report (Expired)
    WE Title: Prepare HEP report for Thompson Unit, which includes Bradley, Greene, and Douglas properties.

    Option 2 (splitting):

    WE: 87. Prepare HEP Report (Expired)
    WE Title: Prepare HEP report for Bradley property.

    WE: 87. Prepare HEP Report (Expired)
    WE Title: Prepare HEP report for Greene property.

    WE: 87. Prepare HEP Report (Expired)
    WE Title: Prepare HEP report for Douglas property.


Milestone Title
Type
Deliverable?
Description

Prepare cover type maps
Suggested
No
Assist HEP Team with survey
Suggested
No
Obtain HEP data from Regional HEP team
Suggested
No
Perform analysis on HEP data
Suggested
No
Submit draft HEP report to BPA for review
Suggested
No
Upload final HEP report to BPA-s website
Suggested
No


Location Requirement Type:
Location Work Site in CBFish
Number of Locations:
1 - 100
Location Guidance:
Identify point(s) at approximate center of parcel(s) where activities will take place. The location point must be the same for all associated TBL Work, Conduct Pre-Acquisition Activities, and Land Purchase work elements. If an associated work element and its location are already in Pisces, click the "Link" button to synchronize locations. You may enter or link more than one point for this work element.

Applicability and status of the following environmental compliance requirements can be found on the Environmental Compliance tab for that work element in your SOW for all 2007 contracts forward. BPA's Environmental staff will update and maintain this information in CBFish in real time, so that you can check the status of environmental compliance on your project at any time.

Note: Many of the fields are set to auto-load in CBFish, but the settings will be reviewed by BPA's Environmental staff prior to the contract being finalized, and may be revised depending on the specific circumstances.

  • National Environmental Policy Act (NEPA)
    NEPA coverage for this work element will be determined by BPA's Environmental staff and could include an Environmental Impact Statement (EIS), Environmental Assessment (EA), Record of Decision to an existing EIS, or Categorical Exclusion.

  • Endangered Species Act (ESA)
    ESA consultation is typically not required for this work element.

  • National Historic Preservation Act (NHPA)
    NHPA Section 106 consultation is typically not required for this work element.

  • Public Involvement
    Public involvement is typically not required for this work element.


Reports that Use this Work Element

This work element and its metrics are used in measures in the following reports. These PDF reports are generated dynamically, always showing you the most up to date information. Most of them also have links to download the underlying data sets to structured text or Excel format.

Stats and Overview

Number of active contracts using Work Element #87 by FY

Top 5 BPA Project Managers using this Work Element:
(by number of current contracts)
Virgil Watts III 33
Dorothy Welch 11
Joe Deherrera (Inactive) 7
Jay Marcotte (Inactive) 7
Sandra Fife (Inactive) 7
Average Work Element Budget: $20,433
Average Duration: 11 months