This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $0 | $0 | Covered under WE F |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 2/1/2016 | 2/14/2016 | Active | Joseph Connor (Inactive) | 11/19/2015 7:03:10 PM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff (completion can be based on pre-existing environmental documentation from BPA). | |||||||
B | Sampling juvenile salmonids in side channels of the Entiat River | 3/1/2016 | 10/31/2016 | Concluded | Pamela Nelle | 11/20/2015 11:15:45 AM | |
Description: The USFWS will be tagging juvenile anadromous salmonids using Passive Integrated Transponder (PIT) tags at up to 7 off-channel habitats in the Entiat River mainstem as part of ISEMP's Entiat IMW experimental design. Spring Chinook and steelhead captured will be checked for the presence of a passive integrated transponder (PIT) tag, if not tagged they will be anesthetized, and have length and weight measurements recorded and life stage identified prior to being revived and released at the point of capture. Any spring Chinook and steelhead not previously PIT tagged will be tagged with either a 12 mm or 8.5 mm tag dependent upon their size (fork-length). Scale samples will be collected from a subset of steelhead collected. | |||||||
C | DELIV | PIT tagged juvenile Chinook salmon and steelhead | 12/31/2016 | Concluded | Pamela Nelle | 11/20/2015 11:20:31 AM | |
Description: Tagging files generated from mark-recapture sampling will be submitted to PTAGIS within 14 days following the sampling period. Notice will be provided to BPA and Terraqua, Inc. when the data has been uploaded . The contractor will be responsible for all quality assurance/quality control steps necessary to ensure that data is properly collected and entered. |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1464. Primary R, M, and E Focal Strategy [Population Status, Hydrosystem, Tributary Habitat, Estuary/Ocean, Harvest, Hatchery, Predation, Multiple Strategies] | Population Status | Population Status | |||
1472. Primary R, M, and E Type [Status and Trend Monitoring, Action Effectiveness Research, Uncertainties Research, Project Implementation/ Compliance Monitoring] | Action Effectiveness Monitoring | Action Effectiveness Monitoring | |||
1495. Secondary R, M, and E Focal Strategy [Population Status, Hydrosystem, Tributary Habitat, Estuary/Ocean, Harvest, Hatchery, Predation, Multiple Strategies] | Tributary Habitat | Tributary Habitat |
Work Site ID | Latitude | Longitude | State | County | Province | Subbasin |
---|---|---|---|---|---|---|
90213 | 47.68885 | -120.324154 | Washington | Chelan | Columbia Cascade | Entiat |
90302 | 47.888809 | -120.444574 | Washington | Chelan | Columbia Cascade | Entiat |
90305 | 47.664376 | -120.263386 | Washington | Chelan | Columbia Cascade | Entiat |
90309 | 47.669376 | -120.294285 | Washington | Chelan | Columbia Cascade | Entiat |
90311 | 47.673335 | -120.309262 | Washington | Chelan | Columbia Cascade | Entiat |
90314 | 47.696274 | -120.322437 | Washington | Chelan | Columbia Cascade | Entiat |
90318 | 47.698758 | -120.320377 | Washington | Chelan | Columbia Cascade | Entiat |
90320 | 47.883801 | -120.436893 | Washington | Chelan | Columbia Cascade | Entiat |