This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $7,986 | $2,000 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 7/1/2016 | 7/31/2016 | Concluded | Joseph Connor (Inactive) | 4/23/2016 4:46:22 PM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff (completion can be based on pre-existing environmental documentation from BPA). | |||||||
B | Suggested | Discuss HIP3 ESA coverage with BPA EC lead; obtain HIP3 risk determination | 7/1/2016 | 7/31/2016 | Concluded | Joseph Connor (Inactive) | 4/23/2016 4:46:22 PM |
Description: The EC Lead will determine if work under this work element may be able to have full ESA-coverage (NMFS & USFWS) under the 2013 Habitat Improvement Program Biological Opinion (HIP3). The HIP3 has expanded coverage for projects that may pose a moderate to high risk of impacting an ESA-listed species or critical habitat that would normally require a Biological Assessment. For work that qualifies, projects will undergo a review by the BPA-internal Restoration Review Team (RRT). Before conceptual design commences, contact the EC lead for HIP3 consideration, instruction, and information needs and requirements for coverage eligibility. The HIP3 activity categories and risk criteria are located in the “Note” section of the work element background page here:https://www.cbfish.org/WorkElement.mvc/Summary/165 . | |||||||
C | Implement Beaver Dam Analog based stream restoration actions | 7/1/2016 | 6/30/2017 | Concluded | Chris Jordan | 4/29/2016 1:55:50 PM | |
Description: Implement Beaver Dam Analog based stream restoration actions in coordination with field crews from Eco Logical Research - 2016 contract 71203. Other locations where BDA based work will be supported with design and construction actions are: Bear Creek (Bridge Creek, Lower John Day, with Watershed Council), Pine Creek (Lower John Day, with CTWSR), Camp Creek (Middle Fork John Day, with USFS), South Fork Crooked River (with Watershed Council and OSU). Other project opportunities may develop, and will be coordinated with COTR and BPA RME team as they arise. | |||||||
D | Design Beaver Dam Analog based stream restoration actions | 7/1/2016 | 6/30/2017 | Concluded | Chris Jordan | 4/29/2016 1:55:50 PM | |
Description: Participate in field visits and coordination meetings with collaborators to design Beaver Dam Analog (BDA) based stream restoration actions in watersheds of the interior Columbia River basin to support recovery of ESA listed stocks of anadromous salmonids. Other locations where BDA based work will be supported with design and construction actions are: Bear Creek (Bridge Creek, Lower John Day, with Watershed Council), Pine Creek (Lower John Day, with CTWSR), Camp Creek (Middle Fork John Day, with USFS), South Fork Crooked River (with Watershed Council and OSU). Other project opportunities may develop, and will be coordinated with COTR and BPA RME team as they arise. | |||||||
E | DELIV | In-water work -- Beaver Dam Analogs | 6/30/2017 | Concluded | Chris Jordan | 4/29/2016 1:56:09 PM | |
Description: Install FY16 component of Beaver Dam Analog structures consisting of repairing previous years' component of Beaver Dam Support structures as described in the BCRMP Biological Opinion. Support the design and implementation of Beaver Dam Analog based restoration in watersheds of the Columbia River Basin. |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1387. # of miles of stream with improved complexity | 1.00 | 0.00 | miles of stream with improved complexity | Habitat Miles | |
1389. Start latitude of treated stream reach | 44.591313 | 44.591313 | |||
1390. End latitude of treated stream reach | 44.591313 | 44.591313 | |||
1391. Start longitude of treated stream reach | -120.198938 | -120.198938 | |||
1392. End longitude of treated stream reach | -120.198938 | -120.198938 | |||
1579. # of deflector/barb structures installed for only stabilization | 0 | structures installed | |||
1587. # of log weir structures installed for only complexity | 10 | 0 | structures installed | ||
1748. # of pools created for only complexity | 10 | 0 | pools created |
Work Site ID | Latitude | Longitude | State | County | Province | Subbasin |
---|---|---|---|---|---|---|
29218 | 44.591313 | -120.198938 | Oregon | Wheeler | Columbia Plateau | John Day |