This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. 27178 (06/01/2006 - 06/23/2007) | $25,544 | $25,544 | ||
Work Element Budget (Current Performance Period) | $25,544 | $25,544 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | Environmental compliance requirements complete | 6/1/2006 | 6/1/2006 | Concluded | David Byrnes (Inactive) | 5/12/2007 2:51:16 PM | |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff (completion can be based on pre-existing environmental documentation from BPA). | |||||||
B | Data Collection (trap operation) | 6/1/2006 | 11/30/2006 | Concluded | David Byrnes (Inactive) | 5/12/2007 2:51:15 PM | |
Description: Daily counts of all species, fish size measured from at least the first 25 fish of each species captured daily, and efficiency trials conducted as numbers of fish will allow. Smolt trap will be installed between 2/28/2006 and 3/1/2006 under project number 1996-040-00 for the data collection occurring during 2006. | |||||||
C | Input Data | 12/1/2006 | 12/31/2006 | Concluded | David Byrnes (Inactive) | 5/12/2007 2:51:15 PM | |
Description: Complete data collection input in spreadsheet format. | |||||||
D | DELIV | Submission of Smolt trap data | 12/31/2006 | Concluded | David Byrnes (Inactive) | 5/12/2007 2:51:15 PM | |
Description: Daily counts of all species, fish size measured from at least the first 25 fish of each species captured daily, and efficiency trials conducted as numbers of fish will allow. Quality controlled raw data in spreadsheet format; Quality controlled georeferenced summarized data in spreadsheet format | |||||||
E | Install smolt trap (project #1996-040-00) | 3/1/2007 | 3/31/2007 | Concluded | David Byrnes (Inactive) | 5/12/2007 2:51:15 PM | |
Description: Smolt trap will be installed between 2/28/2007 and 3/1/2007 under project number 1996-040-00 for the data collection occuring during 2007. |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1464. Primary R, M, and E Focal Strategy [Population Status, Hydrosystem, Tributary Habitat, Estuary/Ocean, Harvest, Hatchery, Predation, Multiple Strategies] | Tributaries | Nason Creek, major tributary to Wenatchee River | |||
1472. Primary R, M, and E Type [Status and Trend Monitoring, Action Effectiveness Research, Uncertainties Research, Project Implementation/ Compliance Monitoring] | Status and Trend Monitoring | Juvenile salmonid population monitoring | |||
1478. Secondary R, M, and E Type [Status and Trend Monitoring, Action Effectiveness Research, Uncertainties Research, Project Implementation/ Compliance Monitoring] | Uncertainty Research | PIT tag evaluation of salmonid life history |
Work Site ID | Latitude | Longitude | State | County | Province | Subbasin |
---|---|---|---|---|---|---|
3208 | 47.801856 | -120.715875 | Washington | Chelan | Columbia Cascade | Wenatchee |
Study Plan Name | Study Plan Owner | Protocol State | Sample Design Name |
---|---|---|---|
BPA Fish and Wildlife Program Monitoring v1.0 | Russell Scranton | Draft | Operate smolt trap - Yakama Confederated Tribes v1.0 |