SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. 27178 (06/01/2006 - 06/23/2007) | $2,500 | $2,500 | ||
Work Element Budget (Current Performance Period) | $2,500 | $2,500 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | ASSEB | Accrual - Submit September estimate to BPA | 8/15/2006 | 9/15/2006 | Concluded | David Byrnes (Inactive) | 5/12/2007 2:51:16 PM |
Description: Provide BPA with an estimate of contract work that will occur prior to September 30 but will not be billed until October 1 or later. Generally, this should be done by September 10. | |||||||
B | FPCIR | Funding Package - Conduct internal review (e.g., Supervisor or Interagency) | 1/1/2007 | 2/28/2007 | Concluded | David Byrnes (Inactive) | 5/12/2007 2:51:16 PM |
Description: If necessary, submit next year's SOW and Budget for internal contractor review before submitting to BPA. Assuming this review takes 30 days, start this milestone 120 days before the end of the current contract. | |||||||
C | DELIV | Funding Package - Submit draft to COTR | 2/28/2007 | Concluded | David Byrnes (Inactive) | 5/12/2007 2:51:16 PM | |
Description: In Pisces, enter a new statement of work for the period June 1, 2007 through May 31, 2008 (if applicable). Per BPA contracting requirements, the SOW and all associated documents (budget, spending plan, property inventory, etc.), must be submitted a minimum of 90 days prior to the expiration of the current contract. |