This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $136,505 | $148,666 | Plan to use bridge removed from the Strawberry Cr location |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 2/1/2018 | 5/31/2018 | Concluded | Amy Mai | 9/18/2017 11:55:18 AM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff. | |||||||
B | HIP | Discuss HIP3 ESA coverage with BPA EC lead; obtain HIP3 risk determination | 2/1/2018 | 5/31/2018 | Concluded | Amy Mai | 9/18/2017 11:55:18 AM |
Description: The EC Lead will determine if work under this work element may be able to have full ESA-coverage (NOAA & USFWS) under the 2013 Habitat Improvement Program Biological Opinion (HIP3). The HIP3 has expanded coverage for projects that may pose a moderate to high risk of impacting an ESA-listed species or critical habitat that would normally require a Biological Assessment. For work that qualifies, projects will undergo a review by the BPA-internal Restoration Review Team (RRT). Before conceptual design commences, contact the EC lead for HIP3 consideration, instruction, and information needs and requirements for coverage eligibility. The HIP3 activity categories and risk criteria are located in the “Note” section of the work element background page here:https://www.cbfish.org/WorkElement.mvc/Summary/165 | |||||||
C | Develop RFB for bridge manufacture and delivery and advertise | 2/1/2018 | 2/28/2018 | Concluded | Amy Mai | 9/20/2017 11:16:52 AM | |
Description: CCT project biologists and engineering subcontractor will develop a request for bids (RFB) to manufacture a bridge to replace the existing culvert, following the CCT standard RFB format. The RFB will be submitted to CCT Fish and Wildlife Contract Specialist for review. The CCT Fish and Wildlife Contracts Specialist will advertise the RFB in regional newspapers and trade journals. In addition, the CCT Contracts Specialist may solicit for proposals from individual firms that provide these services, as requested by the project biologists. | |||||||
D | Select bridge manfacturer and negotiate contract | 3/1/2018 | 3/15/2018 | Concluded | Amy Mai | 9/20/2017 11:18:49 AM | |
Description: CCT project biologists, Resident Fish Program Manager, and engineering subcontractor will evaluate the bridge manufacture bids to insure that they meet design specifications, can be supplied within schedule, and for cost. Following evaluation, they will recommend a manufacturer. The Lead Biologist will notify the CCT Contract Specialist as to the selected contractor. The Contract Specialist will initiate the contracting process (negotiations, approvals, etc...) with the selected firm. | |||||||
E | Develop RFP for project implementation and advertise | 2/1/2018 | 4/30/2018 | Concluded | Amy Mai | 9/18/2017 12:05:58 PM | |
Description: CCT project biologists and engineering subcontractor will develop a request for proposals (RFP) to implement the culvert replacement, following the CCT standard RFP format. The RFP will be submitted to CCT Fish and Wildlife Contract Specialist for review. The CCT Fish and Wildlife Contracts Specialist will advertise the RFP in regional newspapers and trade journals. In addition, the CCT Contracts Specialist may solicit for proposals from individual firms that provide these services, as requested by the project biologists. | |||||||
F | Select implementation contractor and negotiate contract | 5/1/2018 | 5/31/2018 | Concluded | Amy Mai | 9/18/2017 12:05:58 PM | |
Description: CCT project biologists and Resident Fish Program Manager will independently review and score the proposals submitted in response to the implementation RFP, using a predetermined standardized scoring protocol. Following independent scoring, they will meet, discuss the scores, and recommend a contractor. The Lead Biologist will notify the CCT Contract Specialist as to the selected contractor. The Contract Specialist will initiate the contracting process (negotiations, approvals, etc...) with the selected firm. | |||||||
G | Remove existing culvert | 7/1/2018 | 10/31/2018 | Concluded | Amy Mai | 9/18/2017 12:05:58 PM | |
Description: Construction subcontractor will remove and dispose of existing culvert in accordance with applicable permits. | |||||||
H | Install new crossing | 7/1/2018 | 10/31/2018 | Concluded | Amy Mai | 9/18/2017 12:05:58 PM | |
Description: Construction subcontractor will install the bridge in accordance with the engineered plans and applicable permits. Engineering subcontractor will provide construction oversight. | |||||||
I | DELIV | Bridge on Iron Creek to provide passage of all redband trout life stages | 10/31/2018 | Concluded | Amy Mai | 12/21/2017 4:01:08 PM | |
Description: In order to provide migratory redband trout access to approximately 0.71 km (0.44 mi) of spawning habitat in Iron Creek, the CCT in coordination with subcontractors, will replace a culvert that is a complete barrier to fish passage. The new bridge will allow for complete fish passage. |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1441. # of miles of habitat accessed to the next upstream barrier(s) or likely limit of habitable range | 0.44 | 0.44 | miles of habitat accessed | Passage Barriers | |
1711. # of bridges installed in the freshwater non-tidal zone | 1 | 1 | barriers improved |
Work Site ID | Latitude | Longitude | State | County | Province | Subbasin |
---|---|---|---|---|---|---|
34112 | 48.138113 | -118.678436 | Washington | Ferry | Intermountain | Sanpoil |