Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
View Work Elements Available in FY:

Summary

<<
<
>
>>
Work Element 184: Install Fish Passage Structure - Published
WE Name:
184. Install Fish Passage Structure (Passage Structure)
Work Category:
Habitat - Instream Passage Improvement
WE Agreement Type:
Contracted
Status:
Active
Owner:
Definition:
Install, replace, or modify structures when the intent is to improve fish passage and/or flow, typically by removing or modifying a full or partial instream barrier. "Structures" include fish ladders, bridges, culverts, jump pools, roughened channels, and weirs. "Barriers" include such obstacles to fish passage as tidegates, weirs, culverts, rock fords, road crossings, and manmade dams. Structures also include natural barriers such as logjams and natural streambeds.

This work element excludes diversion dams. Use 208. Irrigation Infrastructure Construction or Replacement for diversion dam removal, and include this work as a milestone under this WE.

Where anadromous fish are present, structures installed must meet current NOAA specifications and USFWS specifications for lamprey and bull trout respectively. Use 180. Enhance Floodplain/Remove, Modify, Breach Dike if the installation of a passage structure is associated with a dike removal, breaching, and modification, and may create additional acres of habitat as well as providing access to instream habitat. Use 70. Install Fish Monitoring Equipment, for weirs installed primarily to restrict fish passage for the purpose of monitoring or collecting fish (e.g., picket weirs). Design of complex or large-scale fish passage structures is often a separate work element (see 175. Produce Design).

In known or potential lamprey habitat use guidance from these documents:

Guidelines to Minimize Impacts and Maximize Benefits for Native Lamprey During In-water Work https://www.fws.gov/pacificlamprey/BPALampreyGuidanceDocuments.cfm

Pacific Lamprey Habitat Restoration Guide https://www.fws.gov/pacificlamprey/BPALampreyGuidanceDocuments.cfm.

Lamprey presence can be determined from Data Basin map https://www.fws.gov/pacificlamprey/BPALampreyGuidanceDocuments.cfm. This map does not show all distribution due to limited data. Pre-project lamprey surveys should be done (see USFWS lamprey Guidelines document) if the map does not show presence.
WSE Description Template:
Effective Dates:
FY2005 to <no end date>
Work Phase:
construction/implementation
Sort Sequence:
7.05
Focal Species Required:
Yes
RM&E Metadata Required:
No
Finite or Recurring:
Finite
Is BPA Internal:
No
Is Contracted:
Yes
Is Cost Share:
No
Is Construction:
Yes


Deliverable Status:
Required
Default Deliverable Desc:
Inst Passage Structure
Potential Deliverables:
  • Installed fish passage structure - ladder, bridge, culvert, jump pool, weir, etc., or passage barrier removed

  • Rule 1 (Environmental Compliance): NEPA, ESA, cultural resources, and other environmental compliance work should be split out as separate work elements.

    Example:

    WE: 184. Install Fish Passage Structure
    WE Title: Replace Houghton Creek culvert #1.
    Deliverable: Installed pipe-arch culvert designed for 100-year event.

    WE: 165. Produce Environmental Compliance Documentation
    WE Title: Complete NEPA compliance for Houghton Creek culvert #1
    Deliverable: Project description and maps provided to BPA KEC contact.

  • Rule 2 (Location of Work): Each fish passage structure warrants its own work element. This is due to metrics reporting requirements for projects in different locations. The exception to this rule is when the same type of task (e.g. 3 culvert installations) is being performed very close to each other and/or on the same property. Check with your COTR to find out whether similar tasks can be lumped into a single work element.

    Example:

    WE: 184. Install Fish Passage Structure
    WE Title: Build a fish ladder on Johnson Diversion, Spring Creek, river mile 33.
    Deliverable: 1 six-foot-wide baffled fish ladder.

    WE: 184. Install Fish Passage Structure
    WE Title: Build a fish ladder at Power Dam, Spring Creek, river mile 39.
    Deliverable: 1 six-foot-wide baffled fish ladder.

    WE: 184. Install Fish Passage Structure
    WE Title: Build a series of jump pools below Peterman Falls, Spring Creek, river mile 45
    Deliverable: Three jump pools with rock weirs to promote scour and 4 inch openings for juvenile salmonid passage.

  • Rule 3 (Metrics): If the structure being installed is part of a connected effort to correct multiple problems at a single location, each with different metrics, split out each as a separate work element.

    Example: Project involves improving up- and downstream passage at Hot Springs diversion. Passage problems include a diversion that is impassable at low flows and an antiquated fish screen that violates NOAA/FSOC criteria. Other needs include a trap and haul operation, broodstock collection, and fish enumeration. The plan is to install a series of jump pools downstream of the dam, replace the screens, add a head gate to regulate flows and control water surface elevation at the screen site, and install a fish trap to handle the other needs. Use the following work elements:


    WE: 184. Install Fish Passage Structure
    WE Title: Install 3 jump pools below Hot Springs diversion

    WE: 69. Install Fish Screen (Expired)
    WE Title: Install 4 rotary drum screens on canal associated with Hot Springs Diversion.

    Note: Install Headgate is no longer a separate work element, so this activity should be listed as a milestone under 184. Install Fish Passage Structure.

    WE: 70. Install Fish Monitoring Equipment
    WE Title: Install juvenile and adult traps and holding ponds.
    WE Description: Traps and holding ponds will facilitate enumeration, broodstock collection, and a trap-and-haul operation at Hot Springs Diversion.

  • Rule 4 (Complexity): If the project is complex and/or large-scale (e.g., capital construction) feasibility, design, and construction management will likely be separate work elements.

    Example: You manage a project where the contractor is installing a large-scale fish ladder. In order to install the ladder, the contractor must complete several other related work elements. This example shows how the above rules might be applied and how related work might be called out using a typical plan-design-build-maintain-monitor cycle for such a major construction project:


    WE: 196. Council Step Process
    WE Title: Participate in Council's Step Process for Johnson Diversion Fish Ladder

    WE: 175. Produce Design
    WE Title: Design fish ladder for Johnson Diversion
    Deliverable: Technical drawings and specifications.

    WE: 184. Install Fish Passage Structure
    WE Title: Build a fish ladder on Johnson Diversion, Spring Creek, river mile 33.
    Deliverable: 1 six-foot-wide baffled fish ladder.

    WE: 100. Construction Management
    WE Title: Johnson Diversion fish ladder construction management subcontract.

  • Rule 5 (Context): If the structure being installed is part of a larger habitat effort (e.g., 30. Realign, Connect, and/or Create Channel), use that work element and include the construction of the fish passage structure as a milestone.


Milestone Title
Type
Deliverable?
Description

Environmental compliance requirements complete -New
Required
No
On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff.
Environmental Compliance followed for duration of work element
Suggested
No
Contractor and sub-contractors shall adhere to all mitigation and conservation measures, terms and conditions, avoidance areas, and best management practices required under environmental laws as directed by BPA.
Design passage structures to meet lamprey needs
Recommended
No
Lamprey need passage designs that minimize turbulent flows, provide gradual transitions between low and high velocity areas, have rounded surfaces (no sharp angles) and rest areas. Contractors should follow the guidance from these lamprey documents and incorporate lamprey passage criteria into the passage design:

Best Management Guidelines for Native Lampreys During In-water Work, https://www.fws.gov/pacificlamprey/BPALampreyGuidanceDocuments.cfm

Pacific Lamprey Habitat Restoration Guide, https://www.fws.gov/pacificlamprey/BPALampreyGuidanceDocuments.cfm

Practical guidelines for incorporating adult Pacific lamprey passage at fishways, https://www.fws.gov/pacificlamprey/BPALampreyGuidanceDocuments.cfm

Design Guidelines for Pacific Lamprey Passage Structures, http://www.uidaho.edu/~/media/UIdaho-Responsive/Files/cnr/FERL/technical-reports/2015/2015-5-LPS-Design.ashx
Discuss HIP ESA coverage with BPA EC Lead; obtain HIP risk determination
Recommended
No
The EC Lead will determine if work under this work element may be able to have ESA-coverage (NMFS & USFWS) under the current version of the Habitat Improvement Program Biological Opinions (HIP BiOps). Work that qualifies must comply with conservation measures in the HIP Handbook. Medium to high risk projects will require a technical review by the Bonneville Engineering Technical Services. Before conceptual design commences, contact the EC lead for HIP applicability, instructions and information requirements.

The HIP3 activity categories and risk criteria are located in the “Note” section of the work element background page here:https://www.cbfish.org/WorkElement.mvc/Summary/165
Hold initial kick-off meeting with all stakeholders
Suggested
No
Mobilize crew
Suggested
No
Prepare site
Suggested
No
Supplies/materials/equipment delivered
Suggested
No
Provide care of water (i.e. , coffer dam)
Suggested
No
Instream work complete
Suggested
No
Concrete work complete
Suggested
No
Mechanical work complete
Suggested
No
Punch-list inspection items complete
Suggested
No
Site rehabilitation complete
Suggested
No


19 Metrics Associated With Work Element 184: Install Fish Passage Structure

Metric Metric Association Status Last Comment Date Last Comment By Unit Type FY Start FY End Required / Optional Is Activated By Default Included in PI Supports PCSRF/PNSHP (Katz) PNSHP Metric Code PNSHP Metric
1441: # of miles of habitat accessed to the next upstream barrier(s) or likely limit of habitable range Active number 2005 Required Yes Yes Yes C.2.b.1 Length of stream made accessible
ITS Action Category:
Habitat Access
ITS Metric:
Miles accessable
1470: If installing a ladder, does the ladder meet NOAA specifications for attraction flow, pool dimensions, jump height, etc? Active YesNoList 2005 Optional Yes No No
ITS Action Category:
Habitat Access
ITS Metric:
Barrier type
1702: # of culverts installed in the estuarine zone Active number 2011 Required Yes Yes Yes C.9.f.2 Culverts modified/removed to allow fish passage
1703: # of tidegates installed in the estuarine zone Active number 2011 Required Yes Yes Yes C.9.e.2 Tidegates altered/removed to allow fish passage
1704: # of bridges installed in the estuarine zone Active number 2011 Required Yes Yes No
1705: # of natural stream crossings installed in the estuarine zone Active number 2011 Required Yes Yes No
1706: # of rock fords installed in the estuarine zone Active number 2011 Required Yes Yes Yes C.2.h.2 Number of rocked fords placed
1707: # of fish ladders installed in the estuarine zone Active number 2011 Required Yes Yes Yes C.2.e.2 Number of fish ladders installed/improved
1708: # of weirs or fishway chutes or pools installed in the estuarine zone Active number 2011 Required Yes Yes Yes C.2.d.2 Number of fishway chutes/pools installed
1709: # of culverts installed in the freshwater non-tidal zone Active number 2011 Required Yes Yes Yes C.2.f.2 Number of culverts installed or improved
1711: # of bridges installed in the freshwater non-tidal zone Active number 2011 Required Yes Yes Yes C.2.g.2 Number of bridges installed or improved/upgraded
1712: # of natural stream crossings installed in the freshwater non-tidal zone Active number 2011 Required Yes Yes No
1713: # of rock fords installed in the freshwater non-tidal zone Active number 2011 Required Yes Yes Yes C.2.h.2 Number of rocked fords placed
1714: # of fish ladders installed in the freshwater non-tidal zone Active number 2011 Required Yes Yes Yes C.2.e.2 Number of fish ladders installed/improved
1715: # of weirs or fishway chutes or pools installed in the freshwater non-tidal zone Active number 2011 Required Yes Yes Yes C.2.d.2 Number of fishway chutes/pools installed
1407: Was barrier Full or Partial? Expired BarrierTypeList 2005 2010 Required Yes No No
ITS Action Category:
Habitat Access
ITS Metric:
Barrier type
1471: Does the structure remove or replace a fish passage barrier? Expired YesNoList 2005 2010 Required Yes No No
ITS Action Category:
Habitat Access
ITS Metric:
Barrier type
1563: # of barriers in the freshwater zone Expired number 2010 2010 Required Yes No Yes C.2.c.2 Number of blockages/impediments/barriers removed/altered
ITS Action Category:
Habitat Access
ITS Metric:
Number of barriers addressed
1564: # of barriers in the estuarine zone Expired number 2010 2010 Required Yes No Yes C.2.c.2 Number of blockages/impediments/barriers removed/altered

CBFish Metric Set
barriers improved (Required)
Habitat Zone Barrier, or fish passage structure type modified, or upgraded Metric ID and Name Required?
Estuarine Culvert 1702. # of culverts installed in the estuarine zone Required
Estuarine Tidegate 1703. # of tidegates installed in the estuarine zone Required
Estuarine Bridge 1704. # of bridges installed in the estuarine zone Required
Estuarine Natural Stream Crossings 1705. # of natural stream crossings installed in the estuarine zone Required
Estuarine Rock Ford 1706. # of rock fords installed in the estuarine zone Required
Estuarine Fish Ladder Installed or Improved 1707. # of fish ladders installed in the estuarine zone Required
Estuarine Weirs or Fishway Chutes or Pools Installed 1708. # of weirs or fishway chutes or pools installed in the estuarine zone Required
Freshwater Non-Tidal Culvert 1709. # of culverts installed in the freshwater non-tidal zone Required
Freshwater Non-Tidal Bridge 1711. # of bridges installed in the freshwater non-tidal zone Required
Freshwater Non-Tidal Natural Stream Crossings 1712. # of natural stream crossings installed in the freshwater non-tidal zone Required
Freshwater Non-Tidal Rock Ford 1713. # of rock fords installed in the freshwater non-tidal zone Required
Freshwater Non-Tidal Fish Ladder Installed or Improved 1714. # of fish ladders installed in the freshwater non-tidal zone Required
Freshwater Non-Tidal Weirs or Fishway Chutes or Pools Installed 1715. # of weirs or fishway chutes or pools installed in the freshwater non-tidal zone Required

Supports PCSRF/PNSHP (Katz):

Yes

PNSHP Metric Association Metric
C.0 Salmonid Habitat Restoration and Acquisition
    C.2 Fish Passage Improvement
        C.2.b.1 Length of stream made accessible
1441: # of miles of habitat accessed to the next upstream barrier(s) or likely limit of habitable range
C.0 Salmonid Habitat Restoration and Acquisition
    C.2 Fish Passage Improvement
        C.2.c.1 Fish passage blockages removed or altered (other than road crossings reported in C.2.f to C.2.i)
            C.2.c.2 Number of blockages/impediments/barriers removed/altered
1563: # of barriers in the freshwater zone
1564: # of barriers in the estuarine zone
C.0 Salmonid Habitat Restoration and Acquisition
    C.2 Fish Passage Improvement
        C.2.d.1 Fishway chutes or pools installed
            C.2.d.2 Number of fishway chutes/pools installed
1708: # of weirs or fishway chutes or pools installed in the estuarine zone
1715: # of weirs or fishway chutes or pools installed in the freshwater non-tidal zone
C.0 Salmonid Habitat Restoration and Acquisition
    C.2 Fish Passage Improvement
        C.2.e.1 Fish ladder installed/improved
            C.2.e.2 Number of fish ladders installed/improved
1707: # of fish ladders installed in the estuarine zone
1714: # of fish ladders installed in the freshwater non-tidal zone
C.0 Salmonid Habitat Restoration and Acquisition
    C.2 Fish Passage Improvement
        C.2.f.1 Culvert installed or improved at road stream crossing
            C.2.f.2 Number of culverts installed or improved
1709: # of culverts installed in the freshwater non-tidal zone
C.0 Salmonid Habitat Restoration and Acquisition
    C.2 Fish Passage Improvement
        C.2.g.1 Bridge installed or improved at road stream crossing
            C.2.g.2 Number of bridges installed or improved/upgraded
1711: # of bridges installed in the freshwater non-tidal zone
C.0 Salmonid Habitat Restoration and Acquisition
    C.2 Fish Passage Improvement
        C.2.h.1 Rocked ford - road stream crossing
            C.2.h.2 Number of rocked fords placed
1706: # of rock fords installed in the estuarine zone
1713: # of rock fords installed in the freshwater non-tidal zone
C.0 Salmonid Habitat Restoration and Acquisition
    C.9 Estuarine/Nearshore Project
        C.9.e.1 Tidegate alteration/removal
            C.9.e.2 Tidegates altered/removed to allow fish passage
1703: # of tidegates installed in the estuarine zone
C.0 Salmonid Habitat Restoration and Acquisition
    C.9 Estuarine/Nearshore Project
        C.9.f.1 Estuarine culvert modification/removal
            C.9.f.2 Culverts modified/removed to allow fish passage
1702: # of culverts installed in the estuarine zone

Location Requirement Type:
Location Work Site in CBFish
Number of Locations:
1
Location Guidance:
Identify point where installation, modification or replacement will take place. If a location already exists in Pisces, click the "Link" button to synchronize locations.

Applicability and status of the following environmental compliance requirements can be found on the Environmental Compliance tab for that work element in your SOW for all 2007 contracts forward. BPA's Environmental staff will update and maintain this information in CBFish in real time, so that you can check the status of environmental compliance on your project at any time.

Note: Many of the fields are set to auto-load in CBFish, but the settings will be reviewed by BPA's Environmental staff prior to the contract being finalized, and may be revised depending on the specific circumstances.

  • National Environmental Policy Act (NEPA)
    NEPA coverage for this work element will be determined by BPA's Environmental staff and could include an Environmental Impact Statement (EIS), Environmental Assessment (EA), Record of Decision to an existing EIS, or Categorical Exclusion.

  • Endangered Species Act (ESA)
    ESA consultation is typically required for this work element.

  • National Historic Preservation Act (NHPA)
    NHPA Section 106 consultation is typically required for this work element which often includes a cultural/historic resource survey by a qualified archaeologist.

  • Public Involvement
    Public involvement is typically not required for this work element.


Reports that Use this Work Element

This work element and its metrics are used in measures in the following reports. These PDF reports are generated dynamically, always showing you the most up to date information. Most of them also have links to download the underlying data sets to structured text or Excel format.

Stats and Overview

Number of active contracts using Work Element #184 by FY

Top 5 BPA Project Managers using this Work Element:
(by number of current contracts)
Tracy Hauser 45
David Kaplowe 44
Virgil Watts III 26
Jamie Cleveland (Inactive) 21
Jennifer Lord 19
Average Work Element Budget: $122,058
Average Duration: 8 months