1. 27480 REL 1 (07/01/2006 - 06/30/2007) | $2,933 | $6,248 | ||
Work Element Budget (Current Performance Period) | $2,933 | $6,248 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | Prepare draft revised Field Manual | 7/1/2006 | 1/31/2007 | Concluded | David Byrnes (Inactive) | 2/23/2007 2:35:09 PM | |
Description: Submit draft Field Manual to reviewers by January 31, 2007 | |||||||
B | Receive draft field manual comments | 2/1/2007 | 3/1/2007 | Concluded | David Byrnes (Inactive) | 2/23/2007 2:35:09 PM | |
Description: Allow a one month review period of the draft field manual. Comments are to be submitted during this time to assure completion of the manual no later than April 30, 2007. | |||||||
C | Final revised Field Manual | 3/1/2007 | 4/30/2007 | Concluded | David Byrnes (Inactive) | 2/23/2007 2:35:09 PM | |
Description: Incorporate comments from reviewers no later than April 30, 2007. | |||||||
D | DELIV | Final Field Manual | 5/15/2007 | Concluded | David Byrnes (Inactive) | 2/23/2007 2:35:09 PM | |
Description: Revise and update a field personnel training manual incorporating as much information as possible that is currently available. The document should be produce in Portable Document Format (PDF) or other generally accepted format. Any deviation requires prior approval from the BPA COTR. |