1990-018-00 EXP RAINBOW TROUT HABITAT/PASSAGE IMPROVEMENT
Contract Start Date:
2/1/2020
Contract End Date:
1/31/2021
Title:
K: 29 - Moses Creek (BDA installation)
Description:
CCT biologists and technicians will install 3-5 Beaver Dam Analog (BDA) or Post Assisted Log Structures (PALS) to increase stream channel complexity and aid in floodplain re-connection. The intent is to facilitate channel-aggradation, water retention and water table elevation to improve natural regeneration of riparian vegetation within the cattle exclusion fence unit on Moses Creek.

Large and small woody debris will be used in the stream channel and secured in place with wood posts driven into the streambed. Typical construction will utilize hand tools, hand placing of wood pieces, and potentially a hydraulic post pounder. Installation will be completed by Project staff using materials locally sourced or gathered on-site. Additional materials may be obtained on CCT-owned property with appropriate tribal permits.
WE Agreement Type:
Contracted
Deliverable Specification:
Construct and install a series of Beaver Dam Analogs (BDAs) and/or Post Assisted Log Structures (PALS) within the riparian exclusion fence along Moses Creek to: a) create more complex habitat; b) elevate the surrounding water table; c) restore proper riparian function; and d) promote floodplain connectivity within the project reach in Moses Creek.
WSE Effective Budget:
$7,500
% of Total WSE Effective Budget:
0.95%
WSE Start:
02/01/2020
WSE End:
01/29/2021
WSE Completion:
12/03/2020
WSE Progress:
Concluded
WSE ID Continued From:
[Unassigned]
WSE ID Continued To:
[Unassigned]
Finite or Recurring:
Finite

SOWRevision Planned Updated Contractor Comments (optional) BPA Comments (optional)
Work Element Budget (Current Performance Period) $7,500 $7,500

4 Milestones
Sort Type Title Start End Status Modified By Modified Date
A EC Environmental compliance requirements complete 2/1/2020 6/1/2020 Concluded Jamie Cleveland (Inactive) 11/18/2019 10:47:04 AM
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff.
B Final metrics Materials for structure composition obtained (procurement of wood posts, logs, boughs or whips, etc.) 6/1/2020 10/31/2020 Concluded Jamie Cleveland (Inactive) 11/18/2019 10:53:26 AM
Description: Construction materials sourced and acquired: transported and staged on location or in secured areas adjacent to the project site. Obtain wood post material and branches from Tribal timber harvesting/thinning projects and/or collect materials with necessary permits on tribally owned property.
C Construction of BDA/PALS begins 8/1/2020 10/31/2020 Concluded Jamie Cleveland (Inactive) 11/18/2019 10:53:26 AM
Description: Implement the design (WE J) to construct up to 5 BDA and/or PALS within the Moses Creek project area.
D DELIV Improved habitat function, complexity and structure: installed BDAs functioning as designed in Moses Creek 1/29/2021 Concluded Jamie Cleveland (Inactive) 11/20/2019 9:50:16 AM
Description: Construct and install a series of Beaver Dam Analogs (BDAs) and/or Post Assisted Log Structures (PALS) within the riparian exclusion fence along Moses Creek to: a) create more complex habitat; b) elevate the surrounding water table; c) restore proper riparian function; and d) promote floodplain connectivity within the project reach in Moses Creek.

Work Site ID Latitude Longitude State County Province Subbasin
97521 48.444653 -119.095223 Washington Okanogan Intermountain Sanpoil

Primary Focal Species:
Trout, Interior Redband (O. mykiss gairdnerii)
Secondary Focal Species:
None

This work element does not require RM&E metadata