This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $500 | $500 | Time/cost consistent with past efforts and as budgeted. |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | NonT1 | Non-Technical: Prepare for non-technical Progress Report. Review most recent guidance and template. | 10/1/2020 | 9/30/2021 | Concluded | Eric Andersen (Inactive) | 7/8/2020 8:52:04 AM |
Description: Contractor must review guidance and template before starting the first draft of their non-technical report. Please follow the newly revised BPA-required format for Non-Technical Reports at: https://www.cbfish.org/Help.mvc/GuidanceDocuments. | |||||||
B | NonT2 | Non-Technical: Write Non-technical Progress Report | 10/1/2020 | 9/30/2021 | Concluded | Eric Andersen (Inactive) | 7/8/2020 8:52:04 AM |
Description: Please follow the BPA-required format. The newly revised BPA-required format for Non-Technical Reports can be found at: https://www.cbfish.org/Help.mvc/GuidanceDocuments. | |||||||
C | NonT3 | Non-Technical: Upload Non-Technical Progress Report in Pisces | 10/1/2020 | 9/30/2021 | Concluded | Eric Andersen (Inactive) | 7/8/2020 8:52:04 AM |
Description: Use the attachment tab in Pisces to upload your progress report in MS-Word format as "Non-Technical, Draft". After BPA review and finalized editing, BPA staff with post the report for public access. If the file size is too large for Pisces to accept, contact Pisces Support for help. | |||||||
D | IntRev | Distribute Progress Report for Internal Contractor Review | 10/1/2020 | 9/30/2021 | Concluded | Eric Andersen (Inactive) | 7/8/2020 8:52:04 AM |
Description: [DELETE THIS MILESTONE IF YOU HAVE NO INTERNAL REVIEWS OF YOUR REPORT] Internal review will be conducted by [INSERT TITLE OF EACH INDIVIDUAL REVIEWER HERE] before being reviewed externally or being uploaded. | |||||||
E | DELIV | Completed Annual Report | 2/28/2021 | Concluded | Eric Andersen (Inactive) | 7/8/2020 8:52:41 AM | |
Description: The Deliverable is considered complete when the final report is posted. It usually takes BPA 30-45 days to post the final PDF version of a report. This milestone's end date should therefore be 45 days after the final version is uploaded in Pisces. You will receive an email from BPA confirming that your report has been finalized and posted to the web. Mark this milestone complete when you have confirmed your final report has been posted. If you do not receive such an email after 45 days, contact your COTR. |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1768. Start date of reporting period | 10/1/2019 | 10/1/2019 | |||
1769. End date of reporting period | 9/30/2020 | 9/30/2020 |