This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $9,211 | $9,211 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | INSPECT | Provide construction inspection | 3/1/2021 | 6/1/2021 | Concluded | Tracy Hauser | 11/3/2020 12:53:43 PM |
Description: Provide construction inspection on Bowman off-site water project. | |||||||
B | PREFIN | Substantial completion reached and owner notified | 3/1/2021 | 6/1/2021 | Concluded | Tracy Hauser | 11/3/2020 12:53:43 PM |
Description: Notify owner when project is completed. | |||||||
C | RECAPP | Recommend final approval | 3/1/2021 | 7/30/2021 | Concluded | Tracy Hauser | 11/3/2020 12:53:43 PM |
Description: Upon inspection recommend final approval. | |||||||
D | Suggested | Submit summaries of periodic (e.g., weekly) construction meetings | 3/1/2021 | 6/1/2021 | Concluded | Tracy Hauser | 10/28/2020 1:44:17 PM |
Description: Construction manager typically conducts weekly meetings with construction contractor to review progress, resolve issues, etc. Summaries of these meetings will be submitted to the BPA COTR as soon as meeting notes are finalized for the duration of the project. | |||||||
E | Daily Construction Reports | 3/1/2021 | 2/28/2022 | Concluded | Tracy Hauser | 11/5/2020 10:39:41 AM | |
Description: Attach to PISCES contract, daily construction logs/reports for Bowman Off-site Water Development project. May be bundled into several weeks or a month. | |||||||
F | DELIV | Construction Management Complete | 6/1/2021 | Concluded | Tracy Hauser | 10/28/2020 1:44:17 PM | |
Description: 1) Collect and review daily construction logs; 2) Review/approve change order requests (Contractor shall consult with BPA CO (in consultation with BPA COTR) on any desired change orders before directing the construction contractor to make them); 3) Review subcontractor's requests for payments. |