1984-025-00 EXP GRANDE RONDE UMATILLA FISH HABITAT IMPROVEMENT 21
Contract Start Date:
3/1/2021
Contract End Date:
2/28/2022
Title:
G: 100 - Oversee and Administer Construction of Bowman Off-site Water Development.
Description:
Oversee implementation of an NRCS designed off-site watering system on the Bowman Project. Majority of work should be completed before this contract begins but components may need to be constructed in Spring 2021.
WE Agreement Type:
Contracted
Deliverable Specification:
1) Collect and review daily construction logs; 2) Review/approve change order requests (Contractor shall consult with BPA CO (in consultation with BPA COTR) on any desired change orders before directing the construction contractor to make them); 3) Review subcontractor's requests for payments.
WSE Effective Budget:
$9,211
% of Total WSE Effective Budget:
1.74%
WSE Start:
03/01/2021
WSE End:
02/28/2022
WSE Completion:
06/01/2021
WSE Progress:
Concluded
WSE ID Continued From:
[Unassigned]
WSE ID Continued To:
[Unassigned]
Finite or Recurring:
Finite

SOWRevision Planned Updated Contractor Comments (optional) BPA Comments (optional)
Work Element Budget (Current Performance Period) $9,211 $9,211

6 Milestones
Sort Type Title Start End Status Modified By Modified Date
A INSPECT Provide construction inspection 3/1/2021 6/1/2021 Concluded Tracy Hauser 11/3/2020 12:53:43 PM
Description: Provide construction inspection on Bowman off-site water project.
B PREFIN Substantial completion reached and owner notified 3/1/2021 6/1/2021 Concluded Tracy Hauser 11/3/2020 12:53:43 PM
Description: Notify owner when project is completed.
C RECAPP Recommend final approval 3/1/2021 7/30/2021 Concluded Tracy Hauser 11/3/2020 12:53:43 PM
Description: Upon inspection recommend final approval.
D Suggested Submit summaries of periodic (e.g., weekly) construction meetings 3/1/2021 6/1/2021 Concluded Tracy Hauser 10/28/2020 1:44:17 PM
Description: Construction manager typically conducts weekly meetings with construction contractor to review progress, resolve issues, etc. Summaries of these meetings will be submitted to the BPA COTR as soon as meeting notes are finalized for the duration of the project.
E Daily Construction Reports 3/1/2021 2/28/2022 Concluded Tracy Hauser 11/5/2020 10:39:41 AM
Description: Attach to PISCES contract, daily construction logs/reports for Bowman Off-site Water Development project. May be bundled into several weeks or a month.
F DELIV Construction Management Complete 6/1/2021 Concluded Tracy Hauser 10/28/2020 1:44:17 PM
Description: 1) Collect and review daily construction logs; 2) Review/approve change order requests (Contractor shall consult with BPA CO (in consultation with BPA COTR) on any desired change orders before directing the construction contractor to make them); 3) Review subcontractor's requests for payments.

This work element does not require Metrics
Primary Focal Species:
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened); Steelhead (O. mykiss) - Snake River DPS (Threatened); Trout, Bull (S. confluentus) (Threatened)
Secondary Focal Species:
Freshwater Mussels; Trout, Interior Redband (O. mykiss gairdnerii); Whitefish, Mountain (Prosopium williamsoni); Other Resident - Sculpin, Dace, Castomids

This work element does not require Environmental Compliance
This work element does not require RM&E metadata