SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. Amendment 001 (03/01/2022 - 02/28/2023) | $147,336 | $147,336 | ||
Work Element Budget (Current Performance Period) | $147,336 | $147,336 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | ADVCC | Advertise construction contract | 3/1/2022 | 4/29/2022 | Active | Allan Whiting | 10/18/2024 10:24:37 AM |
Description: The work completed under this milestone is ongoing from bid announcement development during contract 87255 (CCR-46753). The extension of the timeline for the Log Springs Meadow Restoration will require internal contract amendments to ensure a continuation of the construction started in 2021. Due to the winter shutdown additional mobilization will required with a cost and timeline need to be developed. Preparation for the start of the Shitike Creek Headworks Removal restoration implementation will require the removal of two unused power poles prior to advertisement of the construction contract. Delivery of the LWD needed for the project implementation will have to be contracted as will the implementation of the restoration design. LWD is being provided/donated from a on-reservation stand already planned for harvest by CTWS. | |||||||
B | AWDCC | Award construction contract | 4/1/2022 | 5/31/2022 | Active | Allan Whiting | 10/18/2024 10:24:37 AM |
Description: Contracts will be awarded to qualified contractors for the Shitike Headworks Removal restoration project before the end of May. | |||||||
C | Manage Construction - Log Springs | 3/1/2022 | 10/31/2022 | Concluded | Allan Whiting | 10/18/2024 10:24:37 AM | |
Description: The funding in this contract will be used to manage the Log Springs Meadow Phase 1 implementation which was extended in 2022 due to unfavorable fire conditions in 2021. | |||||||
D | Manage Construction - Shitike Headworks | 5/23/2022 | 9/28/2022 | Active | Allan Whiting | 2/5/2025 4:44:35 PM | |
Description: The funding in this contract will be used to fund staff oversight and manage the Shitike Creek Headworks Removal contract (CR-343962) which will begin in late may 2022. | |||||||
E | Project completion walk through | 8/1/2022 | 10/31/2022 | Concluded | Allan Whiting | 10/18/2024 10:24:37 AM | |
Description: Upon completion of the projects Tribal staff will complete a walkthrough and develop a redline copy of the design plans for the files. The redline copy will detail any changes and adjustments made to the design during construction. The walkthrough will ensure all elements of the implementation and resource protections have been implemented completely. | |||||||
F | DELIV | Construction Management Complete | 11/16/2022 | Active | Allan Whiting | 2/5/2025 1:46:28 PM | |
Description: A completion report summarizing the implementation of the project will be developed and uploaded to this contract. The completion report will also serve as a deliverable for the cost share funding associated with these projects. |