This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $82,229 | $83,358 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | REVDWG | Review and approve shop drawings | 3/1/2023 | 11/30/2023 | Concluded | Tracy Hauser | 10/25/2022 9:17:08 AM |
Description: Review and approve shop drawings for UGR-Bowman. | |||||||
B | REVCCR | Review and approve change orders | 3/1/2023 | 11/30/2023 | Concluded | Tracy Hauser | 10/25/2022 9:17:08 AM |
Description: Review and approve change orders for UGR-Bowman. | |||||||
C | INSPECT | Provide construction inspection | 3/1/2023 | 11/30/2023 | Concluded | Tracy Hauser | 10/25/2022 9:17:08 AM |
Description: Provide construction inspection for UGR-Bowman. | |||||||
D | PREFIN | Substantial completion reached and owner notified | 11/1/2023 | 11/30/2023 | Concluded | Tracy Hauser | 10/25/2022 9:17:08 AM |
Description: Substantial completion reached and owner notified for UGR-Bowman | |||||||
E | RECAPP | Recommend final approval | 11/1/2023 | 11/30/2023 | Concluded | Tracy Hauser | 10/25/2022 9:17:08 AM |
Description: Recommend final approval for UGR-Bowman. | |||||||
F | ASBUILT | Submit as-built drawings and daily construction logs | 11/30/2023 | 2/28/2024 | Concluded | Tracy Hauser | 10/25/2022 9:17:08 AM |
Description: Submit as-built drawings and daily construction logs for UGR-Bowman. | |||||||
G | Suggested | Submit summaries of periodic (e.g., weekly) construction meetings | 3/1/2023 | 2/29/2024 | Concluded | Tracy Hauser | 10/25/2022 9:17:08 AM |
Description: Submit summaries of periodic (e.g., weekly) construction meetings for UGR-Bowman: Construction manager typically conducts weekly meetings with construction contractor to review progress, resolve issues, etc. Summaries of these meetings will be submitted to the BPA COTR as soon as meeting notes are finalized for the duration of the project. | |||||||
H | Daily Construction Reports | 3/1/2023 | 2/28/2024 | Concluded | Tracy Hauser | 10/25/2022 9:17:08 AM | |
Description: Daily Construction Reports for UGR-Bowman: Attach to PISCES contract, daily construction logs/reports for Catherine Creek State Park Fish Habitat Restoration Project. May be bundled into several weeks or a month. | |||||||
I | DELIV | Construction Management Complete | 2/28/2024 | Concluded | Tracy Hauser | 10/25/2022 9:17:08 AM | |
Description: Construction Management Complete for UGR-Bowman: 1) Collect and review daily construction logs; 2) Review/approve change order requests (Contractor shall consult with BPA CO (in consultation with BPA COTR) on any desired change orders before directing the construction contractor to make them); 3) Review subcontractor's requests for payments. |