Show new navigation
On
Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
Select a work element:
Contract Number:
Contract Title:
2000-015-00 EXP OXBOW CONSERVATION AREA
Contract Start Date:
4/1/2023
Contract End Date:
3/31/2024
Title:
Q: 191 - RESTORATION - John Day Watershed Restoration Program Coordination
Description:
John Day Watershed Restoration Program assistance, consulting and other activities.
WE Agreement Type:
Contracted
Deliverable Specification:
Coordinate with John Day Watershed Restoration Project on various projects requiring field crew involvement and properties project work and development.
WSE Effective Budget:
$15,000
% of Total WSE Effective Budget:
1.63%
WSE Start:
04/01/2023
WSE End:
03/31/2024
WSE Completion:
03/31/2024
WSE Progress:
Concluded
WSE ID Continued From:
n/a
WSE ID Continued To:
n/a
Finite or Recurring:
Recurring

SOWRevision Planned Updated Contractor Comments (optional) BPA Comments (optional)
1. 92141 (04/01/2023 - 03/31/2024) $15,000 $15,000
Work Element Budget (Current Performance Period) $15,000 $15,000

5 Milestones
Sort Type Title Start End Status Modified By Modified Date
A Dewitt Roof bid and contract management 4/1/2023 3/31/2024 Concluded Ryan Ruggiero (Inactive) 10/11/2023 1:52:10 PM
Description: This was delayed through the summer and fall of 2022 but may be completed within contract #90035. Assist with the completion of the Dewitt homestead roof repair by creating and managing the bid and contractual process with interested and winning parties. Funding is within the Vinegar to Vincent BPA contract.
B Coordinate with the John Day Watershed Restoration program on planting project efforts 4/1/2023 3/31/2024 Concluded Ryan Ruggiero (Inactive) 10/11/2023 1:52:10 PM
Description: Assist with planting projects in terms of planning, planting, and maintenance. Program staff will consult on planning planting efforts for the JDWR Program. Nursery staff will perform pre- and post-planting project inspections to ensure plants will succeed.
C Coordinate and assist the John Day Watershed Restoration Program on Restoration Project work related to Crew Management 4/1/2023 3/31/2024 Concluded Ryan Ruggiero (Inactive) 10/11/2023 1:52:10 PM
Description: The Technician Crew is 40% funded by the John Day Watershed Restoration (JDWR) Program in order to assist with project efforts. The supervision and hiring of the crew is by the Conservation Area Project Leader, funded by this contract. Supervision of the Crew on restoration projects is perform occasionally by the Project Leader in coordination with the JDWR Program.
D Coordinate with the John Day Watershed Restoration program on restoration project efforts 4/1/2023 3/31/2024 Concluded Ryan Ruggiero (Inactive) 10/11/2023 1:52:10 PM
Description: Coordinate with the John Day Watershed Restoration Program underway on the properties. This includes the Vincent to Vinegar (V2V) project on the Middle Fork Forrest property, development of Mainstem FCA Project, Dunstan, and the Middle Fork Planting and Fencing Project may also include other project efforts in the planning stages.
E DELIV Coordinate with Jahn Day Watershed Restoration Project 3/31/2024 Concluded Ryan Ruggiero (Inactive) 10/11/2023 1:52:10 PM
Description: Coordinate with John Day Watershed Restoration Project on various projects requiring field crew involvement and properties project work and development.

This work element does not require Metrics
This work element does not require Focal Species
This work element does not require Environmental Compliance
This work element does not require RM&E metadata