This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
2. Amendment 001 (05/01/2022 - 09/30/2023) | $171,215 | $167,706 | ||
Work Element Budget (Current Performance Period) | $171,215 | $167,706 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete. HIP4 #2023003 was completed 10/6/2022 | 11/18/2022 | 1/20/2023 | Concluded | Ryan Ruggiero (Inactive) | 9/12/2023 7:14:30 AM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff. | |||||||
B | Final metrics | Provide final metrics | 6/1/2023 | 10/15/2023 | Concluded | Ryan Ruggiero (Inactive) | 9/12/2023 7:14:30 AM |
Description: Verify implemented work is consistent with planned metrics and update final metrics in cbfish. | |||||||
C | Sub-contractor hired for implementation | 2/1/2023 | 2/28/2023 | Concluded | Ryan Ruggiero (Inactive) | 9/12/2023 7:14:30 AM | |
Description: A request for qualification process and bid process has been completed. Custer SWCD will work with the landowner to implement the project under a contract between the district and landowner. The construction contract and landowner contract will be finalized once funds have been approved within this contract. All documents are in order. | |||||||
D | In water work window identified | 2/1/2023 | 2/28/2023 | Concluded | Ryan Ruggiero (Inactive) | 9/12/2023 7:14:30 AM | |
Description: Work with IDFG and NOAA to ensure the work can be completed in the February/March 2023 time frame as identified in the HIP. | |||||||
E | Materials for structures staged at implementation sites | 3/1/2023 | 3/31/2023 | Concluded | Ryan Ruggiero (Inactive) | 9/12/2023 7:14:30 AM | |
Description: Materials will be staged in early to mid January to allow work to be completed in February and early March. Contractor has identified adequate material to complete the project. | |||||||
F | Construction begins | 4/1/2023 | 4/28/2023 | Concluded | Ryan Ruggiero (Inactive) | 9/12/2023 7:14:30 AM | |
Description: Construct can begin as soon as the 404 permit is in place and fish suveys have been completed to ensure the work widow is feasible for the February/March construction time frame. Similar work was completed in 2022 during this period and was less impact on the frozen ground. | |||||||
G | DELIV | Completion of all structure implementation | 7/28/2023 | Concluded | Ryan Ruggiero (Inactive) | 9/12/2023 7:14:30 AM | |
Description: Complete habitat complexity work within Muddy Springs on Phase II by installing a combination of whole trees, rootwads, racking and slash, willow clumps, willow cuttings, and untreated posts. Most structures will be channel spanning. Approximately 6 pools will be installed with this project. |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1387. # of miles of stream with improved complexity | 0.72 | 0.80 | miles of stream with improved complexity | Habitat Miles | |
1389. Start latitude of treated stream reach | 44.601956 | 44.601956 | |||
1390. End latitude of treated stream reach | 44.596857 | 44.596857 | |||
1391. Start longitude of treated stream reach | -113.961465 | -113.961465 | |||
1392. End longitude of treated stream reach | -113.957156 | -113.957156 | |||
1547. # of miles of stream treated with spawning gravel | 0.40 | 0.40 | miles of stream treated with spawning gravel | ||
1592. # of rootwad structures installed for only complexity | 7 | 12 | structures installed | ||
1748. # of pools created for only complexity | 6 | 6 | pools created |
Work Site ID | Latitude | Longitude | State | County | Province | Subbasin |
---|---|---|---|---|---|---|
118825 | 44.601956 | -113.961465 | Idaho | Custer | Mountain Snake | Salmon |