SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $61,775 | $61,775 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 10/1/2023 | 11/30/2023 | Concluded | Jennifer Lord | 8/18/2023 8:56:18 AM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff. | |||||||
B | Prepare draft plan | 9/1/2024 | 12/31/2024 | Active | Jennifer Lord | 9/7/2023 1:18:04 PM | |
Description: Complete initial analysis and develop web-tools for visualization. | |||||||
C | Hold a meeting for final review | 10/1/2024 | 11/1/2024 | Active | Jennifer Lord | 8/18/2023 8:56:18 AM | |
Description: Coordinate and manage consultant and citizen/technical team meetings to review draft conceptual restoration documents. Hold meetings to: initiate and structure the assistance of consulting services; exchange data and information; and develop citizen outreach plan. Convene outreach meetings; solicit and incorporate comment; review and finalize report and plan documents in the Implementation Workgroup (TIG) and RTT. | |||||||
D | DELIV | Complete data analysis and develop reporting tool | 12/31/2024 | Active | Jennifer Lord | 9/7/2023 1:18:04 PM | |
Description: Complete data analysis and summarize for development into wed map for easy visualization and public use. |