This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $34,826 | $11,021 | All invoices are not yet submitted. |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | Provide technical review | 4/1/2024 | 3/31/2025 | Concluded | Verl Miller | 12/21/2023 2:17:50 PM | |
Description: IDFG staff will review, contribute and participate as necessary and available in activities identified in the NPCC's draft work plan and collaborate in other regional technical and policy forums as necessary. | |||||||
B | DELIV | Technical comments (or other communications providing feedback of a technical nature) | 3/31/2025 | Concluded | Verl Miller | 12/21/2023 2:17:50 PM | |
Description: For technical reviews of ongoing issues, no deliverable is required, but may be provided on an as needed basis. In this contract, Work Element B will cover most participation in ongoing forums where IDFG may provide technical or Policy review. |