Work Element 122: Provide Technical Review and Recommendation - Published
WE Name:
122. Provide Technical Review and Recommendation (Provide Tech Review)
Work Category:
Planning and Coordination
WE Agreement Type:
Contracted
Status:
Active
Owner:
Definition:
The review of technical details, including but not limited to engineering plans, restoration plans, project selection, RM&E methods, and deliverable approval. If producing adaptive management recommendations, consider using WE 115 Produce Inventory or Assessment.
WSE Description Template:
Effective Dates:
FY2005 to <no end date>
Work Phase:
multiple
Sort Sequence:
10.06
Focal Species Required:
No
RM&E Metadata Required:
No
Finite or Recurring:
Finite
Is BPA Internal:
No
Is Contracted:
Yes
Is Cost Share:
No
Is Construction:
No


Deliverable Status:
Required
Default Deliverable Desc:
Documentation
Potential Deliverables:
  • Comments (or other communications providing feedback of a technical nature)
  • None (if the review is ongoing or on an as needed basis)

  • Rule 1 (Location of Work): If you are reviewing work occurring in multiple locations, you may still lump it under a single work element. However, you may wish to break the work into separate work elements if it provides clarity or better supports project management.

    Examples:

    Option 1 (lumping):

    WE: 122. Provide Technical Review and Recommendation
    WE Title: Marcotte Bar Fish Ladder and McCloud Bottoms Water Control Structure
    WE Description: Review the engineering designs for the Marcotte Bar Fish Ladder and the McCloud Bottom Water Control Structure.

    Option 2 (splitting):

    WE: 122. Provide Technical Review and Recommendation
    WE Title: Marcotte Bar Fish Ladder
    WE Description: Review the engineering designs for the Marcotte Bar Fish Ladder.

    WE: 122. Provide Technical Review and Recommendation
    WE Title: McCloud Bottoms Water Control Structure
    WE Description: Review the engineering designs for the McCloud Bottoms Water Control Structure.


Milestone Title
Type
Deliverable?
Description

Attend review meetings
Suggested
No
Submit comments to BPA
Suggested
No
Submit comments to third party
Suggested
No
Interpretation and Synthesis
Suggested
No
Provide interpretation of data and synthesis of results in order to develop recommendations to BPA.


Location Requirement Type:
No Location

Applicability and status of the following environmental compliance requirements can be found on the Environmental Compliance tab for that work element in your SOW for all 2007 contracts forward. BPA's Environmental staff will update and maintain this information in CBFish in real time, so that you can check the status of environmental compliance on your project at any time.

Note: Many of the fields are set to auto-load in CBFish, but the settings will be reviewed by BPA's Environmental staff prior to the contract being finalized, and may be revised depending on the specific circumstances.

  • National Environmental Policy Act (NEPA)
    NEPA coverage for this work element will be determined by BPA's Environmental staff and could include an Environmental Impact Statement (EIS), Environmental Assessment (EA), Record of Decision to an existing EIS, or Categorical Exclusion.

  • Endangered Species Act (ESA)
    ESA consultation is typically not required for this work element.

  • National Historic Preservation Act (NHPA)
    NHPA Section 106 consultation is typically not required for this work element.

  • Public Involvement
    Public involvement is typically not required for this work element.


Reports that Use this Work Element

This work element and its metrics are used in measures in the following reports. These PDF reports are generated dynamically, always showing you the most up to date information. Most of them also have links to download the underlying data sets to structured text or Excel format.

Stats and Overview

Number of active contracts using Work Element #122 by FY

Top 5 BPA Project Managers using this Work Element:
(by number of current contracts)
Virgil Watts III 116
Jamie Cleveland (Inactive) 103
Michelle O'Malley 75
Tracy Hauser 72
Carlos Matthew 69
Average Work Element Budget: $44,182
Average Duration: 12 months