2007-403-00 EXP ID SPR CHINOOK CAPTIVE PROP
Contract Start Date:
10/1/2007
Contract End Date:
9/30/2008
Title:
D: 70 - Install and maintain weir/traps on East Fork Salmon River.
Description:
Weirs are maintained to monitor anadromous Chinook salmon migration in the East Fork of the Salmon River (EFSR) and to monitor spawning behavior of captive reared adults released to the study area in the EFSR. Environmental compliance permits will have approval before implementation.
WE Agreement Type:
Contracted
Deliverable Specification:
Removal of the EFSR temporary picket weir (installed under previous contract in July, 2007) after Chinook salmon spawning is complete between October 1 and October 31, 2007 to allow free passage of fish in the East Fork Salmon River. Install picket weir on the East Fork Salmon River to contain fish within study area for observation. Weir will be installed between July 1 and August 1, 2008.
WSE Effective Budget:
$9,000
% of Total WSE Effective Budget:
1.94%
WSE Start:
10/01/2007
WSE End:
09/30/2008
WSE Completion:
09/30/2008
WSE Progress:
Concluded
WSE ID Continued From:
[Unassigned]
WSE ID Continued To:
[Unassigned]
Finite or Recurring:
Finite

SOWRevision Planned Updated Contractor Comments (optional) BPA Comments (optional)
Work Element Budget (Current Performance Period) $10,000 $9,000

4 Milestones
Sort Type Title Start End Status Modified By Modified Date
A EC Environmental compliance requirements complete 10/1/2007 10/1/2007 Concluded Dan Baker 6/15/2007 12:54:44 PM
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff (completion can be based on pre-existing environmental documentation from BPA).
B Remove picket weir from East Fork Salmon River study area. 10/1/2007 10/31/2007 Concluded Dan Baker 7/12/2007 12:22:49 PM
Description: Remove temporary picket weir from the upper EFSR after 2007 Chinook salmon spawning season.
C Install temporary picket weir on the upper East Fork Salmon River. 7/1/2008 9/30/2008 Concluded Dan Baker 6/15/2007 12:54:44 PM
Description: Install temporary picket weir used to section off study area on the EFSR before captive adults are released to the EFSR.
D DELIV Monitoring trap/weir in place and fully functional. 9/30/2008 Concluded Dan Baker 7/12/2007 12:22:15 PM
Description: Removal of the EFSR temporary picket weir (installed under previous contract in July, 2007) after Chinook salmon spawning is complete between October 1 and October 31, 2007 to allow free passage of fish in the East Fork Salmon River. Install picket weir on the East Fork Salmon River to contain fish within study area for observation. Weir will be installed between July 1 and August 1, 2008.

Implementation Metrics
None

Work Site ID Latitude Longitude State County Province Subbasin
37848 44.08251 -114.447948 Idaho Custer Mountain Snake Salmon
38708 44.118238 -114.428225 Idaho Custer Mountain Snake Salmon

Primary Focal Species:
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)