This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $0 | $0 | Work to be completed under contributed costs by Forest Service Staff. |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | Obtain concurrence from NOAA for culvert replacements | 3/1/2008 | 5/15/2008 | Concluded | Mark Johnson | 12/13/2007 3:19:56 PM | |
Description: Obtain letters from NOAA documenting concurrence for projects. | |||||||
B | Obtain concurrence from USFWS for culvert replacements | 3/1/2008 | 5/15/2008 | Concluded | Mark Johnson | 12/13/2007 3:19:57 PM | |
Description: Obtain letters from USFWS documenting concurrence for projects. | |||||||
C | Obtain permits from Army Corps of Engineers | 3/1/2008 | 5/31/2008 | Concluded | Mark Johnson | 12/13/2007 3:19:57 PM | |
Description: Secure all required Army Corps of Engineers permits. | |||||||
D | Ensure cultural/heritage clearance is complete | 3/1/2008 | 5/31/2008 | Concluded | Mark Johnson | 12/13/2007 3:19:58 PM | |
Description: Complete cultural/heritage resources consultation. | |||||||
E | DELIV | Environmental compliance documentation submitted to BPA | 5/31/2008 | Concluded | Mark Johnson | 12/13/2007 3:19:58 PM | |
Description: All of the environmental compliance documentation completed, including NEPA, ESA, and cultural resources consultation, will be submitted to the BPA Environmental Lead for review and approval, as needed. |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1479. Are herbicides used as part of work performed under this contract? | No | No |