SOW Report
Contract 36691: 1996-077-02 EXP USFS LOLO CREEK WATERSHED RESTORATION
Project Number:
Title:
Lolo/Selway River Watershed Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
36691
Contract Title:
1996-077-02 EXP USFS LOLO CREEK WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
32944: 1996 077 02 EXP USFS LOLO CREEK WATERSHED RESTORATION
  • 41713: 199607702 EXP USFS LOLO CREEK WATERSHED RESTORATION
Contract Status:
Closed
Contract Description:
Contract History:  

The Lolo Creek Watershed Restoration project (1996-077-02) has been an on-going project of the Nez Perce Tribe Fisheries Watershed Program and BPA since 1996.  The ultimate goal of the project is to restore the physical and biological characteristics of the watershed to provide quality habitat for anadromous and resident fish species that support the historical, cultural and economic practices of the Nez Perce Tribe.  The Lolo Creek watershed contains proposed critical habitat for listed species steelhead trout, potential critical habitat for bull trout, and has moderate habitat potential for spring Chinook salmon.  Restoration in this watershed focuses on restoring riparian processes by addressing increased water temperatures, increased sedimentation, cattle grazing affects, fish passage issues, and noxious weed infestations.  The project addresses passage problems, primaril... y at road/stream crossings, on both private and federal land, and addresses riparian planting and riparian protection program management. Completed contract work includes culvert prioritization and assessment, installation of an off-site watering development, 19 culvert replacements, 8 culvert removals, 1600 ft. of stream bank stabilization, 62 miles of road decommissioning, 16 miles of fence installation, over 13,800 riparian trees planted, and continued monitoring and evaluation.                                                                                                                      

Summary of FY 08 contract work:

This project is a part of the Clearwater National Forest-Nez Perce Tribe Watershed Restoration Partnership with in-kind contributions from the Clearwater National Forest.  Since the project's inception, we have shared project planning, costs, and implementation responsibilities.  There are two contracts under this project.  The primary contract is with the Nez Perce Tribe.  This contract with the Clearwater National Forest includes only the funding for the White-White road decommissioning.

A) White-White road decommissioning
Road densities in the Lolo Creek watershed are 4.8 miles per square mile, the target for road densities is 1.0 miles per square mile.  Up to 10 miles of road decommissioning will be completed under the proposed White-White road decommissioning project.  This work will include re-contouring roads back to natural topography and de-compacting skid trails and landing areas which will reduce surface erosion and sediment delivery to streams.  The Nez Perce Tribe, under a separate BPA-NPT contract of this project, will assist in bid package preparation, contractor selection, technical oversight, final inspection, and the associated project implementation/effectiveness monitoring.
  
Account Type(s):
Expense
Contract Start Date:
03/01/2008
Contract End Date:
02/28/2009
Current Contract Value:
$70,000
Expenditures:
$70,000

* Expenditures data includes accruals and are based on data through 28-Feb-2025.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Marker
5 m
10 ft
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration No Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Anne Connor US Forest Service (USFS) Yes Contract Manager aconnor@fs.fed.us (208) 476-8235
Lois Geary US Forest Service (USFS) No Administrative Contact lgeary@fs.fed.us (208) 983-7008
Mark Johnson Nez Perce Tribe Yes Technical Contact markj@nezperce.org (208) 621-3561
David Kaplowe Bonneville Power Administration Yes COR djkaplowe@bpa.gov (503) 230-5365
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Heidi McRoberts Nez Perce Tribe Yes Technical Contact heidim@nezperce.org (208) 621-3548
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Tom Reilly US Forest Service (USFS) No Supervisor treilly@fs.fed.us (208) 476-8273


Viewing 5 of 5 Work Statement Elements
Sort Order
WSEV ID
WE ID
Work Element Name
Title
Description
WSE Effective Budget
% of Total WSE Effective Budget
WSE Start
WSE End
A36244165Produce Environmental Compliance DocumentationProvide environmental compliance information to BPA for projects on Forest Service LandsAll applicable NEPA, ESA and cultural resources consultation will be completed for all contract activities by the Clearwater National Forest.$00.00%03/01/200805/31/2008
B3702233Decommission Road/Relocate RoadWhite-White Road DecommissioningExcessive road density was defined as one of the major contributors to degraded habitat condition in Lolo Creek for both aquatic and terrestrial species (Upper Lolo Creek Ecosystem Assessment at the Watershed Scale and Clearwater Subbasin Assessment). Road densities in the Lolo Creek watershed are 4.8 miles per square mile, the target for road densities is 1.0 miles per square mile. The Clearwater National Forest (CNF) and the Nez Perce Tribe (NPT) have worked together since 1996 to decommission roads on National Forest lands under a watershed restoration partnership. In 2004 NPT and CNF personnel began surveying and prioritizing roads in the White-White Creek basin. Initial road decommissioning also began in the White-White area in 2004, and this work element will continue to decommission roads that have been previously identified and prioritized in this basin.$70,000100.00%03/01/200810/31/2008
C36247119Manage and Administer ProjectsManagement, Coordination and CommunicationProject management includes coordinating project activities, attending meetings and workshops, seeking additional funding, prioritizing and scheduling of projects, employee supervision, preparing statements of work, managing budgets, and completing reports. The Nez Perce Tribe and the Clearwater National Forest (CNF) have been partners in watershed restoration since 1996, which includes sharing funds and resources to complete projects. Each year, project specifics are spelled out in an agreement that is signed by both parties.$00.00%03/01/200802/28/2009
D37081132Produce Progress (Annual) ReportProgress report not requiredAn annual report will not be completed for this contract. Instead, a project level annual report, which covers both the CNF contract and the NPT contract, will be completed by the Nez Perce Tribe under the BPA-NPT contract of this project.$00.00%
E36243185Produce CBFish Status ReportPeriodic Status Reports for BPAThe Contractor shall report on the status of milestones and deliverables on a quarterly basis in Pisces. Additionally, when indicating a deliverable milestone as COMPLETE, the contractor shall provide metrics and the final location (latitude and longitude) prior to submitting the report to the BPA COTR.$00.00%07/01/200802/28/2009
      
$70,000
   

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental compliance documentation submitted to BPA A: 165. Provide environmental compliance information to BPA for projects on Forest Service Lands 05/31/2008 05/31/2008
Road decommissioning completed B: 33. White-White Road Decommissioning 10/31/2008 08/29/2008
FY 09 SOW package and accrual estimate C: 119. Management, Coordination and Communication 01/23/2009 02/28/2009

Viewing of Implementation Metrics
Loading...
Sort Order
WE ID
Work Element Name
Title
Description
Metric ID
Metric
End Fiscal Year
Planned
Actual
Contractor Comments
All Measures
Annual Progress Report Measures
Populations
Viewing of Environmental Metrics Customize
Loading...
WSE ID
WSE Start
WSE End
WE ID
Title
WSE Progress
Study Plan
Protocol
Category
Subcategory
Focus 1
Focus 2
Specific Metric Title

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 33 Decommission Road/Relocate Road
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 33 Decommission Road/Relocate Road

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Provide environmental compliance information to BPA for projects on Forest Service Lands 02/09/2007
B 33 White-White Road Decommissioning 04/03/2007
C 119 Management, Coordination and Communication 02/09/2007
D 132 Progress report not required 02/09/2007